EDMS №[Number]. CLIC TBM Prototype T0@CLEX Status update. Dmitry Gudkov. CONTENTS. TBM integration in CLEX Supporting system CLEX room in LAB-169. Status of the room preparation Preliminary planning for the TBM installation in CLEX. TBM Integration of the in CLEX.

genero
Download Presentation

CLIC TBM Prototype T0@CLEX Status update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDMS №[Number] CLIC TBM Prototype T0@CLEX Status update Dmitry Gudkov

  2. CONTENTS • TBM integration in CLEX • Supporting system • CLEX room in LAB-169. Status of the room preparation • Preliminary planning for the TBM installation in CLEX

  3. TBM Integration of the in CLEX • The integration is under way, but.. • DB optics configuration has been changed (new input received from Jakob) • The new study is needed in order to check: • If new positions of the components in CLEX can be applied • Components supporting girder, study is needed. Jakob Esberg

  4. Supporting system status • All 4 girders have been controlled by metrology Results (axis straightness) MBO-2     :0.010 mmMBO-1     :0.014 mmDBO-1      :0.012 mmDBO-2       :0.012 mm • The cradles have been controlled by metrology report is under preparation • ZTS visit for installation of the equipment is confirmed: 24.02 – 28.02 We are waiting for the detailed visit program from ZTS. • CLEX room in the LAB-169 is under preparation See next slides

  5. CLEX room in LAB-169. Status of the room preparation • The floor drilling is finished • Threaded inserts are installed • The location of the racks is defined • OPEN POINTS: • Acquisition and control needs? • Electricity • Internet • Temperature in the LAB (18-28 deg.) • Is everything ready? (SU) RACKS

  6. Lab 169/S-039: Implantation drawing Espace réservé pour manutention

  7. Perçage et installation des chevilles diamètre 20 et 16mm après le tracé du positionnement des supports par les géomètres 40 trous OK Le lab. CLEX est prêt pour l’installation des supports P. de Souza, S. Lebet

  8. Planéité des supports métrologique ??? Rectitude environ 15mm P. de Souza, S. Lebet

  9. Preliminary planning for the TBM installation in CLEX