1 / 19

Presentation Outline

SAFCA Natomas Levee Improvement Program Central Valley Flood Protection Board Briefing February 26, 2009. Presentation Outline. NLIP Overview Construction Phasing Schedule & Cost Estimates Construction Segments Sacramento River, American River Natomas Cross Canal, PGCC, NEMDC

dafydd
Download Presentation

Presentation Outline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SAFCANatomas Levee Improvement ProgramCentral Valley Flood Protection Board BriefingFebruary 26, 2009

  2. Presentation Outline • NLIP Overview • Construction Phasing Schedule & Cost Estimates • Construction Segments • Sacramento River, American River • Natomas Cross Canal, PGCC, NEMDC • Canal Relocations, Borrow Sites • Environmental Constraints • Program Q & A • Phase 2 Crediting Request

  3. Natomas LeveeImprovement Program • Part of comprehensive flood risk reduction program for Sacramento area • Being carried out as part of the federal-state-local American River Common Features Project • Central Valley Flood Protection Board is the Non-Federal Sponsor • SAFCA is the Local Sponsor

  4. Identified Flood Risks • Inadequate Levee • Height • Instability – Geometry, • Underseepage, etc. • Encroachments • Channel Erosion

  5. Program Objectives • Provide 100-year flood protection as quickly as possible • Provide 200-year flood protection over time • Ensure that new development does not substantially increase the expected damage of an uncontrolled flood

  6. Levee Seepage Concerns

  7. Waterside Levee Encroachments

  8. Sacramento River Bank Erosion Sites

  9. NLIP Permit Phasing

  10. Program Cost Estimate Construction $421 M ROW $90 M Mitigation & Permit $28 M Engineering & CM $79 M Total $618 M

  11. Anticipated 2009 Activities SREL – 1 Early 2009 (Reaches 1-4A) NCC – 2 Early 2009 (Reaches 1-7) SREL – 1B Late 2009 (Reach 4B) SREL – 2 Late 2009 (Reaches 5A-9B)

  12. Sacramento River East Levee Adjacent Levee Design Concept

  13. Major Borrow Sites Brookfield Airport North Binford/DeYoung, Horangic, Bianchi, Dhaliwal, Hants, Elkhorn South Site I-5 South Fisherman’s Lake Krumenacher Twin Rivers School District Stockpile

  14. Irrigation and Drainage Canals • Relocated Elkhorn Canal - North of Teal Bend - SREL-1B - South of Teal Bend - SREL-2A • New GGS/Drainage Canal - North of Teal Bend - SREL-1B - Teal Bend to I-5 - SREL-2A - South of I-5 – Phase 4b Project • Relocated Riverside Canal - SREL-3

  15. GGS/Drainage Canal • Excavated Soil Reused for Irrigation Canal Embankment (or Levee) Construction • 23,000 linear feet • 250,000 cubic yards • excavation • 600 lf 8’x6’ Arch Culverts • Dewatering

  16. Elkhorn & Riverside Canals • Replaces Existing NMWC Canals • 41,000 linear feet

  17. Environmental Constraints • Swainson’s Hawk • Giant Garter Snake • Cultural Resources

  18. Requested Actions from CVFPB March 2009 CVFPB Meeting Modify permit # 18159-2 18159-3 Adopt New CEQA Findings related to Supplemental EIR

  19. ProgramQuestions?

More Related