An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. What has been learnt from LS1 K. Foraz

  2. Content • Preparation phase • Implementation phase • Safety • Resources • Discrepancies between baseline and reality Disclaimer: This is a 1st debriefing – the LS1 post-mortem day will be organized in 2015  Feedback got by Group Leaders (those available) K. Foraz - LHC Performance Workshop

  3. Preparation phase "By failing to prepare you are preparing to fail.“ B. Franklin Preparation phase includes • What  Goal & Collection and prioritization of activities • How  Work Package analysis meetings, procedures • When ….diditstart ? For the 1st time in my life I’m feeling I should've done something about my weight K. Foraz - LHC Performance Workshop

  4. Preparation phase - Goal • Activities to be performed according to the following priorities: • P0: Safety • P1: Beam to 7TeV, nominal performance • P2: Reliable operation improvement • P3: CERN approved projects • P4: CERN non approved projects • Main activities • LHC • SMACC • Repair He leaks (sectors 3-4 and 4-5) • R2E (mainly Pt1, Pt5 and Pt 7) • Injectors • CPS - Installation of the new access systems, Cooling and ventilation maintenance & renovation, Upgrade of the RF systems,.. • SPS: Consolidation of 18kV transformers, Replacement of irradiated cables in BA1 and in TCC2, Installing new optical fibbers, New coated magnets in BA5 • Maintenance of all the systems after 3 years of operation K. Foraz - LHC Performance Workshop

  5. Preparation phase - What • Collection and prioritization of activities: • Plan.cern.ch • Unique repository, useful for communication between groups  Groups had a clearest picture of the support to be given to other groups • Attenuate bad surprises • Ease the prioritization process for LS1 team, focusing only on discordance points But • Should have come earlier • Not all activities were announced • Resources details redundant with APT ? Are they really needed in plan? In the future ? • Use plan.cern.ch for collecting future activities • Give enough time to groups to fill data • Improve the tool to better fit with needs: redundancy with other tools, granularity between items + + + ~ ~ ~ K. Foraz - LHC Performance Workshop

  6. Preparation phase - What • Collection and prioritization of activities: • LS1 day - Plenary session • Very useful to have a better understanding of the requests • Gave a good overview on LS1 activities • Should have been scheduled earlier • “Why not a recurrent annual meeting?” In the future ? • Organize LSx day(s) • On an regular basis + + ~ K. Foraz - LHC Performance Workshop

  7. Preparation phase - How • Items covered: • Description • Conditions prior to start • Schedule • Perimeter of worksites • Storage areas • Logistics • Risks and compensatory measures • Radiological management • Work Package analysis meetings • Organized by coordination teams • Gathered all stakeholders around the table • Gave the opportunity to understand what other groups intend to do and how • Lots of points clarified • Procedures: Well prepared • Review • External review fruitful for SMACC In the future ? • Work Package analysis & Procedures Mandatory step • External review: identify as soon as possible, which projects are concerned + + + + + K. Foraz - LHC Performance Workshop

  8. Preparation phase - When • Main projects • SMACC project: 4 years of preparation • R2E: 3 years of preparation • Contracts: Up to 30-40wks to get a contract  technical specification from clients shall be ready in due time • Recruitments - Flexibility posts: staff have to be hired 1.5-2.5 years prior to a shutdown In the future ? • “The man who is prepared has his battle half fought” Miguel De Cervantes • Keep allocating adequate & sufficient resources for preparation, in due time + + K. Foraz - LHC Performance Workshop

  9. Implementation phase “Organize, don't agonize.” Nancy Pelosi Coordination Scheduling Documentation Daily management Information exchange K. Foraz - LHC Performance Workshop

  10. Implementation phase - Coordination • Coordination meetings held on regular basis • Good feedback from groups • Some concerns reported: • North Area coordination: enhance group participation and publicize EATM meetings • 7 injectors areas =7 meetings. Some rationalization ? • Dedicated project meetings (SMACC, R2E) • Solving technical aspects, daily schedule + ~ ~ + • Enhance team spirit & ease information flow • Very good follow-up on fields + + K. Foraz - LHC Performance Workshop

