An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NAD/SAD REGIONAL DREDGING MEETING/WEDA US Army Corps of Engineers Mobile District MOBILE DISTRICT FY 2007 DREDGING PROGRAM

  2. Mobile District Navigation Projects 7 Deep Water Harbors 22 Shallow Draft 5 Inland Waterways 2200 Miles of Inland Waters TN Tenn-Tom Waterway Black Warrior River GA MS AL Chattahoochee River Tombigbee River Flint River Alabama River GIWW Apalachicola River Gulfport FL Port St. Joe Pascagoula Panama City Bayou La Batre Pensacola Mobile

  3. FY06 FY07 FY08 SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT Scheduled FY07 Dredging Work in Mobile District Hopper Dredge Maintenance Dredging Mobile Hbr Bay/Bar (Rental) Manson/ Glenn Edwards Mobile Hbr Bay/Bar (Rental) $4M IDIQ B.O. OCT 06 Mobile Hbr Bay/Bar (Rental) $4M IDIQ B.O. JAN 07 Mobile Hbr Bay/Bar (Rental) $4M IDIQ B.O. Jun 07 Mobile Hbr Bay/Bar (Rental) $4M IDIQ (Contingency) Used for emergency work, to be opened by amendment Mobile Hbr Bay/Bar (Rental) $4M IDIQ (Contingency) Used for emergency work, to be opened by amendment Pascagoula Bar (Rental) 1MCY IDIQ B.O. MAR 07 Panama City Beach Nourishment Unit Price 500KCY B.O. FEB 07

  4. Mobile Harbor Channel Type of Work: Maintenance Depth: 47’ Bar and 45’ Bay Width: 600’/400’ Length: 42 Miles Quantity: 1.0/2.25 Mcy Type of Material: Sand, Silt and Clay Placement Area: Ocean D/A Distance to Placement Area:30 Miles Type of Equipment: Hopper Small Business Set Aside: No Last Dredged: 2006 Contract Amount: $1,000,000-$5,000,000 Schedule: Continuous

  5. Pascagoula Bar Channel Type of Work: Maintenance Depth: 44’ Width: 450’ Length: 6.2 Miles Quantity: 1.0 Mcy Type of Material: Sand, Silt and Clay Placement Area: Ocean D/A Distance to Placement Area: 2-3 Miles Type of Equipment: Hopper Small Business Set Aside: No Last Dredged: 2004 Contract Amount: $1,000,000-$5,000,000 Schedule: Begin late March – End early June

  6. FY 06 FY07 FY08 SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT Scheduled FY07 Dredging Work in Mobile District Hydraulic Pipeline Dredge Maintenance Dredging Pascagoula Sound (Rental) Mike Hooks Missouri H 27” 2M CY Gulfport Sound Channel (Rental) 1.5M CY Mobile River (Rental) 800KCY IDIQ B.O. May 07 Pascagoula Sound (Rental) 2MCY IDIQ B.O. MAY 07 BWT/GIWW (Rental) $15M IDIQ B.O. FEB 07 Tenn-Tom/ Ala River (Rental) $10M IDIQ B.O. FEB 07 Harrison County Beaches Unit Price 800KCY B.O. NOV 06

  7. Gulfport Sound Channel Type of Work: Maintenance Depth: 36’ Width: 220’ Length: 12 Miles Quantity: 1.5 Mcy Type of Material: Silt, Clay and Fluff Placement Area: Open Water D/A Distance to Placement Area: 5-10 K Feet Type of Equipment: Large Cutterhead Small Business Set Aside: No Last Dredged: 2006 Contract Amount: $1,000,000-$5,000,000 Schedule: Begin early February – End mid May

  8. On-Going Dredging Work inMobile District

  9. Black Warrior and Tombigbee Rivers, Alabama River Tennessee-Tombigbee Waterway, GIWW Type of Work: Maintenance Depth: 9’ – 12’ Width: Various widths Length: Various Lengths Quantity: Rental Type of Material: Sand/Gravel Placement Area: Upland and Within Banks Distance to Placement Area: Various Distances Type of Equipment: 18” - 24” Cutterhead Last Dredged: 2006 Contract Amount: $1,000,000 - $5,000,000 Schedule: Summer 2007 Tenn-Tom Waterway