1 / 14

Jack Bartley Former Deputy Director of EH&S Presentation to LBNL Safety Coordinators Meeting

McCallum-Turner Integrated Safety Management System Evaluation at Lawrence Berkeley National Laboratory Corrective Action Plan Overview. Jack Bartley Former Deputy Director of EH&S Presentation to LBNL Safety Coordinators Meeting April 13, 2007. Today’s Presentation.

donniej
Download Presentation

Jack Bartley Former Deputy Director of EH&S Presentation to LBNL Safety Coordinators Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. McCallum-TurnerIntegrated Safety Management System Evaluation atLawrence Berkeley National LaboratoryCorrective Action PlanOverview Jack Bartley Former Deputy Director of EH&S Presentation to LBNL Safety Coordinators Meeting April 13, 2007

  2. Today’s Presentation • Key milestones in developing the CAP • CAP schedule • CAP organization • Corrective Action summaries • Causal factors • Crosswalk from Peer Review CAP • Summary

  3. Key Milestones in Developing CAP • January/February 2006 - ISM Peer Review & Report • March/April 2006 - Back-look and Root Cause Analysis • June 1, 2006 - Peer Review CAP submitted to BSO • June/July 2006 - DOE Validation Review & Report • September 2006 - McCallum-Turner (M-T) Review • November 2006 - McCallum-Turner ISMS Evaluation Report • March, 2007 - McCallum-Turner review of draft ISM CAP • March 30, 2007 - Final ISM CAP submitted to DOE-BSO

  4. Seven Corrective Actions

  5. Major Activities Supporting the Seven Corrective Actions • 58 Major activities/outcomes planned • 37 (64%) scheduled for completion by 10/1/07 • 54 (93%) scheduled for completion by 12/1/07 • 4 ( 7%) scheduled for completion in 2008 FY07 PEMP: B+ = 90% (34 of 37) of major activities scheduled for completion by 10/1/07 are completed

  6. CAP Organization • Overall “front matter” • Background/History/Objectives/Organization • How the CAP was developed • Senior management commitment & oversight • Project tracking and change control • Commitment to ISM continuous improvement • CA Specific “front matter” • Objectives • Crucial assumptions • Major activities • Condition/Status as of 12/1/07 • Final closure

  7. CA-1 Re-emphasize expectations for line accountability and responsibility for safety and strengthen implementing processes to reflect these principles • Summary of major activities completed • Safety communications plan in-place and working • “Safety line management chain” and “work leader” now defined • Walk-around requirements revised, tailored training being provided • New Job Hazards Analysis (JHA) process requires direct interaction between work leaders and workers, resulting in specific authorization • 2006 Integrated Functional Appraisal (IFA) focused specifically on implementing formal authorization • Summary of major activities planned • Enhance safety expectations used in PRD process for HEERA supervisors and managers • Develop a safety performance assessment process for non-HEERA Safety Line Managers • Modify institutional ISM Plan, Job Hazards Questionnaire (JHQ) process and Division S/A process to support implementation of Safety Line Manager concept • Develop and initiate training of non-HEERA Safety Line Managers • Add requirements for worker involvement in policies and ISM Plans • Implement the new JHA process

  8. CA-2 Restructure and refine institutional EHS/ISMS documents to clarify their inter-relationship and provide overarching set of safety principles and expectations • Summary of major activities completed • Formal procedure developed for Safety Review Committee (SRC) review and approval of ES&H Manual (Pub 3000) changes • Over 18 changes formally reviewed and approved by the SRC since September, 2006 • Division Safety Coordinator and EHS Liaison roles and responsibilities revised • Summary of major activities planned • Clarify and articulate the hierarchy of ISMS documents • Develop a set of high level institutional safety goals • Formalize procedures for the annual WSS process

  9. CA-3 Increase the rigor of the performance management process • Summary of major activities completed • Performance Evaluation and Management Plan (PEMP) sets annual goals and objectives, and performance is measured to these • 2006 IFA and MESH reviews focused on significant ES&H concerns • Annual Division Self-Assessment criteria revised for 2007 to reflect institutional goals and objectives • Lessons Learned/Best Practices up and running • Trending and analysis training for Subject Matter Specialists (SMEs), Coordinators and Liaisons • Summary of major activities planned • Develop methodology for reviewing effectiveness of assurance systems • Apply analysis and trending methodology to FY07 ESH S/A results • Implement procedures for incorporating lessons learned and corrective actions into an overall Issues Management Program • Develop mechanisms for collecting and utilizing sub-contractor and vendor on-site safety record in procurement processes

  10. CA-4 Fully implement an integrated corrective action management system • Summary of major activities completed • Increased staffing for ESH assurance • CATS database developed and functional • Monthly review of CATS actions with Divisions and COO • Trending and analysis training being provided to safety managers and staff • Summary of major activities planned • Develop and implement Issue Management Program • Develop and implement ESH Technical Assurance Program

  11. CA-5 Strengthen Laboratory self-assessment processes • Summary of major activities completed • Revised 2007 Division S/A criteria • Summary of major activities planned • Develop and implement a risk-based gap analysis methodology to prioritize assurance activities • Develop and implement ESH Technical Assurance Program • Initiate assurance system effectiveness review • Revise Division S/A Program Manual

  12. CA-6 Increase the rigor and consistency of the work planning and control processes • Summary of major activities completed • Developed a new Job Hazards Analysis (JHA) process that incorporates hazard assessment, identification of controls and authorization of work • Upgrading HEAR (Hazard, Equipment, Authorization, and Review) database functionality • Enhanced oversight of construction-related work • Streamlined the penetration (Dig) permit process • Summary of major activities planned • Conduct JHA pilots, revise process, roll-out institution-wide • Revise Safety Analysis Document (SAD), establish Un-reviewed Safety Issues procedure and shielding policy for ALS (Advanced Light Source Division) • Complete refresher training on JHA process in Facilities • Complete HEAR upgrades • Develop and implement formal process for pre-construction O&M (Operations and Maintenance) maintainability reviews

  13. CA-7 Assure that the ISMS-related elements of LBNL-UCB relationship are consistently articulated and clearly understood • Summary of major activities completed • UCB/LBNL Research Collaboration Steering Committee established in July 2006, Chaired by Deputy Director Fleming and Vice Chancellor Burnside • ES&H Sub-committee discussing mechanisms for assuring equivalent safety for LBNL-funded work conducted on UCB campus • UCB and LBNL laser safety training now equivalent • Summary of major activities planned • Modify UCB/LBNL Partnership Agreement as needed • Develop an initial listing of locations and individuals performing LBNL-funded work in UCB space • Develop and implement a process for assuring equivalent protection for LBNL-funded work at UCB

  14. Summary • Accepted all seven recommended actions as the foundation of the CAP • CAP builds on the strengths/noteworthy practices identified by M-T ISMS review • Incorporates and builds on ISM Peer Review corrective actions and 10CFR 851 related program changes • CAP will improve implementation of ISM in key areas and help us sustain excellent safety performance • UC/LBNL Contract Assurance Council will review the status of ES&H performance progress and CAP implementation

More Related