1 / 29

Equipment Costing CAPEX

Equipment Costing CAPEX. Sieder-Chapter 16 Review CH EN 5253 Terry A. Ring. Design I Coverage. Time Value of Money Capital Costs Operating Costs Profitability Analysis Reading Materials. Cost Estimate Methods. Order of Magnitude Estimate Method of Hill Marshall Swift for I/Ibase

aidac
Download Presentation

Equipment Costing CAPEX

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Equipment CostingCAPEX Sieder-Chapter 16 Review CH EN 5253 Terry A. Ring

  2. Design I Coverage • Time Value of Money • Capital Costs • Operating Costs • Profitability Analysis • Reading Materials

  3. Cost Estimate Methods • Order of Magnitude Estimate • Method of Hill • Marshall Swift for I/Ibase • Six Tenths Rule for Production Capacity • CTCI-2 (I)=CTCI-1 (Ibase)*(I/Ibase)* (Capacity2/Capacity1)0.6 • Study Estimate (±35%) • Method of Lang • CTCI=1.05*fL-TCI ∑ (Ii/Ibase-i) Cp-i • Lang factors for different types of Plants • Solids -3.10, Solids&Fluids 3.62, Fluids 4.73 • Sum over all major equipment • Preliminary Estimate (±20%) – use this method in CHEN 5253 • Method of Guthrie • Bare module cost, CBM=Cp-base(I/Ibase)[FBM+(FdFpFm-1)] • d= design factor, p = pressure factor, m =materials factor • Quote Estimate

  4. 6/10th scale up/down Factor • Used for scaling the total capital cost for a chemical plant of a different size • Cost2/Cost1 = (Capacity2/Capacity1)0.6 • 0.6 - Accounts for economy-of-scale

  5. Accounting for Inflation • Cost to purchase = Base Cost*(I/Ibase) • Base Cost, CB, = Historical price at Io • I is a Cost Index at present time • Chemical Engineering, CE, Plant Cost Index • Ibase=567 (<2013>) for your equations in Sieder’s 4th Ed. • Marshall and Swift (MS) Equipment Cost Index • Nelson-Farrar (NF) Refinery Construction Cost Index • Engineering News-Record (ENR) Construction Cost Index • Cp(I) = Cp(Ibase)*(I/Ibase) • Cp(Ibase)=FT*Fm*Cbase(Ibase) (Hill Method) FT= Type factor Fm= Materials factor

  6. Cost Estimate Methods • Order of Magnitude Estimate • Method of Hill • Marshall Swift for I/Ibase • Six Tenths Rule for Production Capacity • CTCI-2 (I)=CTCI-1 (Ibase)*(I/Ibase)* (Capacity2/Capacity1)0.6 • Study Estimate (±35%) • Method of Lang • CTCI=1.05*fL-TCI ∑ (Ii/Ibase-i) Cp-i • Lang factors for different types of Plants • Solids -3.10, Solids&Fluids 3.62, Fluids 4.73 • Sum over all major equipment • Preliminary Estimate (±20%) – use this method in CHEN 5253 • Method of Guthrie • CTCI=(Ii/Ibase-i) ∑ Cp-i • Bare module cost, Cp-BM=Cp-base[FBM+(FdFpFm-1)] • d= design factor, p = pressure factor, m =materials factor • Quote Estimate

  7. Purchase Costs for Equipment • Size Factor, S, depends on type of equipment • Cp(Ibase)= A + b* (S)n • Ibase= 567 (2013 average) • Cp(Ibase)=exp(Ao+A1[lnS]+A2[lnS]2+…) • Ibase = 567 (2013 average)

  8. Construction in Carbon Steel

  9. Installation Factors

  10. Materials Costs The materials factor is different for different pieces of equipment!

  11. Compressors • Compressor types (Ibase=394, equations from 3rd Edition of book) • Centrifugal, CB=exp{7.2223+0.80[ln(PC)]} • Reciprocating, CB=exp{7.6084+0.80[ln(PC)]} • Screw, CB=exp{7.7661+0.7243[ln(PC)]} • Size factor is the power consumed, PC=PB/ηC • CP=FDriveFMatCB • FDrive =1 (electric motor), 1.15 (steam), 1.25 (gas turbine) • FMat = 1.0 Carbon steel, 2.5 SS, 5.0 Nickel Alloy • CBM=FBM*∑CP • FBM = 2.15 Fully Installed Cost