  11. Implementation phase - Scheduling • Schedules kept up to date by coordination teams & progress regularly presented: presentations, dashboard • Project schedules • Coordination scheduler part of the project for LHC • Transparency of schedules for surface activities • Hard process for some groups, mainly during the phases of production and surface validation • ALARA: Activities scheduled as late as possible in certain areas • Dose optimization • Give few margin, and lead to stress at the end of the activity In the future ? • Keep a member of coordination team (scheduler) within projects • Improve availability of internal production and tests schedules • To see how to optimize the start of an activity w.r.t. cooling period + + ~ + + ~ K. Foraz - LHC Performance Workshop

  12. Implementation phase - Documentation • Configuration Management • Hardware baseline is kept up to date thanks to ES, HWP, Tests procedures, ECRs • 104 ECRs treated in LHC, ~60 in injectors • 90 ES, Procedures… • Layout database update • MAD/X file already up to date • 2-3 months of update are still needed !! • Vacuum, instrumentation (PVSS), electrical circuits, R2E still need to be treated • Machine drawings with release notes still to be issued – “automatic machine drawings” In the future ? • ECRs presentation in (LSC), LMC, IEFC to be kept on regular basis • ECRs to be edited in due time K. Foraz - LHC Performance Workshop

  13. Implementation phase – Daily management • Stakeholders were the same as during the installation eased the whole process  reactivity • Access … sinew of war • Lifts breakdown • Roadmap for LHC lift exchange in the pipeline • Logistics • Good management of material logistic • TREC is working for underground transport, but shall be improved for surface transport + + ~ + + K. Foraz - LHC Performance Workshop

  14. Implementation phase – Information exchange • Information flow fluid, but we can still improve: • the information has sometimes difficulties to go down to worksite!! • Information, sometimes hard to find • Project: edms, indico, sharepoints… • Up-to date version of schedule • Understanding of the impact of a service unavailability on other equipments In the future ? • How to improve information flow down to the worksites • Rationalized project’ information 1web page indicating hyperlink to projects ? • A repository of services unavailability and impact ? + + ~ ~ ~ K. Foraz - LHC Performance Workshop

  15. Safety • Good Statistics (until September 2014) • approximately 1.5 million hours of LS1 work delivered • 22 minor accidents (no absence) • 11 accidents with 98 days of absence • Frequency rate: 7.3 & Severity rate: 0.07 • New work supervisors and organization of safety • Consensus: “safety rules and training arrived too late !!” In the future ? • Training of work supervisors by safety coordinators ? • Establish safety rules prior to the start (6 months at least) + + ~ ~ K. Foraz - LHC Performance Workshop

  16. Resources Feedback from Group Leaders • Recruitment of our staff • Need 1.5 – 2.5 years before the start • Non LHC facilities suffered from lack of resources, as there were re-oriented to main projects • Temporary detachment • Very useful • To be included before the start of LS • Partial detachment – difficult to handle • On the contractor’s side • Maintenance contract  hard to find adequate personnel • Unforeseen/last minutes work  exotic prices ~ + ~ ~ ~ K. Foraz - LHC Performance Workshop

  17. Discrepancies between baseline and reality • This part will be detailed during the LS1 post-mortem day. First feedback: • All baseline activities were done….and more • Additional activities • There were those unexpected : LHC QRL leaks, 15%-> 30% of splices… • Those were those who «somebody» knew but forgot to inform the community !! Those induced additional workload to the usual support groups In the future ? • Review plan list regularly • Learn to say NO + + ~ K. Foraz - LHC Performance Workshop

  18. Conclusions Disclaimer: Many other information were provided, but 20’ is too short Despite all the points of improvements underlined, so far the LS1 is a success • Thanks to the strong commitments and reactivity of our staff • Most of the groups, and all the projects were very well coordinated • The priorities defined by LS1 project leader were respected: • Safety, • Quality, • Schedule Thank you ! K. Foraz - LHC Performance Workshop