An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Understanding and Valuating Exploration Companies24 May 2007Shane Hunter

  2. Agenda • The mining value chain – where exploration fits in. • What information do we get? • What can we value as we move along the value chain? • Valuation methods • General valuation issues • Summary

  3. The mining value chain Source: www.bullion.org.za

  4. Primary Exploration • Geochemical • Geophysical • Trenching • Drilling • = Metal values • Secondary Exploration • Drilling • Geological modeling • Metallurgical testing • Basic mining methods • (Scoping study) • = Mineral Resource • Business Planning • (Feasibility study) • In-fill drilling • Geological modeling • Metallurgical testing • Mine planning • = Mineral Reserve • Mine Construction • Engineering design • Build the plant • Build the mine • Mine planning details Operate the mine The (simplified) Mining Value Chain • Target Generation • Planning • Historical data • Geophysical • Geology • = A target area

  5. AngloPlats JV AngloPlats JV AngloPlats JV Source: Wesizwe Target Generation Location, location, location Wesizwe Sun City Wesizwe Wesizwe

  6. Source: Pan African Resources Target Generation Location, location, location

  7. Target Generation Source: Pan African Resources

  8. Primary Exploration Source: Pan African Resources

  9. Source: Deep Yellow Primary Exploration

  10. Primary Exploration

  11. Primary Exploration Source: St. Jude Resources

  12. Primary Exploration “We expect a SAMREC compliant Resource Statement to be released by . . . . .” Source: St. Jude Resources

  13. Primary Exploration But . . . . They only achieved 1!

  14. Width Strike Dip Primary Exploration Volume of the ore-body . . . • The ore-body is open along strike and at depth . . . • The ore-body is not closed off along strike or at depth . . .

  15. Source: Adamus Resources Secondary Exploration

  16. Secondary Exploration Source: Adamus Resources

  17. Secondary Exploration Source: Pan African Resources

  18. Business Planning Mine Plan

  19. Business Planning Reserve Statement Source: SXR UraniumOne Plant recovery factor ~ 80 to 95%

  20. Primary Exploration • Geochemical • Geophysical • Trenching • Drilling • = Metal values • Secondary Exploration • In-fill drilling • Geological modeling • Metallurgical recovery • Basic mining methods • = Mineral Resource • Business Planning • In-fill drilling • Geological modeling • Metallurgical testing • Mine planning • = Mineral Reserve • Mine Construction • Engineering design • Build the plant • Build the mine • Mine planning details Operate the mine Value along the Value Chain • Target Generation • Planning • Historical data • Geophysical • Geology • = A target area Speculation Speculation Valuation 1. Valuation 2.

  21. Valuation 1. - Enterprise value per oz in the ground Enterprise value = Market cap + debt - cash

  22. Valuation 1. - Enterprise value per oz in the ground EV/Measured & Indicated resources

  23. Value 1. Enterprise value per M&I oz in the ground - Peer groups

  24. Value 1. Enterprise value per oz in the ground ??? • This method DOES NOT directly consider; • Grade of the ore-body • The cost of mining (shallow, deep, open pit, u/g?) • The capital cost needed to build the mine • When will mining take place, i.e. the time value of money • Any royalty payable • Some companies will various deposits/resources • The EV/oz method also assumes; • All the resource ozs will be mined (or are worth something)

  25. Source: First Uranium Valuation 1. Underground resource Underground resource: ~ 6 million ozs

  26. 20 year life . . . Use site specific factors or industry standards . . . Underground resource: ~ 6 million ozs . . . .

  27. Valuation 1. Shallow Resource Shallow resource: ~ 1.5 million ozs

  28. 10 year life . . . Use site specific factors or industry standards . . . Shallow resource: ~ 1.5 million ozs

  29. Valuation 2. (Reserve) - NPV Model based on Feasibility Studies Mine ABC -1 2 3 DCF Value: $, Rands

  30. Value 2. NPV Model based on Feasibility Studies

  31. Source: First Uranium Inferred Resources - Physical location Indicated resource inferred resource

  32. Normal reef Fault loss fault Reef area reef reef Inferred Resources - Physical location Platinum example . . . Source: Wesizwe

  33. Inferred Resources - Physical location Lease area Target areas Greenstone type deposit or open pit

  34. Physical location of resources Lease area Drilling takes place

  35. Inferred Resources - Physical location Inferred Inferred Area 2 no value Area 3 Lease area no value Area 1 Measured Indicated Inferred some value As at 31 Dec. 2006

  36. Inferred Resources - Physical location Inferred Inferred Area 2 no value Area 3 Lease area 70% ownership no value Area 1 Measured Indicated Inferred some value As at 31 Dec. 2006

  37. Inferred Inferred Area 2 value? Area 3 Lease area Indicated no value Area 1 Measured Indicated Inferred some value As at 31 March. 2007 Inferred Resources - Physical location Valuations will change as more information is released to the market . . .

  38. Exploration planning 2007: Exploration expenditure (R millions) (10,000 metres)

  39. Company valuation • The technical value + . . . • Supply and demand of the shares • Commodity price outlook • Market issues • government policies/legislation • the economy

  40. Important Value Issues • What is the out-look on the commodity price? • Conversion of prospecting to mining rights, • Is the company in a JV with a major? • The major will supply the capital in return for ownership in the operation • How risky is the location (country) of the project • Who are the management team • Potential mergers, acquisitions

  41. Inferred • Target Generation • Planning • Historical data • Remote sensing • Geological • = A target area • Primary Exploration • Geochemical • Geophysical • Trenching • Drilling • = Metal values • Secondary Exploration • In-fill drilling • Geological modeling • Metallurgical testing • Basic mining methods • (Pre-feasibility study) • = Mineral Resource Inferred Area 2 value? Area 3 Lease area Indicated no value Operate the mine Area 1 Measured Indicated Inferred • Business Planning • (Feasibility study) • In-fill drilling • Geological modeling • Metallurgical testing • Mine planning • = Mineral Reserve • Mine Construction • Engineering design • Build the plant • Build the mine • Mine planning details some value As at 31 March. 2007 Date: February 2007 Summary

  42. Questions?