An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPERA Detector Preparation • Electronic Detectors: • status of installation • Brick preparation • lead production • BAM • BMS • Conclusions about the filling • CNGS beam status • Perspectives for the run in 2007 • Conclusions Detector Construction status report

  2. 1. Electronic Detectors Detector Construction status report

  3. SM1 SM2 Electronic detectors installation • All installed and running except: • VETO : commissioning start soon • HPT/SM2 : first half of 2007 Target tracker Veto Spectrometer: XPC, HPT, RPC, magnet BMS Detector Construction status report

  4. CNGS DB (Oracle) Event DB (Oracle) ASCII-2-Root Root • Alignment • Data analysis • Brick finding Gateway DB Eventbuilder • Time coincidence between subdetectors (merge sort) • Event classification wrt the beam UTC • Event header production CNGS Early Warning BMM • Connects theDAQs • Send flaggedcycles • Writes GPSdates Beam syncronizer Raw data DB • postGres (DAQ) • Oracle DAQ manager • Decodes CNGSearly warning • Flag the DAQ cyclewrt the beam ASCII ASCII ASCII HPTdaq TTdaq RPCdaq • Trigger cross-check? • Tests procedure • 105 sensors • Majority trigger • Same DAQ forRPC-XPC-VETO • 54 sensors • X-Y coincidence • L-R coincidence • N planes coinc? • 992 sensors … TTsensors … RPCsensors … HPTsensors DAQ Detector Construction status report

  5. 2. Brick Preparation - Lead - BAM - BMS Detector Construction status report

  6. Westfälische Wilhelms-Universität, Institut für Kernphysik, Münster Lead production Oct.-Dec. 2006 D. Frekers V. Pilipenko

  7. Development in QC • a-activity measured October 2006 • Edge control • Thickness control • Status of lead production in October 2006 • General situation: • We are getting into a much more stable production. Quality control is now routine also among the general personnel at JLGoslar Detector Construction status report

  8. Results of PbCa0.04 and PbCa0.05 a-activity measurements Oct-06 Detector Construction status report

  9.  activity measurements More on radioactivity  210Po : rebuilding from 210Bi , no migration visible Detector Construction status report

  10. Edge control Control improved by introducing one additional microscope with 4.5 x ocular in OPERA hall at JLGoslar site (see photo). Detector Construction status report

  11. Detector Construction status report

  12. Thickness control: • We introduced two additional sensors for the thickness control (see photo). Detector Construction status report

  13. flash light Thickness control: Both sensors perform line measurements. If the thickness of the lead is outside specs, an audio alarm signal will be issued and a light will flash. The rolling will stop. Detector Construction status report

  14. Ca content • Oct-2: decision was taken by Collab. Board to increase Ca content to PbCa0.07 • We produced 3 charges of the PbCa0.05. This increase of the amount of Ca in the lead gave again difficulties with rolling, i.e. keeping specs was not possible. The decision was then taken by JL Goslar to go back to the PbCa0.04. PbCa0.05 rolling

  15. Status of lead production • PbCa0.04 has enough amount of Ca to avoid corrosion on surface, which was also barely observed in case of PbCa0.03. Surface corrosion of the PbCa0.04 is under permanent QC. • truck-6, which was stopped due to problem of stickiness and corrosion on plates, has now been scrutinized and re-checked and delivered in November (feed-back so far OK). • production has now been reduced to <10.000 plates a day until BAM/BMS can ramp up to full performance. • next truck delivery foreseen in Jan-07 • to avoid production stop, a repository of pallets has been ordered -- ~7000 add‘l pallets will give a total of ~11000 pallets in a buffer (equiv. to 600.000 plates or 6 trucks). • 40 000 plates per day has been achieved Detector Construction status report

  16. OPERA Emulsion Workshop, Nagoya, December 2006 BAM Project Status Report S. Buontempo (on behalf of BAM working group) • Brick components • Lead pallet production • BAM fine tuning • BAM additional machines • Drum filling station Detector Construction status report

  17. Brick components – Nov 06 Al Spider : 100000 produced, 50000 delivered in Tecnocut Plastic protection : 50000 produced and delivered in Tecnocut Assembled spider+plastic protection : 5000 assembled and 3000 delivered in GS Plastic cover : 40000 produced, 20000 delivered in GS Al tape: all delivered in GS, Skate tape: all delivered in GS • CS box: • new prototype (20 pcs) produced according to Nagoya requests • 5000 being produced now Bar code labels: 2000 delivered in GS, all the rest ordered now. Skate thickness labes: 20000 being delivered this week all the rest to be ordered CS box glue: for 10000 bricks being delivered this week, all the rest to be ordered

  18. Brick components – Nov 06 Spider-Plastic protection thermal assembly tool Minor problems of mechanical stability of spider position, turned out to be VERY negative for brick precision. This solution was abandoned and pieces are now being glued. Net result is a longer assembly time (about a factor 2 !)

