1 / 72

What is Cost and Project Cost Management?

What is Cost and Project Cost Management?. Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange Costs are usually measured in monetary units like dollars

azuka
Download Presentation

What is Cost and Project Cost Management?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. What is Cost and Project Cost Management? • Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange • Costs are usually measured in monetary units like dollars • Project cost management includes the processes required to ensure that the project is completed within an approved budget

  2. Basic Principles of Cost Management • Most CEOs and boards know a lot more about finance than IT, so IT project managers must speak their language • Profits are revenues minus expenses • Life cycle costing is estimating the cost of a project plus the maintenance costs of the products it produces • Cash flow analysis is determining the estimated annual costs and benefits for a project • Benefits and costs can be tangible or intangible, direct or indirect • Sunk cost should not be a criteria in project selection

  3. Basic Principles of Cost Management • Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars. • Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms. • Direct costs are costs that can be directly related to producing the products and services of the project. • Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project. • Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs.

  4. Basic Principles of Cost Management • Learning curve theory states that when many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced. • Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict. • Contingency reserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline. • Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns).

  5. Types of Construction Costs: • Capital Cost: • Expenses related to the initial establishment of the facility: • Land acquisition, including assembly, holding and improvement • Planning and feasibility studies • Architectural and engineering design • Construction, including materials, equipment and labor • Field supervision of construction • Construction financing • Insurance and taxes during construction • Owner's general office overhead • Equipment and furnishings not included in construction • Inspection and testing

  6. Operating and Maintenance Cost: • The operation and maintenance cost in subsequent years over the project life cycle includes the following expenses: • Land rent, if applicable • Operating staff • Labor and material for maintenance and repairs • Periodic renovations • Insurance and taxes • Financing costs • Utilities • Owner's other expenses • The magnitude of each of these cost components depends on the nature, size and location of the project as well as the management organization, among many considerations. The owner is interested in achieving the lowest possible overall project cost that is consistent with its investment objectives.

  7. Contingencies provisions: • In most construction budgets, there is an allowance for contingencies or unexpected costs occurring during construction. This contingency amount may be included within each cost item or be included in a single category of construction contingency • The amount of contingency is based on historical experience and the expected difficulty of a particular construction project • For example, one construction firm makes estimates of the expected cost in five different areas: • Design development changes, • Schedule adjustments, • General administration changes (such as wage rates), • Differing site conditions for those expected, and • Third party requirements imposed during construction, such as new permits.

  8. Estimation of Construction Projects There are many costs associated with construction projects. Some are not directly associated with construction itself but are important to quantify because they can be a significant factor in whether or not project goes forward. These are; • Financial agreements • Real estate transactions • Consultant services • Public relations • Marketing • Government regulations • Maintenance • Operations

  9. Estimating is a dynamic process that begins in very early stage and ends when the project is turned over to the owner. As project is moves along in time, amount of information generated increases. This information improves an estimate's accuracy but costs more. Estimators consider past projects while anticipating new factors. Some of this factors include: • Current technologies, • Marketplace demands on material and labor, • Quantities of materials, • Timeline of collective bargaining agreements, • Level of quantity, • The requirements for completion.

  10. If we have a good data base of actual costs from past experiences, quick and accurate estimate can be prepared. Each new project provides a clearer picture of the actual cost of construction and adds to the value of the data. Larger design and construction companies maintain their own data bases. Smaller companies may rely on the data developed from independent cost consultants and cost data suppliers. In US R.S. Means supply cost data and sell construction cost information to owner, designer, and constructors.

  11. Common Estimating Traits-1 Specific format estimators use varies with the type of estimate, type of project, and with company procedures. As experienced estimators know, all estimates share common traits as the following • As project develop, there is continual competition among issues of quality, size, performance, and cost. Owners want the biggest building with the best finishes and systems that will perform over the time for the least amount of money. The design and construction team uses estimates to ensure that good cost information is developed and a feedback loop established so that these conflicts can be addressed as quickly as possible.

