1. The Ormen Lange Offshore Gas Projecton the Norwegian Continental Shelf Implementation of Systematic Management WorkProcesses when managing Deep water Projects Senior Vice President Bengt Lie Hansen, Norsk Hydro
Chairman of the Ormen Lange Unit Committee
The World Petroleum Conference
Rio de Janeiro, September 1-5, 2002
3. Norsk Hydro ASA – Operating revenues 2nd quarter 2002
5. Features
6. Facts
7. Key Project Milestones
8. Key Development Challenges
9. Demand for Gas in UK
10. Gas Supply and Demand in Europe
11. Possible Gas Suppliers to Europe
12. Ormen Lange provides new significant gas transport capacity:
13. The Top Reservoir Structural Depth Map
14. The Storegga Slide
15. Local Topography
17. Concept Selection Late 2002
18. Gas Treatment Terminal, Nyhamna
20. Concept Selection Late 2002
21. Full Processing – and Export Offshore Platform
22. Concept Selection Late 2002
23. Concept Selection Late 2002
24. Concept Selection Late 2002
25. Key Project Management Processes
26. Governance Process
27. Governance Process
28. Governance Process
29. Governance Process
30. Sweeping statment
31. Selection Processes
32. Concept Selection
33. Selection Processes
34. Selection Processes
35. Risk Management
36. Risk Management
38. Key Challenges Ahead Verify slide stability
Establish Market and Transportation Strategy in a new commercial environment
Select Ormen Lange Development Conceptin 2002
Submit Plan for Development and Operationto the Authorities autumn 2003
Select and implement Project Execution & Procurement Strategy
39. Thank you for your attention