1 / 38

Immovable Asset Register Enhancement Programme Presentation to Portfolio Committee

Immovable Asset Register Enhancement Programme Presentation to Portfolio Committee 25 February 2014 Director-General: Mr M Dlabantu. Outline of the Presentation. Purpose of the presentation. Background. Feedback on the DPW Immovable Asset Register (IAR) Programme.

fausta
Download Presentation

Immovable Asset Register Enhancement Programme Presentation to Portfolio Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Immovable Asset Register Enhancement Programme Presentation to Portfolio Committee 25 February 2014 Director-General: Mr M Dlabantu

  2. Outline of the Presentation • Purpose of the presentation. • Background. • Feedback on the DPW Immovable Asset Register (IAR) Programme. • Joint IAR action plan (National & Provincial Public Works). • Vesting status. • Other key IAR-related enhancement-related activities. • Extension of the Principles of GIAMA to Local Government. • Demonstration: Level of IAR rebuild. • Immovable Asset Condition Assessment Guideline.

  3. Purpose of the Presentation The Portfolio Committee has requested a briefing by the Department of Public Works on the progress made by the Department on the completion of the Immovable Asset Register

  4. Background

  5. Background • There has been continuous lack of clarity on the nature and extent of State immovable assets as a consequence of a variety of historical and current factors. The said factors include: • Existence of multiple landholding institutions pre 27 April 1994, • Organisational complexities in the management of the transition post 1994 elections, which resulted in the loss and misplacement of some land records as well as the control of some State immovable assets being placed in the hands of private parties, • Incomplete surveying of State land, • Incomplete confirmation of vesting of State immovable assets,

  6. Background cont. • Magnitude of the State immovable assets portfolio in relation to existing capacity to manage and maintain it, • Unprocessed legacy transactions: • Expropriations, • Sales, transfers incorrectly processed by the State Attorney or not updated correctly on deeds, • Data in deeds not accurate when compared to title deeds, • Integration / Cooperation from relevant stakeholders, and • Activities / Actions by client department (DPW not the implementing agent).

  7. Background:What needed to be done? • Identification of all registered State immovable assets, • Identification of relevant ownership records, • Determination of custodianship of State immovable assets in accordance with legislation, • Desktop and physical verification of State immovable assets, • Confirmation of vesting (ownership) of all State land, • Enhancement of State immovable asset registers, • Capacity enhancement to manage and maintain portfolio, • Identification of State immovable assets controlled by other parties, • Improved management and reporting requirements for State immovable assets.

  8. Overview of DPW IAR programme:(IAR phase 2 commencement 6 January 2014 to 6 October 2016) Jan 14 2013/14 2014/15 2015/16 July 16 Dedicated resources (EY, A2A Kopano & Morarinc. consortium) have been procured for a turn-key IAR solution, in addition to Secondary Service Providers for physical verification Manage, process, QA physical assessment & pack IAR Registered land parcels research, reconciliation Surveyed not registered SDF’s not on State Land Rebuild IAR Municipal rates account number linked Link municipal rates recon required(FSP) Apply FV – demo progress Apply FV - final Remaining L&B linked UAMP comparison UAMP comparison IAR/UAMP integration PaperTrail Heritage assets policy/approach addressed Heritage assets classification complete Quarterly reporting, process additions, disposals, adjustments, capitalisations, ongoing deeds & SG reconciliations Maintain IAR GRAP requirements – depreciation, impairment, useful lives, etc State land reconciliation DPW family State land reconciliation DPW family State land reconciliation DPW family Vesting setup Vesting factory Vesting factory Vesting factory Vesting factory Operating model design Operating model final PCMs Transition support Related projects IAR system spec Data migration support Sundry debtors updated OBB plan OBB data OBB execution OBB report Completeness of registered properties, progress on unregistered, FV tested IAR complete for registered land & substantially complete for unregistered + FV substantially applied GRAP compliant IAR Minor snag list for follow up Key milestones

  9. Background:What has been done? • DPW and DRDLR, as the main national custodians, have assumed a collective leading role in the identification and correct classification of government immovable assets. • In view of the existence of legislation which empower other authorities in the national and provincial sphere to control State immovable assets, mechanisms had to be devised to bring all the actors together towards determining, amongst other things, the extent of State immovable assets. • DPW and DRDLR created an intergovernmental structure, currently known as the Provincial State Land Vesting and Disposal Committee (PSLVDC) with a view to coordinate immovable asset disposal processes as well as confirmation of vesting of all State immovable assets in the national and provincial spheres.