  12. Common Estimating Traits • Estimating combines science and art. • Estimates are not guarantees of costs. • An estimate can only be as accurate as the information upon which it is based. Estimates depend on many factors. Document completeness, data base currency, the skill and judgement of the estimator. • An estimate’s accuracy increases as the design becomes more precisely defined. • Methodology and procedure are important for accurate estimating. Otherwise, the ability to process all the information that makes up an estimate will suffer. As the design process proceeds, the level of detail increases.

  13. Function Of Estimate From an owner’s perspective an early estimate helps • To define the affordability of the project, • How big is the project can be for the money available, and • What level of quality is possible. The estimate can also guide the decision among two or three possible options. Estimates offer guidelines to designer, who selects materials and sizes the project to fall within the owner’s budget. At the end of design process estimates must also be prepared by individual trade contactors to figure their bid price.These are done with nearly completed design documents, and are the most timeconsuming and most accurate of estimates.

  14. Function Of Estimate PM team often prepares a detailed estimate at this point to verify the accuracy of bid prices and to negotiate with trade contractors. An estimate can be used by PM to define the scope of work for each subcontractor as well as determine fair pricing. An estimate can also be used as a planning tool. Procurement specialists use it to define how much of a given item will need to be purchased. In the field, superintendents consult the estimate; • to determine total quantity of work in a particular location, • the total number of hours needed to do the work, and • the materials required.

  15. Owner's Purpose of Estimate 1. Making investment decision in the conceptual stage. 2. Negotiate and finalize the contract at the implementation phase. 3. To implement cost control measures.

  16. Contractor’s Purpose of Estimate 1. Determine project cost and profit. 2. To Implement cost control measure. 3. To develop data base that can be used for future project.

  17. Engineer’s Purpose of Estimate 1. Provide the owner with probable estimate. 2. Evaluate alternatives.

  18. Comparison of Contractor’s and Engineer’s Estimator • Contractor’s Estimator • Determines actual cost of project for bidding purposes. • Has detailed company cost data for labor and equipment. • Knows which construction methods are to be used. • Has knowledge of actual materials’ suppliers to be used and quantity discount prices. • Engineer’s Estimator • Determines expected cost. • Does not know who will receive award, therefore does not know contractor’s exact resource costs. Does not know actual labor rates. • Must assume probable construction methods to be used. • Does not know who project supplier will be. Must use local list prices.

  19. Estimate Considerations Every estimate considers the same basic issues. Project price is affected by; • Size of the project, • Quality of the project, • Location, • Construction start and duration, • Other general market conditions Accuracy of an estimate is directly affected by the ability of estimator to properly analyse these basic issues.

  20. Adjust for inflation/price Adjustment index Cost (@ t+ n) = Cost (@t)* (1+i%)n Where “i” is the expected inflation rate • Example: the screening estimate of an industrial plant for the production of batteries is $120 million in 2001 dollars, if the inflation rate is expected to be 8% per year , find the cost in 2004 dollars. • Cost = ($120)(1.08)3 = $151.2 million in 2004 dollars

  21. Adjust for local index of construction costs • Total construction cost of a refinery in Tallahassee, Fl was $100 million. It is proposed that a similar refinery will be built in Los Angeles, CA. if the location index was 0.92 for Tallahassee, FL and 1.14 for Los Angeles, CA, make an order of magnitude estimate of the cost of the proposed plant. • Cost of CA plant= ($100)(1.14/0.92) = $126.67 million

  22. Other An estimator who accurately incorporates project size, project quality location, and time has an estimate that reflects the fair value for the project. In normal market without any unusual circumstances, this estimate should reflect the price that is paid. However, market conditions shift, owner designer and contractor may look from different perspectives. Contractor may bid low or high. Such issues are included as % in either overhead, or profit in a final contingency.