  19. Lead Transportation pallets 19000 pieces ordered (1000 spare). Delivered 18025 (according to Tecnocut). In order to increase the buffer in JL Goslar, Uni Muenster has ordered additional 6600 now. Delivery in 30 days.

  20. BAM fine tuning • Lead Dispatching line : DONE • Lead transportation line: DONE • 5 piling pressing stations: DONE (need to refurbish the emulsion storage containers) • Al wrapping machine n.1 : mechanically DONE, being registered today • Al Wrapping station n.2 : DONE • Skate station : DONE • CS box station : DONE • Data matrix station: DONE • brick dimension control : DONE

  21. BAM additional machines • Skate Additional Label : Being delivered in GS in next week (for 10000 bricks) • Skate additional label machine: being ordered in GS • Glue for CS box: Being delivered in GS in next week (for 10000 bricks) • Glue dispenser for CS box: Being ordered in GS in next week

  22. Drum station Supposed to be delivered this week in GS: Postponed for mechanical defects:TecnoCut found some problems in the precision of the pusher devices which demand some more fine tuning. This operation is much cheaper to be done in their site than in underground lab. For this reason the shipment has been postponed. Most probably to january 8th as there are difficulties to get the material and the re- machining of the pieces before X-mas.

  23. BAM production schedule • Today and Monday: re-printing of DM on old bricks (with DM at lower level) • 250 bricks (mechanical) are already produced (piling-pressing) with light on. Next week they will be completed with Al wrapping and skate + CS with new glue + additional label (if delivered ?) • The mechanical quality of these 250 bricks is MUCH better that the first 1000 produced in october. • The piling is done with 5 stations with a speed of 50 bricks/hour (10 brick/station/hour). • As soon as the 250 bricks are completed we plan to start the real brick production (presumably in second half on next week if all material – glue/label is delivered).  the goal is to reach 3 drums / day in january as a routine speed ( 702 bricks  ~40 000 lead plates)

  24. BMS report • Brick filling and extraction • Situation after the October run • BMS commissioning progress • Improvements, solved problems • Mechanical interventions • Filling rate issue • Fence • Brick production restart • Final tuning to be done with final bricks Detector Construction status report

  25. Brick filling and extraction Until now: 45 rows of bricks inserted, following BAM production, 7 rows extracted to get selected bricks and reinserted In the detector: 13 rows Cside 12 rows Rside + 10 rows out for matrix code repositioning Detector Construction status report

  26. Brick filling and extraction • Problems encountered: • - high friction • CS box bent or not attached solidly • matrix code not well engraved • All those points expected to be solved with next brick production Detector Construction status report

  27. BMS commissioning after the run • New versions of BMM, Supervisor and operator interface • Database updated to correct bug on sign convention for detector side • - Many progresses in automate programs, several bugs corrected • loss of control in vertical moves fixed • problem in inserting a 3rd code reader found • problem of message losses after incidents understood Matrix code readers Detector Construction status report

  28. Mechanical interventions • - Drum cage modifications on 5/6 drums: 9th level access • - Fixation of loading stations • Fixation of 4 surveying cameras (2 on each platform) • new supports for some better adapted sensors (to signal brick presence on carrousel and drums) • study of a shade for BMS lamps (with red filter towards tray) Red filter adaptation successful and adequate for avoiding spurious sensor disconnection (TT light leaks) Detector Construction status report

  29. Filling rate issue • Until now, no effort was done to improve speed of the BMS • priority was given to the security of operation. • Some room for improvement – transitions • speed of individual movements • Present timing for detector filling: 1 hour per row 2 shifts needed at present speed to insert 4 drums/day. Looking for factor 2 speed increase ! Detector Construction status report

  30. Security fence Final fence ordered to BMI-Axelent firm is built and arrives next week in Gran Sasso Detector Construction status report

  31. Brick production restart Very crucial points for BMS: CS box fixation, final skate config. and M-code engraving Waiting presently for bricks of the future production: see Salvatore report, delivery problems Need of bricks representing the new production to perform the final BMS tuning Detector Construction status report

