1 / 28

IDIQ Contracting NCMA Luncheon

IDIQ Contracting NCMA Luncheon. 16 April 2008 Mark Schweer. Why discuss IDIQ Contracting?. Most of DoD’s services needs are acquired on IDIQ contracts Multiple award IDIQs follow unique rules for competition and award

bin
Download Presentation

IDIQ Contracting NCMA Luncheon

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IDIQ Contracting NCMA Luncheon 16 April 2008 Mark Schweer

  2. Why discuss IDIQ Contracting? • Most of DoD’s services needs are acquired on IDIQ contracts • Multiple award IDIQs follow unique rules for competition and award • Many San Diego contractors have SeaPort task orders. SeaPort is a multiple award IDIQ

  3. Overview • Contract Types • IDIQs in General • Multiple-Award IDIQs • Funding Issues • Fee Issue on SeaPort IDIQ • Other IDIQ Issues • Q&A

  4. Contract Types • How to identify an Indefinite Delivery contract: • N00039-08-D-9999 • “D-type” contracts are indefinite delivery • Types of Indefinite Delivery contracts: • Definite Quantity; FAR 52.216-20 • Requirements; FAR 52.216-21 • Indefinite Quantity; FAR 52.216-22

  5. Contract Types Types of Indefinite Delivery contracts: • Definite Quantity • Provides for delivery of a definite quantity of specific supplies or services for a fixed period, with deliveries or performance to be scheduled at designated locations upon order (FAR 16.502) • Requirements • Provides for filling all actual purchase requirements of designated Gov’t activities for supplies or services…. (FAR 16.503)

  6. IDIQs – In General Indefinite Delivery, Indefinite Quantity: • Description • Provides for an indefinite quantity, within stated limits, of supplies or services during a fixed period. (FAR 16.504) • Characteristics • Minimum guarantee (more than nominal) • Stated maximum quantity • Description of work (SOW, PWS, etc.) • Authorized ordering activities/individuals • Identified ordering period and procedures

  7. IDIQ Ordering – In General • TOs vs. DOs • Orders not synopsized • Max practicable use of PBA • Work described sufficiently to price • Mandatory information included • Date • Contract/order number • CLIN/Qty/Price etc. • Delivery Schedule • Place of Delivery • Funding/payment information

  8. Multiple Award IDIQs • Is the preferred method for IDIQs • Not appropriate if; • Only one source is capable • More favorable terms if single award • Cost of admin exceeds benefits • Orders are integrally related • Contract below SAP threshold • Not in the Govt's best interests • Special rules apply for advisory and assistance services

  9. Multiple Award Ordering • Gov’t must provide ‘fair opportunity’ for each awardee to be considered unless an exception applies. (See next slide) • Streamlined procedures/evaluation • Orders not protestable, except: • Scope • PoP FAR 16.505(a)(9) • Max Amount • Exceeds $10M • Ombudsman

  10. FAIR OPPORTUNITY EXCEPTIONS • Agency's need is of such unusual urgency that providing an opportunity to all awardees would result in unacceptable delays • Only one source is capable of responding due to the unique or specialized nature of the work • The new work is a logical follow-on to an existing task order where contractors were given a fair opportunity to be considered • The order must be placed with a particular contractor in order to satisfy a minimum guarantee. • There is a statute that authorizes or requires purchase from a particular source.

  11. Funding Issues

  12. Funding Issues • ‘Color of Money’ Issues • Alignment with PWS/SOW paragraphs • PoP implications; extensions • OMN crossing FYs • Prior years cost growth funded by ‘then current’ money • Full vs. Incremental funding (OPN)

  13. Funding Issues • If the order is fully funded at award, 52.232-20, Limitation of Cost clause applies. • If the order is incrementally funded at award, 52.232-22, Limitation of Funds clause applies. • 75% within 60 days ‘LOF’ notification • Gov’t not obligated to pay costs incurred in excess of funding provided • Contractor not obligated to continue performance beyond funded amount • Only Contracting Officer can commit the Gov’t to an increase in funds allotted. (apparent authority and ‘at risk’ situations) • Fee proportionate to work funded

  14. HANG IN THERE…HALFWAY!!

  15. Fixed Fee Issue on SeaPort-e IDIQ extracts fromJon Wester Brief – May 2007

  16. Fee Issue • CPFF IDIQ Contract Types • Completion: full fee (and no more) if work completed regardless of cost/hours expended • Level of Effort (Term): fee only on labor delivered. Methods to calculate interim payment of fixed fee: • Percentage of Costs Incurred. • Percentage of Hours Expended.

