1.02k likes | 1.03k Views
Taking the Blinders off MS Project and The case for 3rd Party Scheduling Services. Taking the Blinders off MS Project. Taking the Blinders off MS Project. by Ed Mahler edmahler@paiwebsite.com President, Project Administration Institute. Contents. Purpose The Schedule
E N D
Taking the Blinders off MS Project andThe case for 3rd Party Scheduling Services Taking the Blinders off MS Project Taking the Blinders off MS Project by Ed Mahler edmahler@paiwebsite.com President, Project Administration Institute
Contents • Purpose • The Schedule • Basic building block of the schedule • Enhancing MSP out of the box • Customized fields • Customizing the toolbar • Execution • Slippage, the ripple effect, and recovery • Status summary, what changed • Reporting via pdf • Lessons learned • The case for 3rd party scheduling service • References • Benefits of 3rd party scheduling service
Purpose To illustrate how the MS Project schedule can be made more visible for • Planning - being able to see why the timing is what it is. • Execution - being able to see the effects of change and what can be done to stay on schedule. • This is not an MS Project class. Contents
Cost Time Scope Team/sponsor communication Contract negotiation + = Why so much interest in the schedule? Sponsor ’s vision Project + SME’s = Schedule Project Manager Contents
Why do we need a schedule/contract? • Sponsor • Stakeholders • Will assume a schedule you may not like • Project team • Project team’s managers • Project office • So everyone agrees to what must be done by whom and when Contents
The Schedule Must be visible so the parties understand what they are agreeing to Contents
Building block of the schedule Task Contents
Predecessors Duration Successors Its attributes FS Task/Resources Contents
Successors Its relationships Predecessors FF Task/Resources Contents
Successors Its relationships Predecessors SS Task/Resources Contents
Successors Its relationships Predecessors Lag Task/Resources Contents
Successors Its relationships Predecessors Overlap Task/Resources Contents
Successors Its relationships Predecessors SF Task/Resources Contents
External Dependency Successors Its relationships Task/Resources Contents
Predecessors Duration Deliverables Its relationships Task/Resources Contents
Understanding the schedule For each task in the schedule what do you need to see? • Description (task name) • How long it will take (duration)? • Who will do it (resources)? • What has to happen before this task can be done (predecessors)? • What can’t happen until this task is done (successors)? • External date constraints (constraint type and date)? – Must have at least one! • What are the project’s external deliverables (no successors)? – Must have at least one! • A picture of the schedule (Gantt diagram) – Nice to have • If you want to be able to quantify and balance work load you need to estimate how much of each resource’s time will be spent on the task? Contents
Where the schedule originates A schedule is constructed from any combination of the following • An template created for the type of project being constructed • A prior plan for a similar project • A list of tasks in text format that can be copied into MS Project • SME interviews • An MS Project schedule for a project that is already under way Contents
MSP out of the box Gantt diagram The Gantt Chart view Contents
The View menu The Entry Table MSP out of the box Gantt diagram The Gantt Chart view Contents
Task name Task duration Task start Task finish Predecessors Resources The entry table Gantt diagram The Gantt Chart view all FS except this one is FF+ Contents
Indicator The entry table Contents
Indicator The entry table Contents
Indicator The entry table Contents
Summary tasks Summary tasks Overall duration Earliest start Latest finish Summary tasks Contents
Tools Options Adding a project summary Contents
View tab Select Project Summary Task OK Adding a project summary Contents
Project Duration Project Start Project Finish The project summary is task 0 Contents
Tools Options Changing summaries from days to weeks Contents
Schedule tab Change “Duration entered in” from days to weeks OK Changing summaries from days to weeks Contents
Changing summaries from days to weeks All summary durations now in weeks Contents
MSP out of the box For each task in the schedule what do you need to see? • Description (task name) • How long it will take (duration)? • Who will do it (resources)? • What has to happen before this task can be done (predecessors)? • A picture of the schedule (Gantt diagram) – Nice to have • What can’t happen until this task is done (successors)? • External date constraints (constraint type and date)? – Must have at least one! • What are the project’s external deliverables (no successors)? – Must have at least one! Contents
Adding the Successors column Right click the column heading and Insert Column Contents
Adding the Successors column Select Successors from the pull down Contents
To find missing successors click the filter pull down and Use a No Successors Filter to identify missing successors What can’t happen until this task is done? Added Successors column Contents
What can’t happen until this task is done? Only lines with blank Successor cells appear but without the rest of the schedule can’t see where to connect them Contents
and turning on the Highlight filter Changing the filter to highlight tasks By editing the view Contents
One can see the missing Successors in the context of the whole schedule Highlighted missing successors No Successors Filter Contents
This missing successor is a project deliverable Adding missing successors Add the missing Successors Contents
Missing Predecessors What about missing predecessors Use the No Predecessors Filter to identify missing predecessors Contents
Missing Predecessors with date constraints confirms they are external dependencies And running the “Tasks w constraints” filter Use the Tasks w Constraints Filter to identify date constraints Contents
MSP out of the box plus For each task in the schedule what do you need to see? • Description (task name) • How long it will take (duration)? • Who will do it (resources)? • What has to happen before this task can be done (predecessors)? • A picture of the schedule (Gantt diagram) – Nice to have • What can’t happen until this task is done (successors)? • External date constraints (constraint type and date)? – Must have at least one! • What are the project’s external deliverables (no successors)? – Must have at least one! Contents
Indicator Add the Notes field Inserting a column for notes Contents
Use tools/options to reduce column width req’ts Reduce duration and date formats Contents
Then reduce column widths Now reduce column widths Contents
and eliminate unneeded column and eliminate unneeded columns Reduced column widths Contents
The team now has what they need to understand the schedule except..... What should be under way or done by 11/18? Contents
What should be under way or complete by 11/18? Adding columns to indicate what should be under way or done by a status date Contents
Defining customized fields Right click on the column heading Select Contents
Create a formula for the field Rename the field Select the graphic to display for each value of the formula The logic behind the field Select Contents