An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S.P. 8680-1652011 MnROAD Reconstruction Pre-Letting Conference April 8, 2011

  2. Cell 105-205 & 6 XXXXX Low Volume Road XXXX Cell 63 & 96 Stockpile Area Mainline (I-94) • Secured Area • Roadway Closed to Traffic XX Demo Slab (200’)

  3. Construction Timeline • Construction will begin July 11, 2011 or 8 days after notice to proceed, whichever is later • Construction Completion Date is September 1, 2011

  4. Removals Existing Cells 4” 5+” 12*+” * Subgrade will be excavated to 4% cross slopes.

  5. Grading Work • OGAB Special, subgrade cross slope 4%, top of base cross slope 2% • Base material to minimum 6” at centerline. • OGAB Special will be continued and day lighted into ditches. • Demonstration Slab (Demo Slab)= 6” OGAB Special

  6. Instrumentation • Days needed for instrumentation (Mn/DOT) after • - Excavation completion cell 6 (2 days) • - Aggregate Base installed cell 6 (3 days) • - Removal of concrete and PASSRC cell 5 (2 days) • - Install geotextile fabric cell 5 (2 days)

  7. Concrete Paving – 3 Mixes • Cell 505 and 605 Pavement Mix Design shall comply with the following • CA-15 coarse aggregate gradation. • Cell 306 Pavement Mix Design shall comply with the following: • CA-35 coarse aggregate gradation. • Cell 406 Pavement Mix Design shall comply with the following: • Either a CA-15 or CA-35 coarse aggregate gradation. • Cell 505, 605, 306, 406 shoulders, and Demonstration Slab: • Provide Roller Compacted Concrete (RCC) as per specifications.

  8. Finished Textures Cell 306 and 406 – Longitudinal Tining Cell 505 and 605 – Transverse Broom Cell 63 and 96 – Traditional Grind

  9. Demonstration Slab • Located in the stockpile area • 200’ long • Same operations as shoulders on cell 6 * 4” RCC Concrete * 6” OGAB Special * Installed at 4% cross slope. • Goal for the demo slab * Experience with materials * Experience with RCC placement * Experience with OGAB Special.

  10. Shoulders • Cell 505 and 605 • RCC Placed directly on existing materials. • Wick Drains to be installed prior to paving • Cell 505 shoulders will be jointed similarly to mainline • Cell 605 – no joints • Cell 306 and 406 • RCC placed on OGAB Special • Cell 306 shoulders will be jointed similarly to mainline. • Cell 406 – no joints

  11. Cell 63 and 96 • 4” x 5’ x 6’ misc. concrete panel repair in cell 63. • Both cells 63 and 96 will receive a traditional concrete grind

  12. Extra Research Quantities Demonstration Slab • 4” RCC pavement 8’ x 200’ • 6” OGAB special 10’ x 202’ Research Samples • 1 cubic yard extra of each concrete mix (3 mixes total) • 15 cubic yards extra of OGAB Special

  13. Questions? Melissa K. Cole, P.E. MnROAD Forensic Engineer (651) 366-5432 melissa.cole@state.mn.us