1 / 22

Update on the North Carolina Transmission Planning Collaborative

Update on the North Carolina Transmission Planning Collaborative. January 30, 2007. For the North Carolina Utilities Commission and the North Carolina Public Staff. Purpose of NCTPC.

andres
Download Presentation

Update on the North Carolina Transmission Planning Collaborative

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on the North CarolinaTransmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public Staff

  2. Purpose of NCTPC Provide the Participants and other stakeholders an opportunity to participate in the transmission planning process Preserve the integrity of the current reliability and least-cost planning processes Expand the transmission planning process to include analysis of increasing transmission access to supply resources inside and outside IOU control areas Develop a single coordinated transmission plan for the Participants in North Carolina that includes reliability and enhanced transmission access considerations while appropriately balancing costs, benefits, and risks associated with the use of transmission and generation resources.

  3. Benefits of the Process • Insight into the neighboring system’s modeling approaches, including resource assumptions, contingencies evaluated and system dispatch assumptions; • Higher confidence in and understanding of data provided by all participants, including more detailed and timely information shared; • Improved understanding of the neighboring transmission system, including its strengths and weaknesses and the relationship of impacts between the two transmission systems;

  4. Benefits of the Process • Shared technical and planning expertise that resulted in improved modeling, more comprehensive evaluation of the impact of generation and transmission contingencies, and consideration of more extensive sets of solutions; and • More comprehensive approach to developing solutions to address not only reliability, but also to increase access to alternative resource supply options for LSEs.

  5. Organizational Structure Oversight / Steering Committee (OSC) Planning Working Group (PWG) Transmission Advisory Group (TAG) Independent Third Party (ITP)

  6. Reliability Planning PWG coordinates the study analysis, identifies reliability problems, develops solutions with estimates of costs and schedules PWG evaluates reliability problems and current transmission upgrade plans Participants and TAG review the reliability study results PWG develops and the OSC approves the reliability study scope OSC selects reliability and enhanced access solutions; checks for improved reliability through enhanced access solutions OSC creates final draft Collaborative Plan Feedback and Iterative Studies Participants and TAG recommend scenarios and interfaces. The OSC selects interface and scenario studies for analysis PWG develops and the OSC approves the enhanced access study scope PWG coordinates the study analysis, identifies access problems, develops solutions with estimates of costs and schedules Participants and TAG review the enhanced access study results TAG feedback on final draft Collaborative Plan OSC approves final Collaborative Plan Enhanced Transmission Access Planning Participants’ resource planning processes

  7. Reliability Planning Study • The Scope of the Reliability Planning Study included a base reliability analysis as well as analysis of potential resource supply options • The purpose of the base reliability study was to evaluate the transmission system’s ability to meet load growth projected for 2011 through 2016 with the Participants’ planned Designated Network Resources (“DNRs”) • The purpose of the resource supply analysis was to evaluate transmission system impacts for various resource supply options to meet future native load requirements.

  8. Enhanced Transmission Access Planning • The ETAP Process evaluates the means to increase transmission access for LSEs in North Carolina to potential network resources inside and outside the control areas of the IOUs. • The ETAP Process begins with the Participants and TAG members proposing scenarios and interfaces to be studied. • The final results of the ETAP Process include the estimated costs and schedules to provide the increase transmission capabilities. The results are reviewed with the TAG. • No requests for Enhanced Transmission Access Planning were received in 2006. • Parties can now make proposals for 2007.

  9. Overview of the Study Process • Assumptions Selected • Study Criteria Established • Models and Cases Developed • Study Methodologies Selected • Technical Analysis Performed • Problems Identified and Solutions Developed • Collaborative Plan Projects Selected • Study Report Prepared

  10. Summary of 2006 Collaborative Plan • Comprised of 16 Duke and Progress Projects • Only projects with projected cost of $10 million or more are listed • Details listed in Appendix B & C of report • List will be updated on an ongoing basis

  11. Phase Angle Issue on Richmond-Newport 500kV Tie • This 500 kV interconnection is approximately 80 miles long and carries large amounts of power during high import conditions • Closing the line with phase angles greater than 30 degrees creates an unacceptable sudden change of power on the generating units in the electrical vicinity • PWG brainstormed potential solutions • Progress hired consultant to assist in researching available technologies • Progress has added 500 kV series reactors at Richmond 500 kV Sub to the Plan

  12. Projects Identified through the Collaborative Process • Add a third Wake 500/230 kV transformer • Construct Duke/Progress 230 kV line • Construct new Progress 230 kV line

  13. Add 3 Project Detail Sheets and 3 Map Inserts Here

  14. Evaluate current reliability problems and transmission upgrade plans • Perform analysis, identify problems, and develop solutions • Review Reliability Study Results Enhanced Access Planning Process • Propose and select enhanced access scenarios and interface • Perform analysis, identify problems, and develop solutions • Review Enhanced Access Study Results • Combine Reliability and Enhanced Results • OSC publishes DRAFT Plan • TAG review and comment 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Reliability Planning Process Coordinated Plan Development Coordinated Plan Development TAG Meetings

  15. Appendix

  16. Key Assumptions • Study Year and Planning Horizon • Used 2011 Summer for Duke – Progress East • Used 2010/11 Winter for Duke-Progress West • The Plan addresses a 10 year planning horizon through 2016 • Network Modeling • Included projected transmission and generation • Included Cliffside (Duke), Anson and Richmond (NCEMC), and Wayne Co. (Progress) future generation • Interchange and Generation Dispatch • Each Participant provided resource dispatch order for its Designation Network Resources • Transmission Reliability Margin (TRM) was modeled for Progress import cases

  17. Major Projects from Base Analysis • Richmond 500 kV Substation, add 500 kV series reactors • Durham 500 kV Substation, the Mayo-Wake 500 kV line will be looped in and one new 500/230 kV transformer bank will be installed • Construct Cape Fear-Siler City 230 kV line • Rockingham-West End 230 kV line, construct the Wadesboro tap line and the new Rockingham-West End 230 kV East line projects • Construct Asheville-Enka 230 kV line and the install a new 230/115 kV transformer establishing 230 kV at the Enka 115 kV Substation • Increasing the 500/230 kV transformer capacity at the Antioch Substation • Bundling of the London Creek (Riverview Switching Station to Peach Valley Tie) 230 kV line.

  18. Insert 8 project detail and 7 map insert sheets here (2 Duke map inserts are already here, 2 Progress projects will share a single map insert)

  19. Increase Antioch 500/230 kV Transformer Capacity

  20. Bundle London Creek (Riverview to Peach Valley) 230 kV Lines

  21. Resource Supply Option Study Results

  22. Enhanced Transmission Access Planning • TAG Responses – Due by February 14, 2007 • PWG reviews all proposed scenarios / interfaces and provides OSC a recommendation on the Enhanced Transmission Access Options for analysis in 2007 • OSC to provide TAG feedback by end of March 2007

More Related