1 / 56

Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998

Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998. Architect: Humberto Cavallin Engineer: Alec Zimmer Construction Manager: David Miller Owner Representative: Luciana Barroso. Presentation Outline. The Project Statement

Download Presentation

Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mountain Ridge Team Final PresentationThe Ridge University Engineering BuildingMay 15, 1998 Architect: Humberto Cavallin Engineer: Alec Zimmer Construction Manager: David Miller Owner Representative: Luciana Barroso The Mountain Ridge Team

  2. Presentation Outline • The Project Statement • Early Proposed Concepts • The Idea: Product, Evolution, and Process • The Final Product • Summary: The Team Process The Mountain Ridge Team

  3. Project Definition • Facility: A new 30,000sf academic building for The Ridge University School of Engineering with classrooms, labs, offices and auditorium • Year: 2010 • Location: Tahoe City, California The Mountain Ridge Team

  4. Project Definition:Physical Constraints • Must use one of 2 existing footprints The Mountain Ridge Team

  5. Project Definition:Physical Constraints • Must use one of 2 existing footprints • 35’ height restriction • Very heavy snow loads • Moderate to high seismicity (Zone 3) • Remote site with limited access The Mountain Ridge Team

  6. Proposed Concept - Lshape1 The Mountain Ridge Team

  7. Proposed Concept - Square1 The Mountain Ridge Team

  8. Proposed Concept - Lshape2 The Mountain Ridge Team

  9. Proposed Concept -Square2 The Mountain Ridge Team

  10. Proposed Concept -Square2 The Mountain Ridge Team

  11. The Iterative Process Square2 E C Lshape2 A O Square1 Lshape1 First Quarter Second Quarter The Mountain Ridge Team

  12. Site Plan The Mountain Ridge Team

  13. The Building 1 2 3 The Mountain Ridge Team

  14. Activities • Administrative • Students • Educational The Mountain Ridge Team

  15. Architectural Evaluations - Floor 1 The Mountain Ridge Team

  16. Architectural Evaluations - Floor 2 The Mountain Ridge Team

  17. Architectural Evaluations - Floor 3 The Mountain Ridge Team

  18. Architectural Evaluations - Section The Mountain Ridge Team

  19. Architectural Evaluations - Section The Mountain Ridge Team

  20. Engineering Loads-Gravity Loads Dead Loads Including 25 psf floor & partitions 10 psf MEP equipment 83.5 psf for 6.5” slab and metal deck 109.6 psf total (205 psf is seismically effective) Live Loads Including 100 psf in halls & library 50 psf in offices 40 psf in classrooms The Mountain Ridge Team

  21. Engineering Loads-Seismic and Snow Loads Snow Loads 223 psf Ground Snow 1.0 Importance Factor 0.6 Exposure D Factor Nominally Flat Roof 133 psf roof snow load (75% is seismically effective) Seismic Loads from 1994 UBC Z = 0.3 Seismic Zone 3 T = 0.203 by Method A C = 2.75 for firm soil Rw = 8 compromise for this dual system Vbase = 608 kip Mot = 9426 k-ft The Mountain Ridge Team

  22. Engineering Evaluations - Floor Details and Load Path Composite steel deck - concrete slab Shallow beam sections Typical Sections: Beams sizes from W10x12 to W12x30, unshored construction All columns W12x40 to facilitate connections Shear connections only Cross Beam: W10x19, Typ. Ext. Girder: W10x22, Typ. Typ. Vertical Gravity Load Transfer Column: W12x40, Typ. 12” Shearwalls Resist All Lateral Loads Second Floor Beams - Plan View The Mountain Ridge Team

  23. Engineering Evaluations -ETABS model Verify period with modal analysis Evaluate deflections and interstory drift Verify load path assumptions Problems in model The Mountain Ridge Team

  24. Engineering Evaluations - Cross Sections at Lines 1 and 3 • Note typical sections and detail references The Mountain Ridge Team

  25. Third Floor Moment Frame Connection Detail Engineering Evaluations - Critical Connection Details The Mountain Ridge Team

  26. Engineering Evaluations -Shear Wall-Beam Connection Details The Mountain Ridge Team

  27. Engineering Evaluations -Shear Wall Design Resist all lateral loads, both seismic and wind • Mot = 1061.9 k-ft per wall • Vbase = 484 k • No boundary zones • No additional moment reinforcement • Torsional effects are negligible The Mountain Ridge Team

  28. Engineering Evaluations - MEP Assumptions Steam heat and chilled water from central facility 15’ x15’ room provided on ground floor for equipment Circular ducts standard throughout with rectangular ducts in congested areas, 18” max. Small equipment rooms provided on all floors for advanced communications equipment Air requirements in auditorium are 20 CF/person/minute, given an approximate capacity of 250 people The Mountain Ridge Team

  29. Engineering Evaluations - Three-Dimensional Model The Mountain Ridge Team

  30. Contractor - Site Plan The Mountain Ridge Team

  31. Contractor - Fall 2011Schedule The Mountain Ridge Team

  32. Contractor - Spring 2012 Schedule The Mountain Ridge Team

  33. Contractor - Winter Respite Analysis • Impractical to weatherproof before winter weather hits • Either shut job down during winter or rent tent for $42,000 per month • Project can still be completed comfortably if dormant for <4 months • Respite allows for coordination and planning The Mountain Ridge Team

  34. Contractor - Estimate Details • Location adjustment factor of 1.15 • $160/s.f. 1998 dollars ($210/s.f. 2010 dollars) • 6% Contractor fee • 10% Architecture and Engineering fee The Mountain Ridge Team

  35. Contractor - Critical Phases of Work Heaviest lift complete The Mountain Ridge Team

  36. Contractor - Critical Phases of Work Floors and roof complete The Mountain Ridge Team

  37. Contractor - Equipment • Crane selection for steel erection • 50T hydraulic rough terrain crane with 65’ boom • Critical lift: 4 ton beam at 60’ radius • Gradall material handlers The Mountain Ridge Team

  38. Contractor - Estimate Progression The Mountain Ridge Team

  39. Contractor - Schedule Loading 2011 2012 The Mountain Ridge Team

  40. Contractor - Budget Breakdown The Mountain Ridge Team

  41. Contractor - Inflation Analysis The Mountain Ridge Team

  42. Contractor - Construction Cost Index The Mountain Ridge Team

  43. A/E/C/O Height variance Ramp in rear of building 2 plane vs. 4 plane roof system C/E Beam spacing Floor system A/E/O Window wall Balcony in rear 3rd floor Shearwall Entrance façade column locations A/C/O Cladding Excavation costs Product, Evolution, and Process The Mountain Ridge Team

  44. Floor and Structural Systems -E/C Trade-off Analysis • Concrete for floor decks: • Lightweight concrete? • Normal weight concrete? • Steel Framing: • Moment resistant frames - shop welded? • Eccentrically braced frames? • Simple gravity frames? The Mountain Ridge Team

  45. Beam Spacing -E/C Trade-off Analysis • 20’ column grid • Beams can be spaced at 10’ or 20’ on center? • Larger beam spacing means fewer pieces, fewer connections and thus faster construction. • But, also requires deeper slabs • Cost basically unaffected • Long-term usability chosen over short-term construction schedule benefits The Mountain Ridge Team

  46. Basement Layout vs. Excavation -A/E/C/O Trade-Off Analysis Building Functioning Space allocation slope floor, owner requirement Costs Activities and program requirements O/A Evaluation The Mountain Ridge Team

  47. Ramp in Rear of Building -A/E/C/O Trade-Off Analysis • Relationship with the excavation • Development of the option • Rejection of the ramp alternative The Mountain Ridge Team

  48. East Balcony and Column Locations -A/E Trade-Off Analysis Owner requirements for a balcony Architectural solution - cantilever Engineer’s response with additional columns - spares moment connections Added Columns Plan of East Balcony The Mountain Ridge Team

  49. Window Wall and West Balcony -A/E/O Issues The Requirements of O/A/E The communications breakdowns The positioning of walkway supports The Mountain Ridge Team

  50. Exterior Cladding -A/C/O Cost vs. Appearance Concerns Plaster or stone Stone more has institutional, timeless appearance Stone $1 million than plaster Stone/plaster combination chosen The Mountain Ridge Team

More Related