  32. Filling the detector • Drum : 9 rows for a semi wall  9x26 = 234 bricks / drum • Wall : 64 lines of 26 bricks per semi wall  3328 bricks / wall • Target : 31 wall per Super-Module  103168 bricks / target • Filling strategy: • leaving 3 rows empty at the bottom and top  3016 bricks / wall • leaving 2 wall empty on both side of the target  81432 bricks / target •  ~79 % of the initial target mass • Filling schedule: • one SM : 27 walls, 58 lines , 116 trays  3132 trays to be filled  348 drums • assuming 15 drums / week  23.2 weeks • 6 months per Super Module Detector Construction status report

  33. 3. CNGS Status Detector Construction status report

  34. Today we have removed one shielding block of the side shielding of the CNGS reflector. The radiation was low enough to stay beside the reflector for some minutes and to have a direct look to the possible leak locations. The leak in the closed water cooling circuit of the reflector was located immediately: The insulating ceramic part of the most downstream tube connecting the outer conductor with the water drain pipe is broken (see attached picture). The reason for this rupture has to be understood. Most likely is due to additional clamps that provide vapor tightness (a condition that could be negotiated), which might overconstrain the system. These clamps could be removed quite easily, an operation that we would then like to do at all the other connecting tubes of the reflector and also the horn. We are investigating the possibility for repair of the connecting tube in-situ, i.e. without moving the reflector, but just the side shielding. In the next days we will prepare a detailled plan of the interventions during this shut-down, such that CNGS is ready for the 2007 re-start. Detector Construction status report

  35. Detector Construction status report

  36. Detector Construction status report

  37. Status of the Horn 1 • The most important modifications concern the water cooling systems (sprayers lines and drain tubes) TIG Welding (Al 6083) Helicoflex SS collar Ceramic muff with Titanium flanges Tin/Ag O-ring Old version SS bellow (316L) ARCLEX insulators cannot be used in wet areas Detector Construction status report

  38. NUMI : Two horn water system leaksHorn 2 in February 2006, Horn 1 in August 2006 Have brazed ceramic electrical insulators on horn water lines They are strain-relieved with invar+ceramic clam-shells On horn 1, developed a 7gal/day water leak on line to spray header On horn 2, leak on suction line drew air in, reducing amount of water ejector pump could remove from horn collection tank Both ceramic sections were successfully replaced Speculate braze corrodes… planning to switch from brazed to a shrink-fit ceramic/steel connection for spare horns Detector Construction status report

  39. NUMI Horn 2 going back in shielding after suction line replacement New ceramic Water suction line Detector Construction status report

  40. T2K Horn design Supply lines Welded bellows with ceramic isolation Auxilliary drain lines

  41. Other beam aspect under investigation: Timing: Investigations with portable atomic clock. Found at CERN the reason for other 110 ns of the 600 ns of extra delay remaining. Stopped due to the beam problems. We will see how to continue in the next months at CERN without beam and ,also at LNGS. Database: Claim that all the problems were fixed during the MD devoted to CNGS two weeks ago. Unfortunately we could not investigate better due to lack of beam/ We have some doubts that all the problems are solved. In the CNGS data there are from time to time missing spills and inconsistent data (e.g. protons + secondaries after the target but no muons). Padova is looking if in the data there are neutrino interactions not on-time. SPS: Stable condition with 3 CNGS cycles not reached yet, tuning interrupted by the reflector problem. Continue in the next days with dry magnet cycles or some beam to the dump Detector Construction status report

  42. 4. Perspectives for the run in 2007 Detector Construction status report

  43. 2007 Draft SPS schedule • SPS physics run: • Start: 26/5/2007 • End: 7/11/2007 • 141 days after having excluded the MDs • ( 200 days expected ) • proton intensity on target • canonical 4.5 1019 pot • today performance 2.3 1019 pot • SPSC outcome (november 06): • completion of the CNGS commissioning at the beginning of the physics run • no high intensity beam for the CNGS until OPERA has reached 75% of the target mass Detector Construction status report

  44. OPERA beam request for 2007 • we should sent it before the next SPSC ( february 6-7th )  beginning of january • in the low intensity mode ( 1.7 1013 pot:extraction) we can expect: • 1.1 1016 pot/day with one CNGS cycle / supercycle (18 sec) • 1.6 1016 pot/day with 3 CNGS cycles / supercycle (39.6 sec) • end of may we should have ~74 K bricks in the detector •  6 – 9 events in the bricks per day • end of october ~154 K bricks  12 – 19 events per day • running over 141 days  1200 – 2000 events integrated Detector Construction status report

  45. Conclusions The OPERA collaboration can be proud of the real success of the construction of the detector  still one year of big efforts needed  are the needed resources available ? If we can guarantee the schedule discussed before ,we can have the first physics run of OPERA next year in 2007 Detector Construction status report