1 / 13

Procure to Pay Project All Staff meeting August 21, 2018

Procure to Pay Project All Staff meeting August 21, 2018. Last Updated : August 20, 2018. Agenda. P2P Status and EUAT Results final Bernie Updates Bernie Jaggaer and WalkMe Demo Glori Procure to Pay impact on … ACM Bernie General Questions All. P2P EUAT Results Final.

bolding
Download Presentation

Procure to Pay Project All Staff meeting August 21, 2018

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Procure to Pay Project All Staff meeting August 21, 2018 Last Updated: August 20, 2018

  2. Agenda • P2P Status and EUAT Results final Bernie • Updates Bernie • Jaggaer and WalkMe DemoGlori • Procure to Pay impact on … ACM Bernie • General Questions All

  3. P2P EUAT Results Final Key Messages: Customer Service Desk Week 9 22 contacts 3 (13%) Escalations to Level 3 EUAT Assessment - Successful Test Much faster than 312 Reqsand F4s Increased Transparency All issues addressed as EUAT progressed Reformatted training, offering additional options. Adding WalkMe, step by step, on demand guidance Incorrect/inaccurate Spend Categories being worked Added a Medical Supplies SIG led by Katie Oleksyn and Carl Tietjen Early User Acceptance Test (EUAT) Results Requisitions EUAT Total New89 Completed79 in process/Draft 3 Cancelled /Denied 9 Supplier Invoice Request (SIRs) New141 Completed135 In process 3Cancelled/Denied6 • Turn Around Time • Requisitions Total TAT Days 3.9 • Req Procurement 2.1 • Req Approval .7 • SIRs Total TAT 2.2 • SIRs Procurement .7 • SIRs Approval.47

  4. Workday Release 31 • Workday will be issuing Release 31 on September 8 • Major releases twice per year • Increased capabilities/functionality: • Will have the opportunity to add estimated freight to a requisition • UIT has been testing and will continue to rigorously test • Will enable approximately 1 week later • Workday general communications come from Jim Dobbertin • Procurement specific communications will be posted on the URProcurement site https://www.rochester.edu/adminfinance/urprocurement/ and published in the Newsletter.

  5. P2P Updates • Added a Medical Supplies SIG • Ensure we understand Medical Supplies Requirements and concerns • Added /will be adding a handful of new users • Testing Requisitioner Training for MyPath • SIR Initiator and all approver training is tested and available in MyPath • Testing WalkMe for EUAT participants • Requested WalkMe support for Procurement

  6. P2P Updates – Pilot 1 • February Pilot - 20 Groups confirmed Biological Supply Center Vivarium Budgets Core Nucleic Lab for the SRLs Processing Core Finance Food & Nutrition Services Friends of Strong Budgets Campus Dining Biology EH&S Remainder of UIT Chemistry Treasury Procurement Public Safety Audit Human Resources Admissions, Enrollment and Financial Aid • Target ~5-10% of the Requisitions and F4 populations • Balance # of transactions and $ spend • Current Pilot candidates sized at over 1,800 Requisitions/SIRs valued at $32M annually • Monthly estimate~ 1500 Reqs/SIRs valued ~ & $2.6M

  7. Marketplace and Walkme Demos Glori Tatro

  8. How will P2P impact the ACM Role? For the ACM • Far fewer requisitions will need touching • What will I do with all the free time? • Automation enables working smarter – not harder

  9. How will P2P impact the ACM Role? Data means the opportunity to do higher value work The opportunity to turn this data into a strategy

  10. How will P2P impact the ACM role? • Turn Data into • Something actionable • Merge diverse sources of data • Pivot Tables • Perform Analytics • Charts & Graphs • Research • Compare to Jaggaer catalogues • Illuminate Options & Make recommendations • PowerPoint • Could be asked to Negotiate w/ Suppliers • Negotiation skills, meeting facilitation skills

  11. ACM Qualifications and Skills Required • Career position • Bachelor’s Degree • 3+ years relevant experience • Or combination of equivalent experience • Strong • Communication • Facilitation • Team-building • Analytical • Microsoft Office skills Excel PowerPoint Word Outlook