1 / 21

Choi, Mihee 2008. 8. 11

Multi-criteria analysis on Decision-Making Process in Public Investment in case of road construction project in Korea. Choi, Mihee 2008. 8. 11. Contents. Introduction II. Multi-Criteria Analysis in Decision-Making Process - Environmental cost-benefit analysis as EIA

Download Presentation

Choi, Mihee 2008. 8. 11

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Multi-criteria analysis on Decision-Making Process in Public Investmentin case of road construction project in Korea Choi, Mihee 2008. 8. 11

  2. Contents • Introduction • II. Multi-Criteria Analysis in Decision-Making Process • - Environmental cost-benefit analysis as EIA • - Stakeholder participation • III. Decision-Making Process Problem in Public Investment • IV. Case Study • V. Lession

  3. Study Point and Methodology

  4. Focus on three categories Study point and Methodology used • Positive Impact on the Environmental/ Economical Efficiency • Positive impact on the environment, EIA • Economically efficient, CBA • Various Factors and their Priorities • Consideration of the various factors and priorities, MCA • Stakeholder’s Opinion • Reflection on stakeholders’ opinion in EIS, PI

  5. Decision-Making System in SOC investment

  6. Decision-Making Process in Korea Decision-making System in SOC construction, Korea Environmental Impact Analysis (EIA) Cost-Benefit Analysis (CBA) Stakeholder Participation: Public Involvement (PI) To minimize economical damage To get rid of disbelief of administration

  7. Case Study Chuncheon-Yangyang Highway Construction Project

  8. Information of Baekdudaekan Ecosystem Case study of Chuncheon-Yangyang Highway

  9. Pressure of Development on Baekdudaekan Case study of Chuncheon-Yangyang Highway • Development Project: • Until currently, large-scale project have continued. • Mines, dams, routes, leisure facilities, farmland, etc. • Ecosystem has been destroyed on a large scale by projects. • 8% of Baekdudaegan has been damaged. • Road and Railroad in Baekdudaekan • There are a lot of roads. • 30 Pavements, 3 railroad and 20 forest roads which go through 7.88km. • This construction has seriously damaged Baekdudaegan.

  10. Chuncheon-Yangyang highway project Case study of Chuncheon-Yangyang Highway • Outline of the Project • Large-scaled road construction has 4 lines. • Total amount of project is around 3,843.9 billion won. • 71.7km long tunnel will be constructed. • This tunnel will extend over 10.9km through Baekdudaekan.

  11. Chuncheon-Yangyang highway project Case study of Chuncheon-Yangyang Highway

  12. Multi-criteria analysis in Decision-making Process, Chuncheon-Yangyang Highway

  13. Environmental Impact Analysis (EIA) Cost Benefit Analysis (CBA) Multi-Criteria Analysis (MCA) Multi-criteria analysis in Decision-making • Predictive and Evaluative Stage • Identification of impacts • Prediction of impacts • Evaluation of impacts • Evaluation Stage • Measured in economic terms • : Use information on the relationship among physical, biological, ecological attributes • Note the major problem • : limitation of theory and data

  14. Environmental Impact Analysis (EIA) Problem Multi-criteria analysis in Decision-making • EIS not anticipate and evaluate the result • Limitation of both theory and data in the realm of biology and ecology • Go through the UNESCO biosphere reservation in Bakdudaekan • Violates Bakdudaekan Protection Law • Caused conflicts between the Government and the residents

  15. Cost Benefit Analysis (CBA) Problem Multi-criteria analysis in Decision-making • Evaluation Stage • EIA does not satisfactorily give environmental impact • : cannot get precise result to convert it into economic value • Use I presuppose an assumption • : destruction of ecosystem is around as half-length of tunnel • The result • : Total cost of construction: 24,336 billion won • : Total benefit: 19,728 billion won • : B/C ratio: o.81 • : NPV: 4,608 billion won

  16. Public forum at EIA and Public Involvement: Problem Case study of Chuncheon-Yangyang Highway • Public Forum • Government used PI, when the government got residents’ opinion • Public Involvement Setup: • - In July 2005, the government and NGO asserted their own opinions • but not reach the agreement it in TV debate • In Setember 2005, NGOs held the forum with stakeholders • Negotiation impossible each other, NGOs and government • Public Involvement Process: • Open a website(http://www.ccyypi.net) • From September 2005 through March 2006: three conference • Government interest : highway construction and impact reduction • So, be never interested in discussing in social request item

  17. Multi-criteria Analysis (MCA): limitation Multi-criteria analysis in Decision-making • Reasons decision-making process complicate • Hard to anticipate environmental impact • To evaluate economic efficiency, we cannot avoid strong assumption • To protect ecosystem of Baekdudaegan institutionally • Sharpening conflict • Because of this reason • Strongly suggest MCA method • : environments, economics, institutions and opinions of residents

  18. Multi-criteria Analysis: EIA, CBA, PI Case study of Chuncheon-Yangyang Highway • National environmental impact for Backdudaekan(EIA) Valuation of economic efficiency(CBA) Consideration of institution and policy Opinions of Residents(PI)

  19. Multi-criteria Analysis: EIA, CBA, PI Case study of Chuncheon-Yangyang Highway • Elements as multi-criteria analysis: AHP • Environmental influence: 0.417 • Economical influence: 0.140 • Policy and system: 0.388 • Democracy in decision-making process in policy: 0.155 • Priority is the following orders • (1) environmental influence • (2) economical influence • (3) policy and system • (4) democracy in decision-making process in policy • lesson • necessary to give priority to environment and economic • policy and institution take precedence over economical influence • reconsider the construction of Chuncheon-Yangyang highway

  20. Lesson Multi-criteria analysis in Decision-making Should consider the following points(MCA) • EIA requires anticipation and valuation of environmental impact • Environmental BCA have to be included when we evaluate environmental impact • In decision-making process, included following information • The policy and institutional effect • Deliberative decision-making • Environmental impact • Economic effect

  21. Multicritia analysis on decisionmaking process in public investment- in case of road construction project, Korea Thank You