E N D
Safety in Excavation & Blasting operation By Umesh Chandra Swain
EXCAVATION Reference Standard IS 3764 : 1992
Excavation • Excavation. Any man made cut, cavity or depression in the earth’s surface formed by earth.
Excavation Hazards • Soil Collapse • Utilities • Hazardous atmospheres • Adjacent structures • Falls / Falling loads • Access / Egress • Vehicle traffic • Mobile equipment • Water accumulation • Cave-in
Prior to Excavation • Obtain a work permit • Check Ground / Soil condition • Check Ground / Surface Water • Check the Location of Water Table • check Under ground / Overhead utilities • Adjacent buildings • Dynamic load / Traffic
Soil Classification • Type A : • Clay, sandy clay, clay loam • Type B: • Angular gravel (similar to crushed rock), silt, silt loam, sandy loam • Type C: • gravel, sand, loamy sand,Submerged soil or soil from which water is freely seeping; or Submerged rock that is not stable
Preventing Soil Collapse Soil classification (Type a, b, or C) • Sloping • Benching • Placing a shield. • Shoring(Timber / Aluminum shoring • Sheet piling
Simple Sloping • Stable Rock : 900 • Type A - 3/4:1 530 Short term up to 12’ -630 Note :Greater than 20 feet deep shall be designed by a registered professional engineer.
Unsupported Vertically-Sided Lower Portion <8 ft Unsupported Vertically-Sided Lower Portion <12 ft Simple Sloping -Type A Soil
Supported or Shielded Vertically-Sided Lower Portion Simple Sloping -Type A Soil
Simple Sloping • Type B - 1:1 450 • Type C - 1½ :1 340 Note :Greater than 20 feet deep shall be designed by a registered professional engineer.
Benching • Type A • Type B (cohesive soil) • Type C
TimberShoringInstallations REFER TO DESIGN ENGR.
Utilities Underground PERMIT SYSTEM
UNDER GROUND ABOVE GROUND EFFECTS OF UTILITIES
FIRE EXPLOSION EFFECTS OF UTILITIES
UTILITIES PREVENTION • Obtain work permit and get clearances from the concerned • Electricity • Water & Sewage Pipeline • Communication • Oil & Gas Pipe Line • Use Detectors ( for More Reliable)
Water Accumulation • Ground water • Surface water
Surface water accumulation PREVENTION: If excavation work interrupts the natural drainage of surface water • Diversion ditches, • Dykes • other suitable means to prevent surface water • Excavations subject to runoff from heavy rains require an inspection by a competent person to evaluate water accumulation hazards.
Hazardous Atmospheres Never Start Work if, • Oxygen Level less than 19.5 % • Permissible limit of the toxic gases exceeded. • More than 20 % of Lower Explosive Limit. PRECAUTIONS • Ventilation to over come the above said. • Blocking the source, incase of toxic and flammable gases. (Using other effective controls to reduce the level of atmospheric contaminants to acceptable levels)
Adjacent Structures • Ensure structure stability • Shoring • Bracing • Evaluation by Professional
FALLING LOAD • Gravity • Weight of soil pile • Weight of near by structures • Weight of personnel &equipment • Vibration PREVENTION • Never operate a construction equipment within 2.5 m from the edge of the excavation. • Stacking the material 1 Meter away from the edge of the excavation.
Access / Egress • Ladders • Ramps with soil with slope not more than 15o • Stairs cut on earth
Vehicle Traffic Control Measures • Traffic Management Plan • Traffic Control • Traffic Safety Vests • Fencing • Illumination
Traffic Management Plan • Width of the passage. • Radius of curve. • Clearance with the side by objects.
Fencing • Hard Barrication shall be provided, in the fall prone areas and if depth is more • Physical barricades required always • Must be placed 2m away from excavation edge. • Standard fall protection required for vertical falls over 1.3m • Traffic diversions • Pedestrian walkway diversions
Caution Signs Barricades Reflective Cone
ILLUMINATION Temporary Lightings: • Sufficient Area Lighting. • Emergency Lighting with Power back up.
Excavation Inspections • Daily Inspections by Competent Person Start of shift, as needed, following rainstorms or other hazard-increasing event • Possible cave-ins • Protective system failure • Water accumulation • Hazardous atmospheres
Blasting operations • IS 4081 : 1986 • Explosive Act, 1884 • Explosive rules, 1983
What is Blasting • Blasting is the process in which, the high pressure to which the rock is exposed shatters the area and exposes the space beyond that to vast tangential stresses and strains. • The phenomena takes place under the influence of outgoing shock waves which travel in the rock at velocity of 3000-5000 meters per second.
Principle of Rock Blasting • A Blasting operation is constituted of three stages: • Compression: High velocity pressure waves create micro-fractures. • Reflection: Waves bounce back from the free face & convert into tensile & shear waves causing more fracture growth. • Gas Pressure: Large volume of high pressure gas expand the cracks
Hazards • Fly rock. • Misfire. • Fumes. • Dust. • Unintentional charging. • Friction developed during next drilling. • Smoking. • Radio frequency waves. • Lightning. • Static electricity.
Sequence of Operation • Drilling a hole • Inserting a charge, • Stemming (covering the charge with a dense material to prevent dissipation of the explosive force) • Firing (detonator or fuse)
Cross – section of Blasting Hole Detonating Fuse Stemming ( Sand, Clay or Mud ) * * * * * * * * * * Explosive Cartridge Primer Explosive Detonator
Pre-splitting • Row of holes drilled along the final excavation line. • Holes loaded with light charge prior to the main blast causes a fracture. • Fracture generates a discontinuity which minimize the Over-break & produces a smooth finished wall.
Generation of Discontinuity in Pre-splitting • Pre-splitting holes stemmed very lightly. • Used mostly in road cuts and foundation blasts where structural concrete is directly poured against the rock wall.
Explosives • An Explosive is a solid or liquid substance or mixture of substances which change themselves instantaneously into a large volume of gases of high temperature or pressure when a flame, heat or sudden shock is applied to it. • The amount of energy developed per unit of time is of the magnitude of 25000 MW - i.e it exceeds the power of most of world’s present largest power station
Explosives • 13th century Gunpowder used in military purposes • 17th century gunpowder used in mines for blasting • 19th century French Scientist Sobrero prepared NG explosives • Alfred Noble used it in 1st commercial high explosives, dynamite
Classes of Explosives • Low Explosives • High Explosives • Low Explosives Example Gun powder • High Explosives Example Nitroglycerine Dynamite
Types of Explosives • Nitro compound explosives • Nitrate mixture explosives • LOX explosives • SMS explosives • ANFO explosives
Safety Code For Blasting And Related Drilling Operations Container (for quantity up to 5 kg). • Designed insulated container with lid. • Wood - 50 MM thick. • Plastic - 6 MM thick. • No metal parts. • Carrying device –. • Rubber, leather, canvas. • Separate container for Explosives / detonator.
Safety Code For Blasting And Related Drilling Operations Should be clearly marked for: • Mfg name or trade name. • Name of the explosive. • Lot number. • Date of mfg. / Expiry date. EXPLOSIVES – HANDLE WITH CARE
Safety Code For Blasting And Related Drilling Operations • Vehicle. • Licensed driver. • “EXPLOSIVES” lettering on both sides of vehicle and end. • Fitness of all parts. • Explosives & detonators – separate vehicle. • Material to be carried to site in original container. • CO2fire extinguisher kept / driver trained.
Safety Code For Blasting And Related Drilling Operations STORAGE OF EXPLOSIVE (magazine). • Explosives & blasting caps - separate storing. • 8 M all sides - free from vegetation, debris and combustible. • Desensitizing agent used, in case of leakage of nitroglycerine. • Lightning protection in accordance with IS : 2309 & tested once a year.