  10. Background:What has been done? cont. • The original idea was to prevent the possible disposal of an immovable asset controlled by one department whilst it may be required by another for its service delivery purposes. • The PSLVDC also serves to achieve consensus amongst all State immovable assets controlling departments on whether an immovable asset vests in the respective national or provincial sphere. • In 2009 Cabinet set up an Inter-Ministerial Committee (IMC) on Immovable Assets. This IMC is chaired by the Minister of Public Works and includes the Minister of Finance and that of Rural Development and Land Reform as members. • A national surveying programme was initiated in 2011 under the leadership of the Chief Surveyor General.

  11. Background:What has been done? cont. • The plan was aimed at identifying and surveying all un-surveyed State land and State Domestic Facilities. • The surveying has practically been completed except for minor ‘gap areas’ and ‘slithers’ of State land between river bank boundaries. • Though surveying has been done correctly in terms of the Land Survey Act, there are some few challenges relating to the separation of provincial facilities from larger national land parcels. This issue is currently being addressed. • As can be appreciated from the above slides, the magnitude of State immovable assets challenges has necessitated a multifaceted collaboration approach at various levels.

  12. Feedback on the DPW Immovable Asset Register (IAR) programme

  13. Overview of DPW IAR Programme:Progress from inception of Programme to 31 March 2013 • Comfort on completeness of land parcels, • Continuous interaction with the State Land custodians, • Worked with the Provincial custodians to analyse and reconcile registered land, • Clear requirements were defined for the Immovable Asset Register and related matters, • Appointed vendors for physical assessments and condition assessments, • Physical verification commenced with the development of software, the procurement of robust tools, definition of clear processes and quality control procedures, • Commenced work on State Domestic Facilities (SDF’s) – State Domestic Facilities are defined as DPW buildings on someone else’s land.

  14. Overview of DPW IAR programme:Plan from 1 April 2013 to March 2014 • On-going deeds refresher for registered land parcels. • Build IAR for surveyed and not registered land. • Build IAR for SDF’s (state domestic facilities not on state land). • Conduct physical verification of identified DPW properties. • Draft and implement IAR policies and processes. • Capitalise projects with effect from 1 April 2013. • Apply municipal values to properties. • Link correct municipal rates account to IAR. • Initiate Operation Take Back.

  15. Status of audits:(From 2011/2012 to 2013/2014 financial year end)

  16. Graphical representation of registered land

  17. State land reconciliation as at January 2014:(includes Registered, Unregistered and Sec 42 land parcels) 1 2 1 2 Disclosed by DPW for 2012/13 as per National Treasury Sector Specific Guide. Provinces will have to disclose these for 2013/14 as per the new Sector Specific Guide DPW is currently busy resolving And will be completed by March 2014

  18. Physical verification: • The Department has embarked on a process of physical verification of its immovable assets to confirm information contained in its enhanced register, • Two service providers have been appointed to execute this task: • PWC Consortium, and • eValuations. • The physical verification project commenced on 11 October 2013 and the planned date of completion is 28 February 2014.

  19. Physical verification:Progress as at 17/2/2014 cont.

  20. DPW IAR improvement programme:Phase 2 key elements • Service Provider on boarded w.e.f January 2014: • Work stream leads & resources secured to deliver 2016 target: • Management the physical assessment stream & QA, • GRAP compliance, • IAR on iE-Works and suitable accounting platform, • Vesting of DPW properties to meet March 2016 target, • Supplement current DPW teams and ensure skills transfer. Registered Land Surveyed not registered State Domestic Facilities Physical assessment Operating Take Back Operating Model PaperTrail Vesting GRAP IAR finance specification Fair value Property rates Heritage assets GRAP Accounting Immovable Asset Register Other related projects

  21. DPW IAR improvement programme:Key successes to date • Increased confidence in data & numbers being reported as evidenced in 2013 Audit results. • Physical assessment to corroborate and enhance cleansed IAR. • Identified transactions for investigation & follow up (OTB). • Vesting factory set up to meet 2016 vesting target. • System enhancement on iE-Works ahead of envisaged go-live during 2014 and integrate IAR with required accounting & reporting system. • iE-Works being availed to the Provinces. • Suitably qualified team to see enhancement through to 2016 target on boarded.

  22. Joint IAR action plan(National & Provincial Public Works)

  23. Action Plan on IAR:(National and Provincial Public Works)

  24. Key results- Position with Provincial DPW’s as at September 2013 (interim AFS submission)

  25. DPW Vesting Status

  26. DPW Vesting Status:Progress as at 31 December 2013

  27. DPW Vesting – projected delivery of land parcels to be vested by March 2016

  28. Other key IAR enhancement-related activities

  29. Other key IAR related activities cont. • In reconciling State land: • land parcels in the former TBVC states have been recorded in the Immovable Asset Register of DRDLR; • Facilities used by the National Government in the former TBVC states have been recorded in DPW’s Immovable Asset Register, and • facilities used by the Provincial Government in the former TBVC states have been recorded by the respective Provinces. • An immovable asset policy document for the PMTE has been drafted covering all the asset management and accounting requirements.

