1 / 7

PIP Update

PIP Update. Oct 24 2012. Agenda. Summary Update Current Activities Updates/Talks: Salah Chaurize - Short Kicker Plans Matt Slabaugh / John Reid - Lessons Learned from 3rd Cavity Refurb Matt Slabaugh / John Reid - Test Tuner with New Ferrites. Update. General Info Current Work

benito
Download Presentation

PIP Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Update Oct 24 2012

  2. Agenda • Summary Update • Current Activities Updates/Talks: • Salah Chaurize - Short Kicker Plans • Matt Slabaugh / John Reid - Lessons Learned from 3rd Cavity Refurb Matt Slabaugh / John Reid - Test Tuner with New Ferrites

  3. Update General Info • Current Work • Booster RF cavity rework – Talk Today • Tuner with new ferrite – Talk Today • LCW – Fill is not done, still working on leaks (one at 4-2 fixed today?) • RFQ –Electrical work completed, Source under vacuum – preparing for beam this weekend! • HPower RF – ODDONE,PIERMARIA has signed the 1.4Mrequisition! Will submit the next req. to complete order soon…… • Booster Absorber – Kicker and PS work continues – Issues with blocks • Linac Modulator – Plans in place for EE support, SLAC to continue • Booster Solid State – Rack work? • Booster Modulator work – 8 done 2 in progress, 12 still need socket rings (due Oct 25) • Cogging – Software work continues • Booster Shielding – Safety is locating penetrations of concern Shutdown - comments (Fernanda, Todd, Mary) End of Fiscal Year – Not much change – There is still some FY12 –> FY13 funding discussions occurring

  4. RFQ Connected LEBT Vacuum Completed

  5. Upcoming • RLS – Just about done with updates and FY13 plans • Fiscal Year Start – • Will have special meeting today with Ann to discuss FY13 • Status requests will go out Oct 29. (next Monday) • Reports (October) • PMG (Thursday) • Quarterly Report (Soon)

  6. Upcoming Talks October 31: • Elmie Peoples / Ken Domann - Project Status Updates

More Related