An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPD VFE and CB status and plans • VFE status and plans • CB status and plans • Issues • Plans Calo commissioning meeting – CERN 16th January 2008 Calo Comissioning Meeting

  2. (1) VFE tests on A-side • Digital test (LVDS phase, VFE reset, DACS/ASICs R/W): • OK on 49 VFEs • 8T01/8TOU/S070: status register errors. Check LV, GND and CB. • LVDS test (BER) : • Random pattern • Status OK on all data links (between VFE and FE). • Problems: • LVDS test bit on VFE is writen and test stopsfor VFE while CAT is on... • Communication breakdown in the middle of a test. SPECS needs to be restarted. Observed mostly on some channels of CB at PRS4 i PRS5. • Offset measurements: • Done for all VFEs. • Review GND PRS5 CB2 ch4. Maybe GND could be better. • Threshold values are 9 sigma from offset (or pedestal). • Recipes prepared and under use for LED measurements. Calo Comissioning Meeting

  3. (1) VFE tests on A-side • LED measurements: • The measurements are done using CAT and taking just a few triggers. • HV = 700V (approx. the one expected to be applied for physics) • Problems found: • Very hot channels: • PRS5CB16ch4/6T04/S092: saturation on ch56. Hot on ch 5, 6, 7, 8, 9. • PRS6CB5ch6/5T01/S051: saturation on ch 53 and 54. Very hot on ch 61 • PRS6CB16ch2/6T01/S034: saturation on ch 20 and 36. Other very hot channels. • PRS6CB16ch3/6T03/S035: ch 7 and 8 very hot. • Trigger problems: for SPD 5-4 and SPD 8-3 trigger cables no data havs been seen except on a few triggers. • Only the Vled can be tuned in order to have signal on all channels. All Vled are applied corresponding to groups of VFEs that not necessarily need the same Vled. There is an important difference between SM5 inner and middle that would lead to loose 4 VFEs LED signal if flashed toghether (4x64 channels). Will all channels be flashed toghether? Will it be necessary to flash in groups and change Vled? • Mapping: we are investigating the mapping to correct channel problems and to verify it. Just started today: full top, half to data! Calo Comissioning Meeting

  4. (2) Control Board status and plans • For some triggers on cosmics we need: • Multiplicity • BCID alignment • Optical link Calo Comissioning Meeting

  5. (3) Issues • SPD A-Side movement: • Lead problem • Open end too far • Scaffolding access: • Top floor is loose • Check with Cedric tomorrow Calo Comissioning Meeting

  6. (4) Plans • Plans: • This is the last acces to A-side. • Understand all CAT problems. • Access and repair the 2 VFE. • Solve as LED problems as possible • Check mapping configurations • Calibrate temperatures probes. • Try to synchronize CB, FE, VTB, CROC... Calo Comissioning Meeting