Appsworld 2003 Integrating the Supply Chain in Process Industries Cesare Kim 26 June 2003

Appsworld 2003 Integrating the Supply Chain in Process Industries Cesare Kim 26 June 2003. Oraplus Background. “We leverage Oracle technology in order to achieve major cost reductions and provide strategic advantage to our clients”. Founded in 1997

bell
Download Presentation

Appsworld 2003 Integrating the Supply Chain in Process Industries Cesare Kim 26 June 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Appsworld 2003Integrating the Supply Chain in Process IndustriesCesare Kim26 June 2003

  2. Oraplus Background “We leverage Oracle technology in order to achieve major cost reductions and provide strategic advantage to our clients” • Founded in 1997 • Offices in Italy, France, USA and the UK • Specialised in the implementation of Oracle based solutions • Vast repository of technical and functional expertise • Participation in over 40 major projects in 8 countries in 3 continents • Oracle Certified Partner • Extensive experience in Remote Oracle Support and Hosting • Certified ISO 9001 EN:2000 for the design, development, management and support of solutions based on Oracle Technology www.oraplus.com

  3. Agenda Introduction The OPM Solution The Oracle APS Solution ASCP and Manufacturing Scheduler Integration Case Study for a Bio-Chemical Company Q&A www.oraplus.com

  4. Introduction

  5. Third-party APS systems • OPM has traditionally integrated with i2 and other packages such as Manugistics • Different look and feel for the different modules • Three points of failure • OPM • Links • Third-party APS system • Different vendors with different support policies • Different vendors with different upgrade and technology stategies www.oraplus.com

  6. An Integrated Solution • Same look and feel • Single sign-on • Single-vendor interface • Integrated support/upgrade strategy • No need for customization/data cleaning due to architectural differences • Lower TCO www.oraplus.com

  7. The OPM Solution

  8. Native Planning Capabilities • Static lead-time and standard lot size definition • Identification of standard procurement leadtimes and lot sizes • Auto-calculation of standard leadtimes for manufactured goods • Quick single planning run • OPM MRP runs can be multi-warehouse and are very quick to produce a single MPS/MRP • Infinite Capacity Planning • Infinite Capacity capability only. • Graphical drag and drop interface allows quick manual leveling • Inter-organization transfer capability • Creation of an internal distribution network with specific transfer rules www.oraplus.com

  9. ModellingConsiderations • Model creation based on simplification – Occam’s razor • Identify critical processes • Identify critical resources • Model creation based on standard Client processes • Pareto Principle (80% of the issues are resolved with 20% of the effort) • Model by increasing complexity • Initial model should be limited to simple processes to enhance Client understanding of OPM • As processes and resources increase, so do their interactions, and a model that approaches reality is developed collaboratively www.oraplus.com

  10. Bio-Chemical Process Modelling • Chemical and Biological synthesis processes are different for assembling and mixing processes • Reactor planning requires fixed leadtimes - resource capacities have different meanings • The interaction between different operations can be very complex as constraints are not fixed but depend on the interaction of all processes www.oraplus.com

  11. The Oracle APS Solution

  12. Supply Chain Modelling • Multi-server Architecture • Multi-site • Planning across time-zones • Resource and Supplier capacities • Single-Cycle Planning run • Model Procurement and Manufacturing simultaneously • Optimise by Objectives Supplier Ingredients and Resources Intermediate or Bulk Products Finished Product Customers www.oraplus.com

  13. Manufacturing Scheduling • Modelling environment on top of Transactional System • Capacity-constrained fine scheduling • Setup optimization • Resource rather than Material-centric www.oraplus.com

  14. ASCP & Manufacturing Scheduler Integration with OPM

  15. ASCP Architecture • Logical segregation of Transactional and Planning Data • Data can be on one or two physical machines • Integration between the two worlds by Data Collection • Normalisation of data from heterogeneous Transactional systems • Return to Transactional system as recommendations www.oraplus.com

  16. ASCP OPM Integration • Model Formulas and Routings from OPM • Model Effectivities using OPM Recipes • Model Resource Capacities using OPM • Model Suppliers using Supply Chain Planning www.oraplus.com

  17. ASCP OPM Integration Limits • Cannot model charges • Powerful but delicate sinergy • Information is distributed over many modules • Significantly more maintenance at the technical level www.oraplus.com

  18. Manufacturing Scheduling OPM Integration • Take a snapshot of current jobs • Calculate resource availabilities • Manually level resources by drag and drop • Automatically schedule using optimization objectives and constraints www.oraplus.com

  19. Case Study

  20. Common Bio-Chem Requirements Need to: • Plan reactors • Coordinate extremely long and complicated routings with significant resource overlaps • Manage maintenance • Manage cleaning and setups • Schedule operations over inactive periods • Plan across a very long horizon for procurement www.oraplus.com

  21. Modelling Reactors • Chemical and biological synthesis processes are quantity independent • The reactor volumetric capacity will only dictate maximum quantity • Reaction time is based on process not quantity • Charge functionality partially addresses issue • Reactor volumetric capacity is modelled but this is often insufficient • Many companies manage different levels of detail for planning and fabbrication modelling www.oraplus.com

  22. Generic Resource www.oraplus.com

  23. Plant Resource www.oraplus.com

  24. Operation Header Information www.oraplus.com

  25. Operation Detail Information 1/2 www.oraplus.com

  26. Operation Detail Information 2/2 www.oraplus.com

  27. Objective: Complete Reactor Saturation www.oraplus.com

  28. Maintenance Management • Can use Resource Exceptions for basic scheduled maintenance • Enterprise Asset Management will be interfaced with ASCP to have a completely integrated Management suite www.oraplus.com

  29. Manage Reactor Cleaning and Setup • Cleaning operations and setups depending on the material processed in the previous batch • Modelling different recipes is a possible solution • Manually inserting downtimes is another possibility • Using Manufacturing Scheduler for fine scheduling is probably the best solution www.oraplus.com

  30. Break Management • Special cleaning processes may be required if reactors are inactive for too long • Some operations may not be interrupted • Model operations for minimum length to complete operations www.oraplus.com

  31. Procurement • Many tipologies of ingredients can be purchased at cheaper rates in relatively distant countries • Need to plan for long procurement cycles • Use ASCP long-term Procument Planning www.oraplus.com

  32. Prototype Solution • Use ASCP to develop a long-term infinite capacity plan • Actuate mid-term finite capacity procurement and manufacturing • Fine schedule using Manufacturing Scheduler • Minimal level of detail necessary to schedule and plan • Complete automation is difficult using a simplified model so a graphical drag and a drop interface becomes crucial for planners www.oraplus.com

  33. Lessons learned • Stay up to date with latest rollups during implementation • ASCP is an integrating force • Include a heavy patch installation and testing contingency • Unexpected results are often due to setup issues • Profile Options! www.oraplus.com

  34. Q&A www.oraplus.com