1 / 14

Developing a Decommissioning Acquisition Strategy for 2014-26

Developing a Decommissioning Acquisition Strategy for 2014-26. Paul Foster, Decommissioning Director Rob Harries-Harris Contract Officer, Commercial Directorate. Date: March 2013. Agenda. Background Principles Underpinning the Future Model Enablers. 3. Orientation - Where are we now?.

albin
Download Presentation

Developing a Decommissioning Acquisition Strategy for 2014-26

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Developing a Decommissioning Acquisition Strategy for 2014-26 Paul Foster, Decommissioning Director Rob Harries-Harris Contract Officer, Commercial Directorate Date: March 2013

  2. Agenda • Background • Principles Underpinning the Future Model • Enablers 3

  3. Orientation - Where are we now? • The Sellafield Plan • an accurate and realistic picture of the state the site is in • sets out what we are doing to reduce hazard, with milestones and governance in place to enable the NDA to monitor our progress and hold us to account • risks to the plan remain but we are currently on target to deliver decommissioning milestones 4

  4. Key Deliverables 2014/15 to 2025/26 • First generation magnox storage pond • sludge retrievals begin in 2014/15, export of fuel and skips in 2015/16 • bulk desludging complete by 2018/19 • Pile fuel storage pond • bulk desludging and metal fuel export complete in 2014/15 • local sludge treatment plant export complete 2017/18 • Pile fuel cladding silo • retrievals begin in 2017/18 • Magnox swarf storage silo • retrievals targeted to start 2016/17* • residuals removal to begin no later than 2023/24* • Site remediation and decommissioning • Ongoing hazard reduction and decommissioning across SRDP portfolio throughout contract term Source: Sellafield Plan Aug 2011 * subject to confirmation

  5. Areas for Improvement • Public Accounts Committee Concerns: • Planning and schedule adherence • Programme and project management capabilities • Collaborative working to package resources • Robust performance management • Other bodies, including NDA: • Identify SL’s historical contracting model as a priority development area • some weakness in capacity and capability of supply chain • SL does not always strategically think through and establish a model for core and non core capability • SL does not always adopt a strategy for best value and performance (including schedule assurance) maximising available supply chain capability and capacity 6

  6. ... To • Longer contracts • Focus on benefits • Built in quality • Benchmarked costs • Long term vision • Develop resources • Collaborative • OUTCOME • Accelerated hazard reduction • Fit for purpose assets • Access to resources • Economic operations • From … • Short term contracts • Price driven • Control vs quality • Mini-competitions • Short term plans • Itinerant workforce • Inefficient • Ineffective • Adversarial Our Challenge: Clear focus on outcomes

  7. Engagement to Develop and Implement the Strategy • 18-24 Month Engagement Process begins today • Next 6 months will be vital • SL commitment to engage constructively with Supply Chain at all levels • Your contributions are invited • Early contractor involvement in programme and project cycles 8

  8. Strategic Context UK & Local Government NDA Commercial Supply Chain OJEU, etc. SLCs 22 & 35 Over-Arching Acquisition Strategy Special Arrangements Technical R&D and Strategy Decommissioning Acquisition Strategy FGMSP PFSP MSSS PFSS W’scale SR&DP DSA DFA Benefits Learning From Experience Innovation MDSW Major Projects ISA Infrastructure Production Operations

  9. Decommissioning Programme Management FGMSP PFSP MSSS PFSS W’scale SR&DP Make v Buy Decomm Delivery 4P/Major Projects Current Arrangements DSA ISA MDSW/Other Simplified Engagement Structure

  10. Effective Planning at All Stages Reactive Work Increase the Proportion of Planned Work Over Time Planned Work

  11. Collaboration/Sharing Enablers • Share Information • Share Risks not Responsibilities • Share Benefits • Keep savings on at risk elements • Share savings on variable cost elements • Innovations benefit client and innovators • Align objectives through strong incentives 12

  12. Supply Chain Assurance • SL is Tier 1 contractor and must manage the performance of its supply chain • This requires visibility, oversight and governance of Tiers 2/3/4 performance: • Safety, Health and Environmental • Time, Cost, Quality • Wider government agenda, SME and Socio-Economic issues • Desired Outcomes • Accelerated hazard reduction • Fit for purpose assets • Access to resources • Economic operations 13

  13. The Opportunity • Longevity • A programme of work lasting up to 10 years • Scale • up to £700m of work between 2014/15 and 2025/26 14

More Related