Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August

Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August (still at 50% of FR4 sheets delivered by ELTOS) – Restarted in Sept. PNPI : M3R4-M2R4 under production LNF : production of M5R3 started

december
Download Presentation

Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August (still at 50% of FR4 sheets delivered by ELTOS) – Restarted in Sept. PNPI : M3R4-M2R4 under production LNF : production of M5R3 started CERN : waiting for M2R2-M2R1 (should be moulded together !) PZ-FE – FI : in stand-by (enough already done) – Additional material needed Problems Quality tests at the company have improved Still some problems with the new moulds – Erratic quality - may be due to thickness of FR4 sheets (0.8 mm up to 0.95 mm, marginally in acceptance) - under investigation, probably solved Feedback to Eltos given – promise not to exceed 0.9 mm Production yield 60/1300 + panels discarded in PZ/FE LNF team (Alvaro & co.) continuing to check the planarity of all panels ROME2 panel-o-meter with new measuring technique ????? P. Campana – LHCb Week – Chia – September 2004

  2. HV bars 40% of the material delivered: M3R3-M3R4-M1R3 finished, M2R3-M2R4-M5R3 under completion the rest by the end of the year FR4 frames M2R4-M3R4-M3R3-M2R3 delivered M5R4 1/3 ordered the rest to be ordered now (waiting for offer) Faraday cages Finalizing INFN layout – to be replicated to PNPI (order next year) OPB 2100 red+1400 yellow +120 DCRO delivered (needed INFN 1300 red+950 yellow; CERN ? Which type ? In total 752) SPB needed to test chambers >> PZ <<!

  3. Honeycomb for M1 Waiting for a global offer from Imatec (cut included) [ special gas angular pieces under preparation ] M1 Panels 2 companies contacted (Lugano [Rm2]+Faenza [GEM]) Tests underway (order next year) Rest of the material R+C+pins+spacers+gas connectors delivered HV plastic distributors ordered (50% delivered)