1 / 12

Planning For The Future

Planning For The Future. Idaho Power’s 2006 Integrated Resource Plan. 2006 IRP Timeline. Idaho Power submits an Integrated Resource Plan to the Idaho and Oregon Commissions every two years 2006 IRP process began in September 2005 Submitted the 2006 IRP to the IPUC on September 29, 2006

baba
Download Presentation

Planning For The Future

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planning For The Future Idaho Power’s 2006 Integrated Resource Plan

  2. 2006 IRP Timeline • Idaho Power submits an Integrated Resource Plan to the Idaho and Oregon Commissions every two years • 2006 IRP process began in September 2005 • Submitted the 2006 IRP to the IPUC on September 29, 2006 • Planning period extended from 10 to 20 years • Align with the term of PURPA contracts • Long lead times required for certain generation resources and transmission projects • Begin 2008 IRP process in May 2007 (June 2008 submittal)

  3. IRP Planning Process Forecast Future Needs • Develop load, hydrologic and generation forecasts • Determine average energy deficiencies (monthly) • Determine capacity deficiencies (peak-hour) • Determine Pacific Northwest transmission deficiencies (peak-hour)

  4. Forecast Load Growth (2006-2025) • Summer peak load growth continues to drive peaking needs • Firm summer peak load growth – 80 MW/year (2.1%) • Firm winter peak load growth – 50 MW/year (1.6%) • Average annual firm load growth – 40 aMW/year (1.9%)

  5. Energy (Average Load) Surplus/Deficiency (2006-2025)

  6. Peak-Hour Load (Capacity)Surplus/Deficiency (2006-2025)

  7. Monthly Peak-Hour NorthwestTransmission Deficiency (2006-2025)

  8. IRP Planning Process Determine the Best Way to Meet Future Needs • Estimate costs of supply-side resources and demand-side measures • Construct numerous portfolios containing both supply-side resources and demand-side measures designed to meet average energy and capacity deficits • Determine the total cost of each initial portfolio • Select 4 finalist portfolios for further qualitative and quantitative risk analysis • Select preferred portfolio

  9. 2006 Preferred Portfolio Year Resource MW 2008 Wind (2005 RFP) 100 2009 Geothermal (2006 RFP) 50 2010 Combined Heat & Power 50 2012 Wind 150 2012 Transmission (McNary to Boise) 225 2013 Wyoming Pulverized Coal 250 2017 Regional IGCC Coal 250 2019 Transmission (Lolo to IPC) 60 2020 Combined Heat & Power 100 2021 Geothermal 50 2022 Geothermal 50 2023 INL Nuclear (PPA) 250

  10. Coal-Fired Resource Update Idaho Power and Avista • Idaho Power and Avista have executed a MOU to study and analyze the potential for developing one or more coal-fired generation facilities • Letters sent to project developers & mine owners on September 27th • Initial Data submittals were due October 25th • Currently analyzing and screening responses • Expect to have initial screening completed 1st Qtr 2007

  11. Near-Term Commitments • Assess level of CHP development and consider issuing RFP (IRP includes 50 MW in 2010) • McNary–Boise Transmission Upgrade – Study process initiated, expect to make commitments before filing 2008 IRP (2012 in service date anticipated) • Coal-based Resource – evaluation in progress, expect to make commitments to proceed with permitting and pre-construction activities before 2008 IRP is filed (2013 on-line date anticipated)

  12. Closing Thoughts Incorporate flexibility in the IRP to: • React to changing markets & regulatory conditions • Incorporate PURPA resource development • Acquire more or less of a specific resource depending on RFP results

More Related