Provident Kenworth- Apartment for Sale in Hyderabad

Located on the VNR Expressway - Provident Kenworth Rajendranagar, Hyderabad, has easy connectivity with the entire city. This 1 and 2 bhk apartments in Hyderabad are especially favourable for IT professionals working near the Gachbowli and the Hitech City. The greatest advantage is that Metro Rail Service (expected to be complete this year only) will be functioning soon, making travel to and from Provident Kenworth extremely fast and easy<br><br>Tags : Flat for Sale in Hyderabad , Apartment for Sale in Hyderabad , Flat for Sale in Rajendranagar , Apartment for Sale in Rajendranagar , 1 Bhk Flat in R

Download Presentation

Provident Kenworth- Apartment for Sale in Hyderabad

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August2021

  2. Tower1 TOWER STATUS MILESTONES ACHIEVED • Door & Window work in progress • MEP work inprogress. • External painting, False ceiling & bison board work in progress. • Door fixing 120 flatscompleted. • Internal door 108 flats completed. • External 1st paint 90%completed. • SD fixing 120 flatscompleted. • Lift gladding service liftcompleted. • Bison board work 100 flats completed. • Stilt floor IPS work completed. UPCOMING MILESTONES • 1st coat paint complete 120 flats. • External paint 1st coatcomplete. • Bison board & false ceiling100%. • Terrace OTS covering 100%. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  3. Tower2 TOWER STATUS MILESTONES ACHIEVED • External plastering in progress. • Tile dado & flooring in progress. • Verified flooring inprogress. • External primer work in progress. • External plaster completed 70% completed. • Toilet dado & flooring 157 flats completed. • Flooring tile completed 52flats. • 1st coat putty completed 225flats. • 2nd coat putty 205flats. • External primer 40%completed. UPCOMING MILESTONES • External plaster 100%complete. • Waterproofing 100%complete. • Toilet dada 230 flatscomplete. • Floor tile work 180 flatscomplete. • 1st coat putty 100%complete. • 2nd coat putty 100%complete. • External 1st coat Primer 100% complete. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  4. Tower3 TOWER STATUS MILESTONES ACHIEVED • Putty work inprogress. • Tile work inprogress. • Stilt floor materialremoving work inprogress. • External plaster 97% completed. • 1st coat Putty work complete 120 flatscompleted. • 2nd coat putty completed 96flats. • Tile work completed 100flats. • Toilet dado & flooring 106 flats completed. • External primer 90%completed. UPCOMING MILESTONES • External plaster 100%complete. • 1st coat Putty work complete up to 120flats. • 2nd coat putty 120flats. • Tile work complete 120 flats. • External primer 100% complete. • Kitchen counter 50 flatscomplete. • South side staircase floorcomplete. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  5. Tower4 TOWER STATUS MILESTONES ACHIEVED • Door fixing work inprogress. • Lift gladding work inprogress. • Stilt floor columns & basement columnsplastering in progress. • False ceiling work inprogress. • Stilt floor materialremoving work inprogress. • Service lift gladding & passenger lift gladdingcompleted. • Stilt floor Screedcompleted. • Door fixing work 110 flatscompleted. • Bison board work 110 flats & false ceiling work 120 flats completed. • 1st coat paint 10 flats & 2nd coat paint 10 flatscompleted. • UPCOMING MILESTONES • Finishing work willcomplete. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  6. Tower5 TOWER STATUS MILESTONES ACHIEVED • Tile work in progress. • Putty work inprogress. • Kitchen granite inprogress. • Stilt floor Block work in progress. • External primer work in progress. • UPVC work in progress. • Tile work completed 54 flats. • Toilets dado & flooring 41flats. • 2nd Coat putty 85 flatscompleted. • Lift waterproofingcompleted. • External primer 95% completed. • Windows fixing 105 flatscompleted. • Kitchen counter 18 flatscompleted. UPCOMING MILESTONES • Tile work complete 120 flats. • Stilt floor columns plaster & wall plaster complete100%. • 2nd coat Putty work complete 120flats. • Lift Plaster complete100%. • External primer 100%complete. • Kitchen counter 60 flats completed. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  7. Tower6 TOWER STATUS MILESTONES ACHIEVED • Tile work in progress. • Putty work inprogress. • Door fixing work inprogress. • Kitchen granite work in progress. • External painting work in progress. • Tile work completed 85 flats. • Toilet dado & flooring 67 flatscompleted. • Putty completed 120flats. • 2nd coat putty work completed 108flats. • Internal plastering 100%completed. • Service lift gladding workcompleted. • External primer 90%completed. • External 1st painting 60%completed. • IPS concrete workcompleted. UPCOMING MILESTONES • Tile work complete 120 flats. • Putty work complete100%. • Passenger lift gladding workcomplete. • External primer complete100%. • External 1st coat paint complete100%. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  8. Tower12 TOWER STATUS MILESTONES ACHIEVED • External plaster work in progress. • Wall & ceiling 1st Coatputty work inprogress. • External wall Primer work in progress. • Toilet rough plaster work in progress. • Tile marking inprogress. • 1st coat putty completed 90 Flats. • Toilet rough plaster 108 flatscompleted • External wall plaster 95% completed • Toilets & utility white wash 100% completed. • External primer 85%completed. • Basement IPS flooring completed70%. UPCOMING MILESTONES • 1st coat putty completed 120Flats. • Toilet rough plaster 100%complete. • External wall plaster 100% complete. • External primer 100%complete. • Basement IPS flooring 100%complete. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  9. Tower13 TOWER STATUS MILESTONES ACHIEVED • Terrace floor & Waterproofing screed concrete inprogress. • Internal Wall & ceilingplaster in progress. • Toilet waterproofing & screed work inprogress. • Flats ceiling plaster completed 190flats. • Toilet waterproofing completed 100flats. • Toilet screed completed 120flats. • External plastering completed50% • Internal wall plaster completed 160flats. • External wall primer 30%completed. • 1st coat putty 65 flatscompleted. • Terrace waterproofing & concrete 12 flats completed. UPCOMING MILESTONES • Flats ceiling plaster complete100% • Toilet waterproofing complete 150flats. • Toilet screed complete 150flats. • External plastering complete85% • Internal wall plaster complete100%. • 1st coat putty complete 120flats. • Terrace waterproofing complete100%. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 ConstructionUpdates

  10. Site Office : ProvidentKenworth 6-1-33, Inner Ring Rd, Shivrampalli Village, Shivarampally Jagir, Hyderabad, Telangana500052 Regional Office : Provident HousingLimited No.8, Ulsoor Road, Bengaluru- 560042 Tel:080-44555544 Email : crm@providenthousing.com(Subject line – Project name/ unitnumber) Call Us : +91 - 80-67724001 / 1 860 2080000 Web :www.providenthousing.com