  12. Heat Exchangers • Types of Heat exchangers (Ibase=394, 3rd Edition of book) • Floating Head, CB=exp{11.667-0.8709[ln(A)]+0.09005[ln(A)]2} • Fixed Head, CB=exp{11.0545-0.9228[ln(A)]+0.09861[ln(A)]2} • U-tube, CB=exp{11.147-0.9186[ln(A)]+0.09790[ln(A)]2} • Kettle, CB=exp{11.967-0.8709[ln(A)]+0.09005[ln(A)]2} • Thermosiphon, CB= • Double pipe, CB=exp{7.1248-0.16[ln(A)]} • Size Factor is HX area, A, for heat transfer • CP=FpFMatFLCB • Pressure Factor, Fp= 0.9803+0.018(P(psig)/100)+0.0017(P(psig)/100)2 • Not for double pipe • Materials Factor, Fmat=a+(A/100)b, a & b from Table 16.25 • a≥1.0 note error in Table • Tube Length Factor FL= 1.25 for 8 ft, 1.0 for 20 ft. on a sliding scale • CBM = FBM*CP, FBM=3.17 (S&T), 1.80 (DP), 2.17 (Fin/Fan)

  13. Fired Heaters • Size Factor is the heat duty, Q • CB=exp{0.08505+0.766[ln(Q)]} (Ibase=394) • CP=FPFMatCB • FP=0.986-0.0035(P(psig)\500)+0.0175(P/500)2 • Fmat=1.4 Cr-Mo alloy steel, 1.7 for stainless steel • CBM = FBM*CP, FBM=2.19

  14. Pressure Vessels • Storage Tanks • Distillation Towers • Tray • Packed • Absorber Towers • Stripping Towers

  15. Pressure Vessels • Sizing Factor is the weight of steel, W • Horizontal Vessels, 1,000<W<920,00 lb CB=exp{8.717-0.2330[ln(W)]+0.4333[ln(W)]2} (Ibase=394, 3rd Edition of Book) • Vertical Vessels, 4,200<W<1,000,00 lb CB=exp{6.775-0.18255[ln(W)]+0.02297[ln(W)]2} (Ibase=394) • Add Platform Costs, • Horizontal, 3<Di<12 ft • CPL=1580(Di)0.20294 (Ibase=394) • Vertical, 3<Di<21 ft • CPL=258.1(Di)0.7396(L)0.70684 (Ibase=394) • Weight, W=π(Di+ts)(L+0.8Di)tsρs • C=FMCB+CPL • FM= materials factor see Table 16.26 • Installation, etc, FBM=4.16 (V), 3.05 (H) • CBM=FBM*∑CP

  16. Hoop Stress Calc for thickness, ts • Design Pressure is function of operating pressure, Po • For Po> 1,000psig use Pd=1.1Po • For Po< 1,000psig but not for vacuum Pd=exp{0.60608+0.91615[ln(Po)]+0.0015655[ln(Po)]2} • Thickness (Hoop Stress Calculation) • ts= PdDi/(2SE-1.2 Pd) • S = max allowable stress for steel is f(T) see Book p.466. • E = weld efficiency (fraction) • Ts is Minimum wall thickness for given diameters • May add extra thickness for wind stresses, corrosion allowance • Different calculation for vacuum vessels! • Also account for leakage when vacuum vessel is used

  17. Distillation Towers • Pressure vessel with plates or packing and additional nozzels and manholes • Tray Cost CT=NTFNTFTTFTMCBT • NT= no. trays • FNT= 1 for NT>20 otherwise FNT=2.25/(1.0414NT) • FTT = tray type, 1.0 sieve, 1.87 bubble cap • FTM= Materials, f(D) • Carbon Steel FTM=1.0 • 316 SS FTM=1.401+0.0788 Di • Installation, etc, FBM=4.16 • CT_BM=FBM*∑CT

  18. Packed Distillation Column • Pressure vessel with platforms plus packing • Platforms see Eq. (16.58) • CPL=341 (Di)0.63316(L)0.80161 • Packing Cost basis is volume of packing, VP • C=VpCPK+CDR • CPK= is installed cost per unit volume • Distributors cost, CDR

  19. Absorbers/Strippers • Pressure Vessel • plus platforms • plus packing and distributors • Separate costs for blowers • Separate cost for pumps • Separate costs for motors • On blowers • On mixers • On pumps

  20. Plant Location Factor FISF From T&S Book

  21. Do Not Forget Utility Plants

  22. Total Capital Investment

  23. Conclusions • 0.6th rule • Factored Estimate of Major Equipment • Installation Factor • Peripheral equipment, foundations, piping, etc • Biggest Mistakes • Forget Utility Plants • No Off Sites • No Electrical Substation • No Natural Gas Connection • Neglecting Major Equipment

More Related