  23. Types Of Estimates Estimates are developed early in the design process so that the owner and designer have cost information to guide the design to ensure that costs are within a given budget. Differences among the estimates are a function of information available at the time of estimate. Estimates can be divided into two broad category; • Estimate during design • Rough Order Magnitude Estimates, • Square Foot/Cubic Foot Estimates, • Assemblies Estimates • Estimate during construction

  24. Types Of Estimates ESTIMATING DURING DESIGN: Design estimates are important tools for the owner and the project management team as they develop the project’s scope of work. The discipline of providing cost information throughout the design phase makes cost a significant driver for project team. By providing cost information early and updating it, project team is kept in the realities of cost. • Rough Order Magnitude Estimates • Square Foot/Cubic Foot Estimates • Assemblies Estimates

  25. Rough Order Magnitude Estimates Rough order of magnitude (ROM) estimates typically establish a cost per unit of capacity. These units are developed mainly from past projects. Examples are; • cost per bed for a hospital, • cost per apartment, • cost per pupil for a school, or • cost per mile for a highway. Accuracy of ROM estimate depends on quality of data used. Advantage: it can be calculated quickly, often in a few hours, and is typically assumed to have an accuracy of plus or minus 20 %. These estimates are often first costs that an owner sees.

  26. Square Foot Estimates Once design in early schematic stage, it will start to produce floor plans, elevations, building sections. This information makes possible the calculation of floor areas or building volumes. These values are multiplied by appropriate unit costs to produce a square foot or cubic foot estimate. The appropriate unit costs are derived from either • in-house sources that track past similar projects, or • outside data sources. This base cost is adjusted to reflect more project-specific factors. Information regarding structural systems, building height, exterior closure, and overall footprint of building are all factors that will be assumed by estimator if real data are not available.

  27. Square foot estimate example Problem: Estimate the cost to construct a 55,000 square-foot motel.The motel will be a two-story building.The exterior wall will be made of a decorative concrete block,and the building will use a precast concrete floor system.Other features include 150 ceiling smoke detectors,10 nickel-cadmiumemergency lights, and a 500-square-foot gunite pool. Calculation 1.Interpolate a base price between $74.85(49.000 square feet) and $74.15(61.000 square feet).The interpolation : $74.15 61,000 $ ? 55,000 $74.85 49,000 74.85- ($6,000 * 0.70 )/12,000 =$ 74.50 2.Add the costs of the pool, smoke detectors, and emergency lights. 150 smoke detectors*$141 = $21,150 500-square foot gramite nite pool*$50 = $25,000 total = $52,050 Total project cost (with additives) = $4,149,550

  28. Estimating During Construction This estimate is the most detailed of all estimate types and is also the most important. Companies (interested in actually performing the work) price the project. It carries legal implications. If bid is accepted, a construction company is legally bound to a specific price for a specific scope of work. On large complex projects, the scope of works is a continual focus of discussion between the contractor and designer. Many factors affecting costs lie outside the scope of works; These are owner-requested changes, unforeseen conditions, regulatory requirements.

  29. Bid estimates The contractor's bid estimates often reflect the desire of the contractor to secure the job as well as the estimating tools at its disposal. Some contractors have well established cost estimating procedures while others do not. If all or part of the construction is to be undertaken by the general contractor, a bid estimate may be prepared on the basis of quantity takeoffs from the plans provided by the owner or on the basis of the construction procedures devised by the contractor for implementing the project. Example: The cost of a footing of a certain type and size may be found in commercial publications on cost data which can be used to facilitate cost estimates from quantity takeoffs. Items such as labor, material and equipment needed to perform various tasks may be used as parameters for the cost estimates.

  30. Organization Of Estimate Good organization is key to preparing reliable estimates and avoiding mistakes. Many peopleare involved. Information comes from a variety of sources and must be carefully catalogued. Estimating team’s goal: To minimize the number of company hours involved while preparing a competitive estimate. To begin, • Adequate space is set up, • Right mixture of senior & junior team member are assigned, • Forms are assembled. Most important information comes from contract documents, • whichexplain the scope of the work, • the conditions the contractor is expected to meet, • the legal requirements of the job, and • the schedule of completion.

  31. Quantity takeoff Once estimating tasks are identified, categorized, and organize, team begins quantity takeoff. This is foundation of estimate. • Purpose is to accurately determine the quantity of work that needs to be performed on the project. Every work item is measured and quantified, separating the work into units of labor, material, and equipment. • The goal of the quantity takeoff process is to calculate every item of the project- no more and no less. Takeoff must use correct units. • Example: Excavation and backfill … m3, formwork …m2, concrete …m3, structural steel … ton • The process requires a thorough understanding of work involved in each of different disciplines of project. • Use preprinted takeoff forms as checklist.

