Kanakapura Road is one of the green areas in Bengaluru and is becoming a prominent destination for real estate development. Provident Housing has launched Provident Park Square, flats for sale in Kanakapura Road. The residential project is at par with world-class design and RERA registered.<br><br>Tags : Apartments Kanakapura Road , Apartments in Bangalore Kanakapura Road , Ready to Move in Apartments in Kanakapura Road , 3 Bhk Flats for Sale in Kanakapura Road , Buy a Flat in Bangalore Kanakapura Road<br>

Download Presentation

Provident Park Square- Apartments for Sale in Kanakapura Road

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August2021

  2. Tower 4A &4B 4A 4B TOWER STATUS MILESTONES ACHIEVED • 4A terrace water proofing preparation inprogress. • 4A External painting north side in progress. • 4B above terrace OHT wall concretecompleted. • 4B external sealant work in progress. • 4A 14th floor doors fixing completed. • 4A 14th floor Windows fixing completed. • 4A internal painting inprogress. • 4B 9th floor tiles work in progress. • 4B balcony railing 7th floor in progress. • 4A installation of windows/doors up to 14th floor completed. • 4B completion of flooring up to 7th floorcompleted. UPCOMING MILESTONES • 4A - Completion of erection of lifts, common lobbiesand commonstaircases. • 4B - Completion of flooring up to 10thfloor. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  3. Tower 5A &5B 5A 5B TOWER STATUS MILESTONES ACHIEVED • 5A OHT top slab reinforcement in progress. • 5A External sealant works in progress. • 5B Above terrace OHT walls work inprogress. • 5A 9th floor doors fixing in progress. • 5A 14th floor Windows fixing Completed. • 5A internal painting inprogress. • 5B 3rd floor tiles work completed. • 5B water proofing 7th floor in progress. • 5A installation ofexternal windows/doors up to 7th floor completed. • 5B Completion of terrace slab. UPCOMING MILESTONES • 5A installation of external windows/doors up to 10th floor. • 5B completion of flooring up to 3rdfloor. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  4. Tower 3C, 3D & 3E 3C 3E 3D TOWER STATUS MILESTONES ACHIEVED • 3E Above terrace works in progress. • 3C GF shearwalls completed. • 3D GF roof slab shuttering in progress. • 3E internal waterproofing 6th floor in progress. • 3E internal putty works 2nd floor inprogress. • 3E completionof terraceslab. • 3C & 3DCompletion of 1st (first)slab. • UPCOMING MILESTONES • 3E completion of flooring up to 3rd floor. • 3C & 3Dcompletion of 5th (fifth)slab. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  5. Tower 2C, 2D &2E 2C 2E 2D TOWER STATUS MILESTONES ACHIEVED • 2E 8th floor roof slab in progress. • 2C 4th floor roof slab in progress. • 2D 4th floor roof slab in progress. • 2E completion of9th slab. • 2C & 2DCompletion of 5thslab. • UPCOMING MILESTONES • 2E completionof 13thslab. • 2C & 2Dcompletion of 9thslab. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  6. Tower 1B, 1C &1D 1B 1D 1C TOWER STATUS MILESTONES ACHIEVED • 1B Basement roofslab completed. • 1C Basement roofslab completed. • 1D Basement roofslab completed. • 1B, 1C &1D • Completion of1st (first)slab. • UPCOMING MILESTONES • 1B, 1C &1D • completion of5th (fifth)slab. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  7. OtherActivities Clubhouse TOWER STATUS • Clubhouse internal block work & electrical works inprogress. • STP above truss work and internal water proofing inprogress. • UG Sump 2 excavation inprogress. • Podium pour1 concrete complete & pour2 works inprogress. Actual sitephotograph PROGRESSTIMELINE April21 May21 June21 July21 August21 ConstructionUpdates

  8. Site Office : ProvidentParksquare Judicial Layout, Kanakapura Rd, Bengaluru, Karnataka560062 Regional Office : Provident HousingLimited No.8, Ulsoor Road, Bengaluru- 560042 Tel:080-44555544 Email : crm@providenthousing.com(Subject line – Project name/ unitnumber) Call Us : +91 - 80-67724001 / 1 860 2080000 Web :www.providenthousing.com RERA Registration Number: RERA Nos. - Phase 1 : PRM/KA/RERA/1251/310/PR/180217/002476 Phase 2 :PRM/KA/RERA/1251/310/PR/180507/001648 Phase 3 : PRM/KA/RERA/1251/310/PR/180507/001671 Phase 4 -PRM/KA/RERA/1251/310/PR/190129/002307