RHIC Run 9: Polarized Proton Physics Achievements

A summary of the RHIC Run 9 timeline and key milestones, including the cool down, beam injection, ramp development, and successful collisions at sqrt(s) = 500 GeV. Also, highlights of the physics goals achieved in terms of luminosity and polarization for PHENIX and STAR experiments.

amorales
Download Presentation

RHIC Run 9: Polarized Proton Physics Achievements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Run 9 polarized proton Log • 9 Jan begin 45 degree cool down from room temp (3 MW-NEW) • 2 Feb, Cool-down to 4.5 degrees begins • 5 Feb, Blue ring cold but still stabilizing • 7 Feb, beam injected into Blue ring, • 8 Feb, Yellow cold but still stabilizing • 9 Feb, 2 week “Setup” mode begins(0.5 weeks early) • 13 Feb, Beam injected into Yellow ring • 14 Feb, STAR magnet on, ramp development begins • 17 Feb Nov, First collisions @ s = 500 GeV (2.3 weeks into run – a record!) • 24 Feb, “Ramp-Up” mode begins, overnight stores for experiments • 6 Mar, Machine in “Physics” mode, integrated lumi begins • 16 Mar, Spin rotator ramps established, longitudal polarization available • 17 Mar Experiments in Physics mode • 13 April (1200), end s = 500 GeV physics (3.9 weeks), begin last s = 500 GeV beam development followed by new low level RF setup • 15 April (0800), Maintenance and s = 200 GeV ramp setup • 15 April (2100), begin setup with beam for s = 200 GeV • 20 April (2341), s = 200 GeV physics begins (8 days early) with further ramp-up • 21 April (1802), PHENIX physics begins • 23 April , STAR physics begins • 29 June (0800), end s = 200 GeV main physics run (10 weeks) • 29 June (0800), setup for pp2pp at STAR run begins, PHENIX remains on • 30 June (0009), pp2pp Physics on but beam tune-up continues • 4 July (1000), pp2pp ends (0.6 weeks), beam studies at s = 500 GeV begin • 6 July (1000), RHIC beam studies end, cryo warmup begins • 8 Jul, cryo warm-up ~complete, 22.3 weeks cryo operation

  2. Run 9 s = 200 GeV Physics Goals • PHENIX (revised 5/19/09) • 65 pb-1 delivered, ~25 pb-1 recorded • 60% polarization, quality factor is P4L • FOM = 65 x (0.60)4 = 8.4 pb-1 delivered • STAR • 100 pb-1 delivered, ~50 pb-1 recorded • ~60% polarization, quality factor is P4L • FOM = 100 x (0.6)4 = 13 pb-1 delivered

  3. ~2.3 pb-1/day ~1.1 pb-1/day

  4. Blue Jet weighted average = 55.4 ± 0.5 Yellow Jet weighted average = 54.9 ± 0.5