1 / 11

sPHENIX DOE-SC CD-1/3A Review

sPHENIX DOE-SC CD-1/3A Review. RLS Schedule Development Rich Grubb May 23-25, 2018 BNL. sPHENIX P6 development. 13 Microsoft Project files. P6 Integrated Master Schedule Validated matching to MS Project plan Identified completed work vs work to-go Implemented cost reduction

ida
Download Presentation

sPHENIX DOE-SC CD-1/3A Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. sPHENIX DOE-SC CD-1/3A Review RLS Schedule Development Rich Grubb May 23-25, 2018 BNL

  2. sPHENIX P6 development 13 Microsoft Project files • P6 Integrated Master Schedule • Validated matching to MS Project plan • Identified completed work vs work to-go • Implemented cost reduction • Implemented expanded FY18 R&D phase Aug 2017 • Project Manager’s schedule work fest • All L2 managers and Project Estimators worked in the P6 schedule with Project Controls and improved the work plan. Validated estimate data and project coding. sPHENIX DOE-SC CD-1/3A Review

  3. How costs are shown in reports • Escalated (Esc) equals At Year (AY) = Direct + Burden + Escalation • Total Burdened Esc $ • = Direct + Burden + Escalation • Escalated (Esc) equals At Year (AY) • Direct $ • Labor includes fringe • Nonlabor units is budgeted value of contracts and/or purchase orders Example P6 Activity Report sPHENIX DOE-SC CD-1/3A Review

  4. Tips for Cost Book summary data sPHENIX DOE-SC CD-1/3A Review

  5. Tips for Cost Book detail • Resource level (white rows) is the detail shown • May have many resources to one activity • Highlighted rows are summary • Time phase data is period units or cost. The column title of the column prior to the first period indicates the data type sPHENIX DOE-SC CD-1/3A Review

  6. P6 data tables • Project • Activities • Activity Coding • Resource Assignment • Resource Assignment coding • Resource • Global Codes • Added P6 fields prefixed by • “BNL_” activity code fields • “BNL_UDF” activity user defined fields • “BNL_Res” resource code fields • “BNL_RAU” resource assignment user defined fields sPHENIX DOE-SC CD-1/3A Review

  7. Attribute Coding sPHENIX DOE-SC CD-1/3A Review

  8. P6 Resource Table Project is using 73 resources: 68 Labor 5 Nonlabor sPHENIX DOE-SC CD-1/3A Review

  9. BNL Finance source of resource rates Project base year = FY17 sPHENIX DOE-SC CD-1/3A Review

  10. Open Ends • Activities without predecessors..................................8 •                              Project: POM02B_J         Activity:              S100010              Approve Mission Need CD-0 •                              Project: POM02B_J         Activity:              S100400              CD-1 Review •                              Project: POM02B_J         Activity:              S100600              CD-3a Budget Appropriation •                              Project: POM02B_J         Activity:              S100800              CD-2/3 Review •                              Project: POM02B_J         Activity:              S101008              FY18 funding available •                              Project: POM02B_J         Activity:              S101009              FY19 funding available •                              Project: POM02B_J         Activity:              S101010              FY20 funding available •                              Project: POM02B_J         Activity:              S101015              FY21 funding available •               Activities without successors....................................7 •                              Project: POM02B_J         Activity:              S100200              Prepare for CD-1 Review •                              Project: POM02B_J         Activity:              S100700              Prepare for CD-2/3 Review •                              Project: POM02B_J         Activity:              S100900              Transition to CD2/3 •                              Project: POM02B_J         Activity:              S101008              FY18 funding available •                              Project: POM02B_J         Activity:              S101040              Approve Project Closeout CD-4 •                              Project: POM02B_J         Activity:              S247500              Oversight of sPHENIX Digitizers Procurement •                              Project: POM02B_J         Activity:              S318540              Start of RHIC Run 30-Jan-23 A Fuse Analysis of the schedule has been prepared and is available for Review. sPHENIX DOE-SC CD-1/3A Review

  11. Integration/Summary • Integration with other management tools • P6 data is the source • P6 to Cobra wizard • Cobra is the earned value cost processor • P6 & Cobra used to set the Performance Measurement Baseline (PMB) • Monthly status cycle • Collect status and ETC information prior to end of month in P6 • Import status with wizard from P6 to Cobra • Import of project actuals data from Peoplesoft Financials into Cobra • Post schedule and earned value reports for project team • Project Resource Loaded Schedule well developed for CD-1. sPHENIX DOE-SC CD-1/3A Review

More Related