Beta-Beam Task Progress

Beta-Beam Task Progress. Milestones Status of ongoing work Open issues Conclusion. Milestones. Last milestone (month #9) was to fix the parameters along the accelerator chain In-/ejection energies of the machines, cycling times, ion intensities along the chain ...

ifama
Download Presentation

Beta-Beam Task Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beta-Beam Task Progress Milestones Status of ongoing work Open issues Conclusion EURISOL – Coordination Board Meeting

  2. Milestones Last milestone (month #9) was to fix the parameters along the accelerator chain • In-/ejection energies of the machines, cycling times, ion intensities along the chain ... • Allows the sub-tasks now to progress on detailed design and investigate major technical challenges No milestones defined for the period winter05/spring06 Next milestones are upcoming at reporting month 18, which are • M2.2 RCS first order optics design • M3.2 PS and SPS: Identification of limits • M4.2 Decay ring first order optics design Present activities to achieve the milestones above are ... EURISOL – Coordination Board Meeting

  3. Subtask 2: Low Energy Ring(s) RCS (Orsay) • update on first order design • Ejection energy raised to 3.5 GeV proton equivalent • Simulation of multi turn efficiency: performance better than originally estimated LE accumulation ring (non-baseline option) (SU-MSL) • Simulations of electron cooling EURISOL – Coordination Board Meeting

  4. Subtask 3: PS and SPS • Analysis of dynamic vacuum effects (GSI) • Pressure in PS reaches very high levels • Currently investigation to improve unacceptable situation EURISOL – Coordination Board Meeting

  5. Optical functions (m) s (m) Subtask 4: Decay ring Major issues: • Collimation • Insert dispersion section in straight section • Collimate 1MJ per beta-beam cycle! • High peak current (200 Amps) and RF aspects in the decay ring Collaboration between CERN and Saclay EURISOL – Coordination Board Meeting

  6. Conclusions Work is progressing according to plan of the Beta-beam task. No deviation from planning • Beta-beam task now concentrates on • All machines: address technical design issues (RF, Vacuum requirements, magnet design etc.) • Improvements for vacuum situation in PS • Collimation in the decay ring (Optics design, simulation of energy deposition ...) • 18Ne shortfall • Feedback on expectations for ion production and beam preparation? • For the further progress of sub-task 2 (RCS, LE accumulation) a first order design of the post accelerator should be addressed. EURISOL – Coordination Board Meeting