An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PKP Polish Railway Lines’ investment plans >> Creating a World Class Rail Network << Dr. Marek Pawlik PKP PLK S.A. Vice President Warsaw, 16thNovember 2011

  2. ENE MAI CCS RST OPE TAF/TAP INF Structural sub-systems Functional sub-systems . . . • TSIs for both HS and CR systems: • TSI NOI (Noise) • TSI SRT (Safety in Rail Tunnels) • TSI PRM (Persons with Reduced Mobility) • TSI TAP (Telematics, Passenger Services) • TSIs for High Speed rail systems: • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operation) • TSI RST (Rolling Stock) • TSIs for Conventional rail system • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operational) • TSI RST + TSI WAG (Rolling Stock) • TSI TAF (Telematics, Freight Services) + national requirements

  3. railway network in Poland 20 547 kms of lines PKP PLK S.A. investments in structural sub-systems2007 - 2013 Lines of state importance upgrading for interoperability~1500 kms of lines Lines of local importance upgrading in accordance with EU regulations ~1000 kms of lines

  4. Main Tasks for PreparingHigh Speed LineWarszawa – Lodz – Poznan/Wroclaw 4

  5. Planned HS Lines and its extension to neighbour countries 5

  6. HSL Warszawa – Lodz – Poznan/Wroclaw 6

  7. Modernisation and Extension of CMK line

  8. HSL Warszawa – Katowice/Krakow – South Border 8

  9. High speed trains on conventional railway lines- standards for: - HS lines - HS trains- compatibility with: - 2007-13 CohesionFund investments - existing railway infrastructure • Warszawa - Łódź • 0:35 • Warszawa -Białystok • około 120 km • 3:30 • 1:40 • 1:30 • Warszawa -Szczecin • 3:15 • Warszawa - Berlin • ok. 3:30 • Warszawa -Gdańsk • Warszawa - Lublin • Warszawa - Poznań • 2:40 • 1:35 • około 340 km • Warszawa - Wrocław • 1:40 • około 345 km • Warszawa - Rzeszów

  10. PKP PLK S.A. investment process • plans to the MasterPlan 2030; • tenders for feasibility studies; • gradual change from tenders for design and tenders for construction to tenders for design and construction; • intensive works on standardised tender documents both in legal and technical dimensions.

  11. ENE MAI CCS RST OPE TAF/TAP INF Structural sub-systems Functional sub-systems . . . • TSIs for both HS and CR systems: • TSI NOI (Noise) • TSI SRT (Safety in Rail Tunnels) • TSI PRM (Persons with Reduced Mobility) • TSI TAP (Telematics, Passenger Services) • TSIs for High Speed rail systems: • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operation) • TSI RST (Rolling Stock) • TSIs for Conventional rail system • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operational) • TSI RST + TSI WAG (Rolling Stock) • TSI TAF (Telematics, Freight Services) + national requirements

  12. PKP PLK S.A. CCS investments • plans to the ERTMS National DeploymentPlan quoted by MP2030; • ETCS implementation: - 84 kms - pilot project (l2),- 224 kms - CMK speeding-up (l1)- 8 traction vehicles in the pilot,- 10 HS Locos for IC trains (to be equipped after suply)- 20 HS trainsets to be delivered with ERTMS on-board - European ERTMS Master Plan (~ 300 kms per year in Poland); • GSM-R implementation:- 84 kms pilot + 2 MSCs in Warsaw and Poznań- 1300 kms of lines with already available preliminary GSM-R planning + OPE adaptation + LDL signalling + LX protection

  13. ENE MAI CCS RST OPE TAF/TAP INF Structural sub-systems Functional sub-systems . . . • TSIs for both HS and CR systems: • TSI NOI (Noise) • TSI SRT (Safety in Rail Tunnels) • TSI PRM (Persons with Reduced Mobility) • TSI TAP (Telematics, Passenger Services) • TSIs for High Speed rail systems: • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operation) • TSI RST (Rolling Stock) • TSIs for Conventional rail system • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operational) • TSI RST + TSI WAG (Rolling Stock) • TSI TAF (Telematics, Freight Services) + national requirements

  14. The Railway System Safety Directive Scope of X Acceptance Open Points RUs and IMS Safety Management Systems Legacy National Rules Current TSI Off TENS Final TSI key RS questions • RS certification for networkversus ETCS cert by projects; • PLK Involvement in RS XA legal works: - 2008/57/EC annex VII,- 2009/131/EC changing annex VII; • Follow up EU legal works(GIG based on corr. F & C): • - supporting notification of the Polish requirements for RS, - supporting equivalence checking.

  15. ENE MAI CCS RST OPE TAF/TAP INF Structural sub-systems Functional sub-systems . . . • TSIs for both HS and CR systems: • TSI NOI (Noise) • TSI SRT (Safety in Rail Tunnels) • TSI PRM (Persons with Reduced Mobility) • TSI TAP (Telematics, Passenger Services) • TSIs for High Speed rail systems: • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operation) • TSI RST (Rolling Stock) • TSIs for Conventional rail system • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operational) • TSI RST + TSI WAG (Rolling Stock) • TSI TAF (Telematics, Freight Services) + national requirements

  16. PKP PLK S.A. strategy regarding rail telematics • TAF implementation PLK strategy accepted; • Involvement in TAF CCG: - PLK is investing in TAF Common Components,- PLK is a test partner for Common Interface; • Active in TAF + TAP + WIMO discussions; • Preparing implementation (1st step): • - CE20 east-west on data from SEPE,- CE65 north-south on manualy entered data. (Wagons & Inter-Modal unitsOperational database)

  17. ENE MAI CCS RST OPE TAF/TAP INF Structural sub-systems Functional sub-systems . . . Railway Safety Directive • TSIs for both HS and CR systems: • TSI NOI (Noise) • TSI SRT (Safety in Rail Tunnels) • TSI PRM (Persons with Reduced Mobility) • TSI TAP (Telematics, Passenger Services) • TSIs for High Speed rail systems: • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operation) • TSI RST (Rolling Stock) • TSIs for Conventional rail system • TSI INF (Infrastructure) • TSI ENE (Energy) • TSI CCS (Control Command) • TSI OPE (Operational) • TSI RST + TSI WAG (Rolling Stock) • TSI TAF (Telematics, Freight Services) + national requirements

  18. PLK SMS(safety management system) ACCEPTED by Polish NSA + involvement in international works

  19. Thank you very much for your attention

More Related