  17. Fee Issue • Scenario - CPFF Level of Effort TO on SeaPort-e expends less LOE than negotiated. • Possible Causes • Government: Partial Incremental Funding • Contractor: Delivering more expensive labor categories than originally proposed. • Example: • Original cost estimate of $25,000 • $25 per hour at 1,000 hours • Actual performance: • $50 per hour • Expends $25,000 ceiling with only 500 hours • Result: 500 fewer hours expended than negotiated, but all estimated costs expended.

  18. Fee Issue • What happens with fixed fee if the negotiated Level of Effort (LOE) is not expended? • SeaPort contracts/orders have included a clause to handle a proportionate reduction in fixed fee: SEA 5252.216-9122 (g) If the total level of effort is not provided by the contractor during the period of the task order, the contracting officer shall reduce the fee as follows: Reduced Fee = (Required LOE - Expended LOE)/Required LOE e.g. If the contractor expended 80% of the LOE, the contractor will receive 80% of the fixed fee.

  19. Fee Issue • On SPAWAR orders issued through May 2007, interim payment of fixed fee was made to the contractor equal to X (negotiated rate) percent of the incurred costs invoiced. • At Close Out: • Any balance of fixed fee due the contractor shall be paid to the contractor. • Any overpayment of fixed fee shall be repaid to the Government by the contractor at the time of final payment. • Final payment of fixed fee is made on the basis of labor hours expended/delivered.

  20. Fee Issue- Problem • If the interim fee payment is based on costs incurred and the final fee payment is based on hours expended, then this inconsistency can lead to a significant overpayment of fee to the contractor. • Recoupment of overpaid fee may occur long after performance is over.

  21. Example of Problem

  22. Fee Issue - Solution • Since May 2007, SPAWAR has used a new Section B clause (B-2) in new TOs and urged PCOs to modify existing TOs to include this clause, which makes the interim fee payment formula consistent with final fee payment formula. • Payment of Fee: • The Government shall pay fixed fee to the contractor on each direct labor hour performed by the contractor or subcontractor, at the rate of $X.XX per labor hour invoiced by the contractor. • Computation of Interim Fee: • The fee per direct labor hour is computed by dividing the fixed fee amount shown in Section B by the number of estimated hours proposed.

  23. Example of Solution

  24. Other IDIQ Issues • Small Business Implications • (For LB primes) Subcontracting Goals: scored at contract level rather than TO level [unless a separate subcontracting plan is negotiated at the TO level] • (For SB primes) Limitations on Subcontracting: scored at the contract level, not the TO level

  25. Other IDIQ Issues • Ordering Period • Orders can be issued until the last day of the ordering period • PoP of order near end of ordering period dependent on ‘clean-up’ period (See 52.216-22 or on SPAWAR contracts F-303) • Ex. Order placed on last day of ordering period. Clean-up period is 180 days. PoP of order can be no longer than 181 days.

  26. Other IDIQ Issues • Maximum Quantity (Ceiling) Management • Straight forward if single-award IDIQ • Multiple-award IDIQs: • Acq Plan (AP) authorizes ceiling (ex. $100M) • If 3 awardees; the max ceiling of the procurement is not $300M, but remains $100M per the AP • Section B of each contract may show max ceiling ($100M) because TO awardees not known • Ceiling management must aggregate TOs of all awardees, i.e. ceiling may be reached well before any of the 3 contracts reaches $100M

  27. Congratulations! You have now achieved the degree of “Very Dangerous” in IDIQ Contracting!

  28. QUESTIONS/COMMENTS Mark Schweer mark.schweer@navy.mil 619-524-7165

More Related