  32. Quantity takeoff-Example Problem: Typical plan and sections views of a building footing and foundation wall are given in figures Fig. 1 and Fig. 2. a) Determine the amount of earth that will be removed from the site. (Use a swell factor of 20%). b) Determine amount of formwork required to poor footings, walls and slab. Solution:a) Excavation calculations: Depth of excavation = 17.9 – 16.4= 1.5m. Volume excavated can be calculated as the volume of the rectangular area plus the volume of slopes (shown with S in Figure): Length of rectangular area: 25.6 + 2x0.9 = 27.4 m. Width of rectangular area: 10.6 + 2x0.9 = 12.4 m. Volume of rectangular area: 27.4 x 12.4 x 1.5 = 509.6 m3.

  33. Quantity takeoff-Example Solution:a) Excavation calculations (continued): Width of slopes: (X in Fig 2) is equal to 1.5 m. since angle of slopes is 450. Using figure 3: Volume of slopes ;= 2[½(20.4 x 1.5 x 1.5) + ½(12.4 x 1.5 x 1.5)] = 96.3 m3. Total amount removed from site = 1.2 (509.6 + 96.3) = 727.1 m3. b) Formwork calculations: Footing outer strip: 2 (25.6 + 10.6) x 0.3 = 21.7 m2. Footing inner strip: 2 (24 + 9) x 0.3 = 19.8 m2. Walls outer strip: 2 (25 + 10) x (18.2 – 16.7) = 105 m2. Walls outer strip: 2 (24.6 + 9.6) x (18.2 – 16.7) = 102.6 m2. No formwork is needed for the slab. Total formwork needed: 21.7 + 19.8 + 105 + 102.6 = 249.1 m2. Note: Calculations are made assuming that first walls are poured than slab is poured. If slab is poured first total formwork will be also 249.1 m2.

  34. Unit pricing Next task is to determine how much; • each unit will cost to produce, • to deliver to the site, • to install in the correct position, and • maintain until the project is turned over to the owner. Production of the product and delivery to the site are included in the material unit price. Cost of installing the product is part of the labor unit price. The equipment necessary to move the unit into place and install it is included in the equipment unit price. Project overhead covers the cost of accepting material, storing it at the job site, and protecting it until project is accepted. Company overheads includes estimate preparation, marketing company, and providing broad based technical and administrative support for project.

  35. Unit price Analysis One method for estimating is to estimate the cost for one unit of activity. For Example to determine the cost of the concreting activity, first estimate 1 m3 of concrete and tan multiply this unit price with the quantities calculated. • Unit prices for labor, material, and equipment are usually estimated separately and than added to estimate total unit price of an activity. • Ministry of Public Works in Turkey publishes estimates of various construction unit prices every year. These unit prices are used for bidding of some public projects.

  36. Material costs • Material prices are usually most straightforward to determine. The most reliable source is the supplier. • Estimator must ensure that the price covers all the specification requirements and the estimator’s assumption. Following points must be verified: • Material quoted is correct model number, color, and finish. • Price is valid until the scheduled delivery time. • The price includes delivery to the job site. • Adequate warranties and guaranties are provided. • The lead time fits into the scheduled need on site. • There is adequate stock available. • Payment terms, discounts, and credits are well documented.

  37. Labor costs-1 • The price of labor is the most difficult factor to determine because both the hourly wage rate and crew productivity must be considered. • Wage rate: a factor of rates paid to a specific trade. • Union rate: available from the locals unions and employer bargaining groups. Union rates are generally negotiated by each trade, so these agreements need to be researched. Factors to consider include the following: • Expiration dates of the union agreements • Amount of overtime anticipated. • Availability of skilled labor in the area. • Amount and nature of any hazardous conditions.

  38. Labor costs-2 Once quantity of work is known and hourly wage determined, last step in determining labor cost is to estimate how long the activity will take. An estimator needs to know the following: • Expected efficiency rate. • Other work occurring at the same time interfering it. • Expected weather conditions • Specific conditions of the work • Duration and frequency of overtime. Past project experience is essential in determining these factors.

