1 / 32

Managing and Planning Data Center Implementation

Managing and Planning Data Center Implementation. Vickie Cunderla, Janet Wilson, Chris Jacobson Management Track M-28-2 May 8, 2007. Introduction. Data Center Coordination for R6 – Vickie GIS Library Migration – Janet Local unit lessons learned – Chris * Questions at the end *.

Rita
Download Presentation

Managing and Planning Data Center Implementation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing and Planning Data Center Implementation Vickie Cunderla, Janet Wilson, Chris Jacobson Management Track M-28-2 May 8, 2007

  2. Introduction • Data Center Coordination for R6 – Vickie • GIS Library Migration – Janet • Local unit lessons learned – Chris * Questions at the end *

  3. R6DRM Leadership Team

  4. 5 Customer Service Areas

  5. Who is involved? • IRM – Information Resources Management • ISO – Information Solutions Organization • Region 6 DRM – Region 6 Data Resources Management

  6. Who is involved • Region is a partner with IRM and ISO • Primary ISO contact is Jerry Black • Primary IRM contact is Martin Prather • Additional contacts related to each components • Regional Executive Lead • Single point of contact with IRM/ISO • Manages regional resources, priorities, and decisions. • Regional Technical Contact • Deals with day-to-day technical details

  7. Seven Major Task Areas • Communications • Facilities Preparation • Application Migration • Data Migration • Web Migration • User Preparation • GIS Library Migration

  8. Communications • Communicate with: • Regional and local leadership • User community • Other key groups in the Data Center Migration • What to communicate • When the migration will happen • How to prepare for the migration • User training

  9. Facilities Preparation • Primarily focused on Site Local Servers • Requirements • Rack space, UPS, Electrical upgrades, potential HVAC upgrade, facilities • Requires coordination between: • Regional facilities engineers • Regional contracting • ISO facilities team • Local facilities engineers

  10. Application Migration • National Application Migration Project • Implemented by IRM in 2005 • Inventory of all local, regional, and national applications • Oracle forms, MS Access, Other • Identify application sponsors • Can be started now • Decide • If each application is still needed • Convert as-is or re-engineer

  11. Data Migration • How do we conduct business • New File Structure • Enterprise file structure appears as one system • Allows read access to most files by everyone • Exceptions for Human Capital Management, Fiscal, Law Enforcement • File re-engineering • Coordinate with ‘site contacts’ • Document what goes where and who gets access

  12. Web Migration • Migration of all fsweb sites to new web server • Minor work needs to be done to web site • Mostly drag-and-drop, test first • Coordinate with ISO • Done separately from file re-engineering • Can be done independently of other tasks

  13. User Preparation • Timing of user communication is crucial • Active Directory is the starting point • Inventory of who belongs to which organization/program area • Schedule training just before data migration • 2-3 weeks max • Performed virtually by ISO using web meeting

  14. Summary of Region 6 DRM Resources • Regional Executive Lead • Regional Technical Lead • Communications Lead • Application Lead • 2 application developers • GIS Library Lead • 5 GIS Analysts • File Structure Lead • 4 Data Services Analysts

  15. GIS Library Migration • Goal: Develop a consistent, and standard process to migrate GIS library data for 18 forests to the Portland Data Center • Charted team October 2005 • Representation from each CSA (6 members)

  16. GIS Library Migration Goal: Develop a consistent, and standard process to migrate GIS library data for 18 forests to the Portland Data Center. Focus areas: • Implement the National File Structure • Migrate Forest extent data • fsfiles/ref/library/gis • Excluded other extents • Migrate coverage based data • Excluded remote sensing imagery processed data • Implement Region-wide permissions • Implement common projection • Recommend Site Local Services replications

  17. Extents: (admin, non-admin, provincial extents) Number of Records in database: Number of ‘other extent’ records not addressed: Number of ‘forest extent’ records we focused on: Number of Legacy data set names: Number of Data Center standard names: Number of final reports posted on web: Number of working reports used for peer review: Number of themes to help categorize: 24 9000 4700 4300 2650 1006 72 25 20 GIS Library Inventory Statistics

  18. National File Structure

  19. GIS Library Permission’s • T:/library/gis/r06/ vs. • T:/library/gis/r06/<forest_extent>/ vs. • T:/library/gis/r06/<forest_extent>/<district>

  20. GIS Library Migration Milestones: • Inventoried all coverage-based data sets • Established naming convention rules • Established standard naming conventions • Generated inventory (cross-walk) reports • Developed Data Maintenance procedures • Established group permission’s • Coordinated with the National File Structure team

  21. GIS Library Web Site: Documentation found at: http://fsweb.wo.fs.fed.us/irm/data-centers/pdx/

  22. GIS Library Migration Take home message - start now • Things to think about: • Forest-wide or Region-wide migration effort? • Is your Metadata ready to support the effort? • Will you migrate file-based data? • Will you develop a database for your inventory? • Are you familiar with the eGIS Nat’l File structure? • Will you develop DC Naming Convention rules? • Will you develop a DC Data Maintenance plan? • How will you implement permission’s?

  23. GIS Library Migration Lessons Learned • Metadata is a requirement • Naming convention rules is a requirement • Peer review is a requirement • Inventory Database was a requirement • Knowledge of the eGIS file structure • More integration with SDE team • Chartered team scope was too narrow

  24. Local Unit – Who Were They? • Deschutes NF • Fremont-Winema NFs • Ochoco NF • Western Wildland Environment Threat Assessment Center – PNW Station • Redmond Air Center • R6 Detached Employees • WO Detached Employees (approximately 1000 users)

  25. Local Unit - Advantages of Migration • “Anywhere, Anytime” access to Forest Service data and information • Replaces failing hardware • Reduces maintenance costs • Allows work to be shared between units • Creates one look and feel for users • Leverages skills and tool development

  26. Local Unit - Preparations Before Migration • Provided centralized GIS Library Migration • Assisted with hardware deployment logistics • Retrieved and learned tools to assist transition • Provided group training opportunities • Emphasized important messages for users

  27. Local Unit – Migration Assistance • DRM team at most locations across CSA for on-site help for 2 days • On-site help team connected by Sametime instant messaging for 2 days • Helped users describe problem to Help Desk • Assisted users to find documentation

  28. Local Unit – Migration Day Difficulties • T: S: & P: drives not mapped - Domain Name Services down due to power outage • “Where did my data go?” • Confusion between T: and S: drives • Users didn’t completely migrate to Active Directory • Users didn’t do training before the move • Confusion about Library folder showing in several locations of directory • Needed to know process for getting access to directories

  29. Local Unit - After the Big Day • Citrix was not ready for prime time but the incredible speed will knock your socks off.. • SLS performance less than expected at some sites, team working to find resolution • Found SDE was too slow over WAN for desktop users so exported to pGDB • More coordination required when Library managed by extents

  30. Local Unit - Lessons Learned • Consider the economy of scale when assigning work • Minimize the amount of changes at migration i.e. standard projection, naming conventions, etc. • Implement solutions before migration if possible i.e. layer files, GI, relative pathways, etc.

  31. Questions?