An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Issues that Matter • Sno-Isle Lynnwood Library • May 14, 2019

  2. Lynnwood Link Extension • Project Overview • Preparing for Construction

  3. Construction Schedule (schedules are fluid and subject to change)

  4. Construction Preview

  5. Light rail project timeline PLANNING DESIGN CONSTRUCTION VOTER APPROVAL START OFSERVICE 2–4 years 2–3 years 5+ years 2016

  6. Light rail project timeline PROJECT DEVELOPMENT DESIGN CONSTRUCTION VOTER APPROVAL START OFSERVICE 3-4 years 5+ years 4-5 years Routes development Draft Environmental Impact Statement Board identifies preferred route Preliminary design Final Environmental Impact Statement Board selects projectto be built Federal Record of Decision Conversations withproperty owners Groundbreaking Construction updatesand mitigation Safety education Testing and preoperations 2016 Final route design Final station designs Procure and commission station and public art Obtain land use and construction permits PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT

  7. Light rail project timeline PROJECT DEVELOPMENT DESIGN 4-5 years VOTER APPROVAL 2016 Routes development Draft Environmental Impact Statement Board identifies preferred route Preliminary design Final Environmental Impact Statement Board selects project to be built Federal Record of Decision PUBLIC INVOLVEMENT

  8. Light rail project timeline CONSTRUCTION PLANNING DESIGN 2–3 years Final route design Final station designs Procure and commission station and public art Obtain land use and construction permits PUBLIC INVOLVEMENT

  9. Light rail project timeline DESIGN CONSTRUCTION START OFSERVICE 5+ years Conversations withproperty owners Groundbreaking Construction updatesand mitigation Safety education Testing and pre-operations PUBLIC INVOLVEMENT

  10. Everett Link Extension • Longest extension (16.3 miles) • Northgate is only halfway to Lynnwood • Lynnwood is only halfway to Everett 8.5 16.3 3.2 4.3 Everett2036 Lynnwood2024 Northgate 2021 UW2016 Westlake 2009 32.3 mile corridor

  11. Everett Link Extension • Length: 16.3 miles • Stations: 6 plus 1 provisional • Start of service: 2036