  39. Equipment costs Equipment; • Small tools… covered item by item. • Large machinery such as cranes … covered on a project basis. Equipment costs fall into two general categories: • The equipment itself: covers ownership, lease or rental, interest, storage, insurance taxes, and license. If company owns the equipment, these costs are determined in-house. • The cost of operating: includes gasoline, oil, periodic maintenance, transportation, and mobilization. • Cost of operator is normally covered under labor line item.

  40. Subcontract work • Contractors break down the job into work packages and request bids from pre-qualified subcontractors for each package. Most general contractors do some of the work with their own work force • When bids arrive from subcontractors, a debriefing session take place to ensure that commonly missed items have been picked up. • Separate subcontractor`s work from contractor's (When applying overhead and profit to base cost). Because subcontract prices includes tax, insurance, and overhead and profit, adjustment on this price will be different from work of contractor`s own force.

  41. Overhead-1 • Overhead costs are the costs associated with operating the job site and home office expenses. • Job site costs includes field office people, safety, security, photography, and cleanup. These costs are typically itemized, with quantities and unit prices figured exactly. • Figure 8.11 lists typical general requirements. • One item is main office expense. It is carried as percentage and includes cost such as office rent or real estate costs, vehicles, engineering support, clerical staff, top management salaries, marketing, legal, and accounting fees. • Equipment overhead: managing purchase or rental, storage, handling of materials equipment.

  42. Overhead-2 • Labor overhead (greatest category): worker's take-home pay plus fringe benefits, including vacation time and paid sick days. Also, worker's compensation insurance and unemployment, social security taxes, builder's risk insurance and public liability cost. • Subcontractor` costs are also adjusted for overhead as a percentage. • Although subcontractors include overhead, the contractor's price covers the costs of organizing bid package, pre-qualifying subcontractors, reviewing the bids, and managing the subcontractors` work in field.

  43. Profit • A company grows and maintains its corporate health through its ability to make a profit. • Profit is added after the contractor has priced the labor and equipment involved. Overhead covered costs of managing the job. If no profit were added, the business might stay afloat for some time but would not grow. Companies must add a profit margin into each project. • The amount of profit added is a factor of the type of the project, its size, the amount of competition anticipated, the desire to get the job, and the extent of the risks. • A project with a high risk or one with little competition allows a company to add a higher profit.

  44. Homework • Using Unit price data, construct an assembly for the following: • a) A roofing system • b) A typical partition wall, • c) A pavement system. • Then explain why an assembly can be useful to an estimator.

  45. Project Cost Management • Project Cost Management includes the processes involved in planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. • Cost Estimating – developing an approximation of the costs of the resources needed to complete project activities. • Cost Budgeting – aggregating the estimated costs of individual activities or work packages to establish a cost baseline. • Cost Control – influencing the factors that create cost variances and controlling changes to the project budget.

  46. Cost Estimating: Tools and Techniques • Analogous Estimating: Using the actual cost of previous, similar projects as the basis for estimating the cost of the current project. • Analogous cost estimating uses expert judgment. • Analogous cost estimating is frequently used to estimate costs when there is a limited amount of detailed information about the project • Generally less costly than other techniques • Generally less accurate • Determine Resource Cost Rates • For each resource to estimate schedule activity costs. • Standard rates with escalation factors can be included in the contract. • Obtaining data from commercial databases and seller published price lists is another source of cost rates. • Gathering quotes

  47. Bottom-up Estimating • This technique involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail. • The cost and accuracy of bottom-up cost estimating is typically motivated by the size and complexity of the individual schedule activity or work package. • Generally, activities with smaller associated effort increase the accuracy of the schedule activity cost estimates. • Parametric Estimating • Parametric estimating is a technique that uses a statistical relationship between historical data and other variables (e.g., square footage in construction • This technique can produce higher levels of accuracy depending upon the sophistication, as well as the underlying resource quantity and cost data built into the model. • A cost-related example involves multiplying the planned quantity of work to be performed by the historical cost per unit to obtain the estimated cost.

More Related