PMG Agenda November 1, 2000

PMG Agenda November 1, 2000. Overview (Weerts) Detector status Reportable milestones Summary. Status Overview: SMT. Silicon (more details Demarteau) Production winding down DONE South silicon detector (SMT-S) Ready to move since ~Oct.26 Two dry runs completed Installation next week

draco
Download Presentation

PMG Agenda November 1, 2000

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMG AgendaNovember 1, 2000 • Overview (Weerts) • Detector status • Reportable milestones • Summary

  2. Status Overview: SMT • Silicon (more details Demarteau) • Production winding down • DONE • South silicon detector (SMT-S) • Ready to move since ~Oct.26 • Two dry runs completed • Installation next week • North silicon (SMT-N) • 2 barrels done, 3rd barrel done tomorrow • 1 out of 6 disks to complete • Start assembly into half cylinder next week • Ready for DAB at beginning ~ Dec 12 • H-disks ( need 4) • 3 H disks ready • 10% test • Continuing; 81K channels tested • Have taken cosmic events • Take barrel/disk combination out • Put H disk in

  3. Fiber Tracker Status - Waveguides • Waveguide Production and QC continue • Axial replacements (2+1?) • Stereo remakes (10) • Installation • South • All installed • So far 2 to be replaced • QC Data on about 120 (34 to go) • 90 Fully analyzed • 3(4) bad/6 marginal • LED system still problematic at times • Done by Monday • North Started but now on hold • Installed CPS North • No QC data yet • Need to install all LED cables and test • CFT installation starts when South done • QC in real-time with installation • Too much handling of WGs • Some damage in evidence

  4. Fiber Tracker Status • VLPC Cassettes • Continues • Electronics availability continues to be a problem • WG QC vs. Cassette Charact.

  5. Status Overview • Central Muons (94 PDT’s) • Commissioning continues • Completing electronics installation • Gas system (pipes & pumps) design complete (JK) • Gas recycler/cleaning started (JK) • Forward Muon detectors • Installing

  6. Status Overview • Trigger & DAQ • Details from Blazey last time • Commissioning is still okay, but….. • Final hardware arrival is a worry • L2 VME-Alpha boards still a concern. NO working board yet. Now have 25. Not good • Manpower identified at Fermilab ( team CD) • L3 board production a worry: vendor visit • Technical manpower an issue: Varelas, Johns @FNAL starting December • Online • In use at low rate, not on critical path • Placed order for logging machine made

  7. Status Overview; Electronics • Electronics • Calorimeter • Preamp installation/commissioning underway (10k installed, 12 PS ready, cooling installed) • BLS has vendor delays • Motherboard: 1250/500/165 • need/bare/stuffed • Daughter cards 5000/3250/950 • Daughter card: 300/week vendor (end Jan. 01 complete) • Muon • PDT electronics - done • Scintillator - ~done • MDT - done • Readout electronics • Readout 100% • Fanout, MFC: done; in use

  8. Status Overview; Electronics • Tracking Electronics • Si Interface Card • 160 pc production order released • First deliveries Nov 3. • Testing will start; difficult • Analog Front End boards • Released production start • Taking some $$$ risk to help schedule • 50% in November ??; rest January • MCM going • Company visit next week • Production starts during visit : produced 100; projected rate: 25/day; Need 1900. • Adapter card • 34 with new design at FNAL • Power supplies • VICOR current schedule Dec-Jan • Some power supplies coming in earlier ( still January)

  9. Installation • Progressing well. • Will take shield down next week. • Dry runs of SMT-S completed and successful. Next step is real installation ( next week) • Waiting to hang last LARGE C layer pixel plane ( survey) on truss; will happen today or tomorrow  trusses ready to roll into collision hall. • Install SMT-S next week; start Monday • Mechanical installation going well

  10. Summary • Concerns • NOT Silicon anymore • Installation: lots of activity/m2;are careful • Electronics delays are THE concern for realistic commissioning • Vendor delays, parts availability • Willing to spend $ to fix if possible • Realistic & comprehensive commissioning before March 1 is vanishing