1 / 28

John S. Vento, Esq. Trenam, Kemker, Scharf, Barkin, Frye, O Neill Mullis, P.A. Michael F. D Onofrio, P.E. Capital Proj

epifanio
Download Presentation

John S. Vento, Esq. Trenam, Kemker, Scharf, Barkin, Frye, O Neill Mullis, P.A. Michael F. D Onofrio, P.E. Capital Proj

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    2. Another Day on the Job

    3. An Unforeseen Condition?

    4. A Force Majeure Event?

    5. Dealing With Mid-Course Adjustments

    6. Project Overview Project: Condominium Value: $30 Million Scope of Work: Concrete superstructure, steel frame penthouse and roof Contract Completion: 22 Months Interstate Land Sales Act (ILSA) Deadline: 24 Months Liquidated Damages: $10,000/day

    7. Project Overview Delay & Disruption Issues: Late approval of schedule Differing site conditions Acceleration/re-sequencing of work Penthouse and roof steel design errors Late delivery of windows Clerestory window design errors

    9. Mid-Course Adjustment Month 3 Contractor alleges differing site conditions Baseline schedule not approved Owner’s Rep wants additional detail Owner alleges bias Constructive Acceleration – Compensable?

    11. Mid-Course Adjustment Month 4 Schedule approved 3˝ months after NTP Update shows 3-month delay to project completion due to differing site conditions Owner disputes differing site conditions

    12. Mid-Course Adjustment Time Extension Request Project 3 months behind schedule Contractor prepares time impact analysis and submits time extension request

    14. Mid-Course Adjustment Recovery Schedule Owner refuses to grant time extension Mid-Course ADR? DRB? Mediation? Contractor develops recovery schedule to meet original completion date Recovery of 3 months Accelerate concrete superstructure (1 mo.) Use temporary enclosures to start interior finishes before window delivery (1 mo.) Accelerate interior finishes (1 mo.)

    18. Mid-Course Adjustment Month 12 Contractor accelerates concrete placement – recovers 1 month Owner agrees to pay for acceleration to date Owner grants 2-month time extension Contractor relieved of liquidated damages

    21. Mid-course Adjustments Design Errors

    22. Mid-Course Adjustment Month 14 Design errors Redesigning penthouse slabs Conflicting design to support elevator equipment Missing clerestory window beams Owner issues Stop Work Order Project delayed 2 months Contractual notice of delay and claim required?

    24. Mid-Course Adjustment Second Recovery Schedule Stop Work Order delays project completion 1 month to Month 25 Owner directs contractor to accelerate to complete by Month 24 Effect of window delivery delay – a concurrent non-compensable delay?

    27. Resultant Claims Original Contract to Change Orders

    28. Mid-Course Adjustments Resultant Claims Determining responsibility for delay and disruption Excusable vs. non-excusable delay Concurrent delay as a defense Compensable vs. non-compensable Time Impact Analysis

    29. Mid-Course Adjustments Dispute Resolution of Claims Methods of Alternative Dispute Resolution (ADR) Mediation Arbitration DRBs During progress of the job After Substantial Completion

More Related