1 / 22

Initial Deformation of the PETRA3 slab

Initial Deformation of the PETRA3 slab. Markus Schlösser. IWAA 2010, 13.-17. September 2010. accuracy requirements (components). old octants: s = 300µm / 150m (transverse & height) new octant: magnet – magnet s = 50µm girder – girder s = 100µm (transverse and height)

brandyr
Download Presentation

Initial Deformation of the PETRA3 slab

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Initial Deformation of the PETRA3 slab Markus Schlösser IWAA 2010, 13.-17. September 2010

  2. accuracy requirements (components) old octants: s = 300µm / 150m (transverse & height) new octant: magnet – magnet s = 50µm girder – girder s = 100µm (transverse and height) s = 500µm (longitudinal) (TDR, 2004) • introduction

  3. floor of new experimental hall • introduction • Monolithic floor slab made from reinforced concrete • 300m length • 30m width • 1m thickness • (without joint)

  4. making of concrete slab concrete delivery and filling of pump • introduction pouring of concrete smoothing of concrete surface

  5. cross section of slab top layer, epoxy, t = 15 mm 34.37 34.36 1 (reinforced) concrete with steel fibres (approx. 1% fibers) 49 33.87 1.00 reinforced concrete C30/37 bitumen gliding sheet, t = 3 mm 50 subconcrete 33.37 5 05 3 equalizing layer base layer, concrete-mineral mixture

  6. temperature of concrete (2007 – 2009) • temperature setting of concrete 4th epoch 1st epoch 2nd epoch 3rd epoch

  7. temperature of concrete (2008) daily variation • temperature 2nd epoch activation of air-condition 1st epoch start of survey in the new hall

  8. thermal expansion of concrete slab aconcrete = 10 · 10-6 / K (theoretical value) l = 300m  dl = 3mm / K dT = 22°C – 16°C = 6K  dL16 = 18mm • Problem: • Installation starts at 16°C, final temperature at 22°C • predicted movement is 18mm • accuracy is at the 100µm level • coarse alignment mechanics of most components can notbe moved by more than a few mm • analytical models • Solution: • introduce analytical model • predict position of each network fiducial at 22°C • stakeout coordinates are not affected • independent from the actual temperature

  9. models for expansion of slab • 1st approach • network measurement taken at 16.2°C • estimate position of each monument at 22°C from analytical model (linear / circular) • 2nd approach • network measurements taken at 16.2°C and 20.4°C • estimate parameters for analytical model from combination of measurement epochs • 3rd approach • network measurements taken at 16.2°C and 20.4°C • extrapolate position of each monument at 22°C from empirical model • 4th approach • network measurement taken at 22°C • no model necessary • analytical models

  10. 1st approach • network measurement taken at 16.2°C • estimate position of each monument at 22°C with analytical model (linear / circular) Each monument gets radial and tangential shift component, Dr = h (r) Dj = x (j) aconcrete from literature • analytical models line of no tangential movement line of no radial movement

  11. 2nd approach • network measurements taken at 16.2°C and 20.4°C • estimate parameters of analytical model by combining two measurement epochs Each monument gets radial and tangential shift component, BUT Dr = h (r,j) Dj = x (r,j) estimate aconcrete line of no tangential movement • analytical models line of no radial movement

  12. 3rd approach • network measurements taken at 16.2°C and 20.4°C • extrapolate position of each monument at 22°C from empirical model lines of identical tangential movement Each monument gets radial and tangential shift component, Dr = hh (r,j) Dj = xx (r,j) estimate aconcrete • analytical models lines of identical radial movement

  13. movements 05/2008 -> 02/2009(16.2 -> 22.0°C) 11.5 3.3 • measure-ments 10.0

  14. modell errors 05/2008 -> 02/2009 2.0 3.1 • measure-ments 3.6

  15. movements 08/2008 -> 02/2009(20.4 -> 22.0°C) 3.2 0.9 • measure-ments 2.5

  16. modell errors 08/2008 -> 02/2009 0.5 0.6 • measure-ments 0.5 (0.8)

  17. movements 02/2009 -> 05/2009(22.0 -> 22.0°C) 1.3 • measure-ments 1.2

  18. tangential shifts • measure-ments

  19. radial shifts • measure-ments

  20. height changes • measure-ments

  21. high precision measurement, made by civil engineers

  22. Summary • empirical thermal expansion coefficient (longitudinal)aconcrete = 12 · 10-6 / K • center line of no radial movement is not in the middle of the slab • height change 05/2008 – 05/2009 approx. 1.5 bis 2.0 mm • deformation seems not to have finished after reaching the final temperature of the slab • result

More Related