  30. Other key IAR related activities • In relation to foreign State-owned immovable assets: • The Department of International Relations and Cooperation (DIRCO) was assigned custodianship of foreign assets during 1999 and they have been responsible for the management of such assets including presentation and disclosure in Annual Financial Statements, except disposal of such assets which currently remains the responsibility of DPW. • 13 immovable assets abroad superfluous to the needs of DIRCO have been identified for disposal comprising, inter alia, the former Chancery and Official Residence in Bonn, Germany, • An Immovable Asset Disposal Policy was approved by the Minister of Public Works on 30 May 2013, • The Department has embarked on a process of developing country-specific disposal strategies, in consultation with DIRCO, with a view to the disposal of these assets within the 2014/15 financial year. The proceeds realized from such disposals will be returned to the fiscus.

  31. Extension of the Principles of GIAMA to Local Government

  32. Fundamentals of GIAMA:National/Provincial vs. Local Government • GIAMA provides a framework of basic principles in accordance with which national and provincial departments must manage the immovable assets that they utilise or control in executing their mandates. • GIAMA is structured around the following building blocks: • Role-players involved in the acquisition, operation and disposal (custodians) and the utilisation (users) of the State’s immovable assets; and • Management processes within government. • Whilst the management of all spheres of government stem from the same fundamental principles, the role-players involved in immovable asset management and the strategic management processes of local government differ significantly from national and provincial government.

  33. National/Provincial vs. Local Government A) Role-players: National & Provincial Government • Users: Departments who utilise immovable assets in the performance of their functions. Required to compile annual user asset management plan (U-AMP). • Custodians: Departments who perform “caretaker” functions in relation to immovable assets. Required to (1) provide information on immovable assets allocated to users, to inform compilation of U-AMPs; and (2) compile annual custodian asset management plan (C-AMP). A) Role-players: Local Government • No standard institutional delineation between users and custodians of immovable assets. • No separate accounting officers in various departments within a Municipality.

  34. National/Provincial vs. Local Government cont. B) Management Processes: National & Provincial Government: • National / Provincial Departments (both users and custodians) are obliged to compile annual immovable asset management plans as part of their annual strategic planning process. • User and Custodian Asset Management Plans must be submitted to relevant Treasury to inform annual budget allocations. B) Management Processes: Local Government: • In terms of Municipal Systems Act, 2000 a Municipality is obliged to develop an Integrated Development Plan (IDP) at least every 5 years, which serves as its principal “strategic management planning instrument”. • Municipalities are required to annually review their IDP and this should inform their annual budget.

  35. National/Provincial vs. Local Government cont. • Municipalities are governed by specific body of legislation, of which the Local Government: Municipal Systems Act, 2000 (MSA) and the Municipal Finance Management Act, 2003 (MFMA) are most relevant to immovable asset management - • The principal strategic planning document of a Municipality is its Integrated Development Plan (IDP). • The MSA prescribes a specific process for the compilation of IDPs, which must also be aligned with provincial development plans and national priorities. • The MSA also prescribes comprehensive consultation requirements in relation to the compilation of IDPs.

  36. National/Provincial vs Local Government cont. • An IDP is an inclusive strategic plan guiding all development within a Municipality. In terms of the existing regulatory framework, an IDP may, as part of its financial strategy, contain an asset management strategy. • The shortcomings in the existing IDP process, however, are that • it does not detail a specific immovable asset management planning process,and • it does not make immovable asset management mandatory, as is the case in GIAMA.

  37. Extension of structured Immovable Asset Management to Municipalities: Current position: • Owing to key differences in the legal framework and organisational structure of local government compared to national and provincial government, it would be problematic to incorporate Local Government into the existing legislation (GIAMA) rendering it very convoluted. • DPW therefore holds the view that a different approach would be advisable to extend the principles of GIAMA to local government: Alternative 1: The requirements for immovable asset management could be incorporated in (a) separate set of regulations issued in terms of the Municipal Systems Act, or (b) amendment to the existing Local Government: Municipal Planning and Performance Management Regulations, 2001 issued in terms of that Act.

  38. Extension of structured Immovable Asset Management to Municipalities: Current position cont. Alternative 2: Specific legislation could be developed, based on the requirements, organisational structure and existing legal framework governing municipalities. • DPW has renewed discussions with the Department of Cooperative Governance regarding the optimal approach and timeline to extend the principles of GIAMA to local government. The objective is to reach agreement on specific objectives commencing in 2014/15.

More Related