An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Improvements and Bond Construction UpdateFacilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE EMPOWER

  2. Agenda • Completed Construction Projects • PCC Learning Resource Center • LAC Central Plant • Current & Upcoming Construction Projects • LAC South Quad Complex • LAC Learning Resource Center • LAC Building A, Student Services Retrofit • LAC Math Technology Building • LAC Parking Structure • LAC Infrastructure Improvements – Phase 3 • PCC Central Plant • PCC Industrial Tech Phase 1 • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building C Retrofit • District Wide Building Needs Assessment Projects • Toilet Improvement Projects • Quick-Start Projects • ADA Projects • Lighting Projects • Classroom Improvement Projects • Recently Completed Facilities Improvements • Important Ongoing Initiatives • Planned Phasing of Future Projects • Q & A

  3. Completed Construction Projects PCC Learning Resource Center – Measure E 2002 • Construction Complete • Modern Facility with Computer Lab and Multimedia • Stand alone Data Center. Provides District IT redundancy • Bridge to building E • Design elements move towards energy efficiencies • Ribbon cutting held 9/17/08

  4. Completed Construction Projects LAC Central Plant – Measure E 2002 • Central Plant equipment, Public Safety, & Field House for Athletics • Final FF&E installation underway • Plant ready for operation and awaiting completion of LRC & SQC • Construction Complete • Anticipated startup 12/05/08

  5. Current and UpcomingConstruction Projects Construction approx. 89% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office Multipurpose room State of the art Board Room Substantial completion anticipated 1/09 South Quad Complex – Measure E 2002

  6. Current and UpcomingConstruction Projects Construction 91% Complete Adds 10,000 ASF to existing building Substantial Completion Anticipated January 2009 LAC/Learning Resource Center – Measure E 2002

  7. Current and UpcomingConstruction Projects Design Development to be submitted this month Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction 7/09 LAC Building A – Student Services Retrofit Measure E 2008

  8. Current and UpcomingConstruction Projects Completed Schematic Design (June 2008) Currently in Design Development phase Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction 2011 LAC Math Technology Building – Measure E 2008

  9. Current and UpcomingConstruction Projects LAC Parking Structure – Measure E 2008 • Planning initiated for approximately 900 Vehicles • To be procured under “Design Build Delivery” method • To be located Southeast corner of Lot J adjacent to the Verizon building • Photovoltaic Electrical Generation Array on top level of structure • Anticipated start of construction 2009 Proposed Math Technology Bldg. Lot J Proposed Parking Structure Loc. Verizon Bldg.

  10. Current and UpcomingConstruction Projects LAC Infrastructure Improvements – Phase 3 Measure E 2008 • Planning underway with engineers • Completes chilled water lines to North side of campus • Includes other major utility upgrades; Reclaimed Water, Domestic Water, Data, etc. • Existing building HVAC systems to be upgraded in synch with infrastructure improvements • Coordinated with modernization and quick start projects

  11. Current and UpcomingConstruction Projects Houses Central Plant equipment and Maintenance and Operations facility Construction Approximately 99% Complete Currently provides chilled water to the PCC LRC PCC Central Plant – Measure E 2002

  12. Current and UpcomingConstruction Projects PCC Industrial Technology Center Phase 1 Measure E 2002 • Modern facility houses Welding Department and other trade programs • Construction is 45% complete • Replaces existing antiquated structures • New Northern face of the campus • Completion anticipated summer 2009

  13. Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 • 90% construction documents submitted • Swing space planning completed 9/2008, construction of swing space starts Spring 2009 • Anticipated start of MDAB construction Summer 2009 • To be completed in two phases

  14. Current and UpcomingConstruction Projects PCC Building C Retrofit - Measure E 2008 • To be designed by Hill Partnership Architects • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space to be located on PCC Campus (TBD) • To be completed concurrently with MDAB project • Anticipated start of construction Spring 2010

  15. Current and UpcomingConstruction Projects District Wide Building Needs Assessment Project Measure E 2008 • Toilet Improvement Projects • Quick-Start Projects • ADA Projects

  16. Current and UpcomingConstruction Projects District Wide Building Needs Assessment Projects Measure E 2008 • Lighting Projects • Classroom Improvement Projects

  17. Recently Completed Facilities Improvements Building “B” and “E” Boiler Replacement • Replaced existing boilers, pumps, expansion tanks and common flue with new equipment via helicopter lift. • A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers. • Completed 10/2008

  18. Recently Completed Facilities Improvements Additional Facilities Improvements • LAC upgrades: • Veteran’s Stadium scoreboard and PA system upgrade • Building K upgrades – Exterior door paint, room 111 floor refinishing • PCC upgrades: • Building AA – Built wall for information desk, installed carpet, and power upgrades • Building BB – Carpet and window blind installation • Building CC – Installed fans in gym • Building DD – Carpet and window blind installation • Building EE – Window blind installation • Building MM – Exterior paint, replaced doors and awnings, re-glazed windows, and replaced fascia boards

  19. Important Ongoing Initiatives LBCCD Coming Advancements • Master Landscape Project • District Wide Energy Efficiency Improvements • Electronic Marquee Signage • Wayfaring and Building Signage • Campus Lighting Improvements

  20. Planned Phasing of Future Projects Currently Planned Schedule • 2008-09 • Parking Structure – Design/Build concept • Anticipate awarding bid Spring 2009 • Moving Warehouse from PCC to Alteon Building at LAC – TBD • Moving LAC Building A into Swing Space – Spring 2009 • Install portables at PCC for Swing Space – Spring 2009 • LAC/PCC Building Needs Assessment Projects • Bathroom Improvement Projects • Quick-Start Projects • Lighting Projects • Classroom Improvement Projects • Infrastructure Projects • Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC • Finalize Master Landscaping and Signage plans • Marquee signage anticipated to be installed March 2009

  21. Planned Phasing of Future Projects Currently Planned Schedule • 2009-10 • Begin construction of Building A at LAC • Anticipating July 2009 start • Begin construction of Buildings CC, DD, and EE at PCC • Anticipating July/August 2009 start • Begin Schematic Design for Buildings C and F at LAC • Submit plans to DSA no later than March 2010 • Begin Master Landscaping and Signage Initiatives • Continue District Wide Energy Efficiency Improvements • Phase IIA • Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc • Phase IIB • Upcoming advancements include connecting current buildings to Central Plant infrastructure

  22. Planned Phasing of Future Projects Currently Planned Schedule • 2010-11 • Anticipated Construction completion of Building A at LAC – January 2011 • Submit plans to DSA for Math/Technology Building at LAC • Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Spring 2011 • Construction completion of Buildings CC, DD and EE at PCC • Begin construction of Buildings AA and BB at PCC • Anticipating January/February 2011 start

  23. Planned Phasing of Future Projects Currently Planned Schedule • 2011-12 • Begin construction of Math/Technology Building at LAC • Submit plans to DSA for M/N Building at LAC • 2012-13 • Anticipated Construction completion of Buildings C and F at LAC – December 2012 • Anticipated Construction completion of Math/Technology Building at LAC – December 2012 • Begin construction of Buildings M/N at LAC – January 2013 • Anticipated Construction completion of Buildings AA and BB at PCC – June 2013

  24. QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER