“LHC Controls for Sector Test” Planning

“LHC Controls for Sector Test” Planning. SPS Extraction Kicker and Septa LHC Injection Kicker and other equipment (beam stoppers, dumps, ...) Etienne CARLIER 05-Dec-2001. Assumptions. Major client is operation Commissioning means equipment ready for test with beam Sector test: Q2/2004

Download Presentation

“LHC Controls for Sector Test” Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “LHC Controls for Sector Test”Planning SPS Extraction Kicker and Septa LHC Injection Kicker and other equipment (beam stoppers, dumps, ...) Etienne CARLIER 05-Dec-2001

  2. Assumptions • Major client is operation • Commissioning means equipment ready for test with beam • Sector test: Q2/2004 • Access to restricted underground area UA87 possible up to the end of Q3/2003 • SPS extraction and TT40 commissioning up to TED400354: Q2/2003 • TI8 commissioning up to TED87765: Q3/2003

  3. Sector Test (+ CNGS) – SL/BT Equipment TED400354 TBSE80243 TED87765 MKE MSE TCDI TCDI MKI TDI TCDD SPS – LSS4 TT40 TI8 LHC – RA87 TBSE410113 T40 TT41 Equipment HardwareLocation Electronics Location Commissioning SPS extraction kickerSPS extraction septa MKE4MSE SPS – LSS4 HCA421/422 Q1/2003Q1/2003 T40 beam dump upstream TED TT40 HCA422 Q1/2003 TT41 beam stopperNeutrino target T40 TBSET40 TT41 HCA422 Q1/2005Q1/2005 TI8 beam dump downstreamTI8 collimator TEDTCDI TI8 SR8 Q3/2003??? LHC injection kickerLHC injection dumpLHC injection collimator MKI8TDITCDD LHC – RA87 UA87/SR8 Q1/2004Q1/2004Q1/2004

  4. Architecture Application SL/CO – SL/OP Ethernet Master PLC SCADAOP Equipment Server VME CompactPCI Profibus-DP Fast Control Elementary cycle dependent Timing delay Voltage Fast Acquisition 500Ms/s, 200MHz Analysis (FFT, Fuzzy, DSP) DecentralisedI/O DeportedI/O Slow control Elementary cycle independent State control Monitoring TED, TBSE, TCDI, TDI, TCDD, MSE, MKE, MKI MKE, MKI MKE, MKI

  5. MKE – SPS Extraction Kicker(SL/BT Responsibility) Development Serie production Installation Commissioning HV power supplies DO-Q4/2001 Q4/2002 Q1/2003 Q1/2003 Power trigger ۷ ۷ Q3/2002 Thyristor unit ۷ ۷ Q4/2002 Safety switch ۷ ۷ Q4/2002 Mains distributor [1] Q1/2002 Q3/2002 Q4/2002 Slow interlock [2] ۷ Q2/2002 Q3/2002 Fast interlock [2] ۷ ۷ Q4/2002 Extraction interlock Q3/2002 Q4/2002 Q1/2003 Heater PS [2] DO-Q1/2002 Q4/2002 Q1/2003 Terminating resistor [2] ۷ Q3/2002 Q4/2002 Timing [1] ۷ ۷ Q4/2002 Monitoring [2] ۷ Q2/2002 Q3/2002 [1] : low level software still to be developed[2] : low level software included

  6. MKI – LHC Injection Kicker(SL/BT Responsibility) Development Serie production Installation Commissioning RCPS (Triumf) [2] ۷ ۷ Q3/2003 Q1/2004 Power trigger ۷ ۷ Q3/2002 Thyristor unit ۷ ۷ Q4/2002 Safety switch ۷ Q2/2003 Q3/2003 Mains distributor [1] Q1/2002 Q2/2001 Q4/2002 Slow interlock [2] ۷ Q2/2002 Q3/2002 Fast interlock [2] ۷ Q4/2002 Injection interlock Q3/2002 Q4/2002 Q1/2003 Heater PS [2] DO-Q1/2002 Q2/2003 Q3/2003 Terminating resistor [2] ۷ Q3/2002 Q4/2002 Timing [1] [3] DO-Q3/2002 Q2/2003 Q4/2003 Monitoring [2] ۷ Q2/2002 Q3/2002 [1] : low level software still to be developed[2] : low level software included[3] : Fast timing based on Highland Technology (or similar) VME board

  7. Electromagnetic Septa (SL/BT Responsibility) Development Serie production Installation Commissioning Magnet control [2] ۷ ۷ Q2/2002 Q1/2003 Power Supply control [2] ۷ ۷ Q2/2002 Cooling control [2] ۷ ۷ Q2/2002 Girder positioning [2] ۷ Q3/2002 Q1/2003 [1] : low level software still to be developed[2] : low level software included

  8. TED, TBSE, TCDI, TDI & TCDD Equipment Development Serie production Installation Commissioning Positioning: INOUT [2] TED400354TBSE80243TED87765TBSE410113TCDD ۷ Q3/2002Q3/2002Q3/2002Q3/2002Q3/2002 Q4/2002Q4/2002Q3/2003Q3/2004Q4/2003 Q1/2003Q1/2003Q3/2003Q1/2005Q1/2004 Positioning: SERVO [2] TCDI ۷ ??? ??? ??? Positioning: STEP [3] [1] TDI Q4/2002 Q3/2003 Q4/2003 Q1/2004 Monitoring [2] All ۷ Idem positioning Idem positioning Idem positioning [1] : low level software still to be developed[2] : low level software included[3] : If required precision can not be reached with SERVO positioning system.

  9. Hardware dependencies Access system Cooling system Vacuum Network Fast timing Slow timing VME Front-end PLC Front-end PXI Front-end MPS Machine protection Beam instrumentation Machine energy Signal visualization Electrical distribution Cables MKE MSE TED TBSE TCDI MKI TDI TCDD Specific Standard

  10. Hardware dependencies Access system Cooling system Vacuum Network Fast timing Slow timing VME Front-end PLC Front-end PXI Front-end Power Supply Machine protection Beam instrumentation Machine energy Signal visualization Electrical distribution Cables MKE Q32002 Q32002 Q32002 Q32002 Q32002 Q32002 Q32002 Q32002 Q32002 Q42002 Q32002 Q32002 Q32002 Q32002 Q12003 MSE Q42002 Q42002 Q32002 Q32002 Q32002 Q42002 Q32002 Q32002 Q12002 TED Q32002 Q32002 Q32002 Q32002 Q42002 Q32002 Q32002 Q12002 TBSE Q32002 Q32002 Q32002 Q32002 Q32002 Q12002 TCDI Q42003 ??? ??? Q42003 Q42003 ??? ??? MKI Q22003 Q22003 Q42003 Q32003 Q32003 Q32003 Q32003 Q32003 Q32003 Q42003 Q42003 Q22003 Q32002 Q32002 Q32002 TDI Q42003 Q32003 Q32003 Q42003 Q42003 Q32003 Q32002 TCDD Q42003 Q32003 Q32003 Q42003 Q32003 Q32002

  11. Hardware dependenciesInstallation Cabling MKE LSS4 – HCA421Q4/2001Q1/2002 ECA4 – HCA421Q1/2002 HCA421Q2/2002 HCA421 - FCQ2/2002 MSE LSS4 – HCA422Q4/2001Q1/2002 TDETBSEUpstream TT40/TI8 – HCA422Q4/2001Q1/2002 TDEDownstream RA87-SR8Q3/2002 MKI RA87-UA87Q3/2002 UA87Q3/2002 UA87-SR8Q3/2002 TCDI, TDI, TCDD RA87-SR8Q3/2002 RequestInstallation

  12. Hardware dependenciesElectrical distribution MKE ECA4Q4/2001Q3/2002 HCA421Q4/2001 MSE LSS4 Q4/2001Q1/2002 HCA422 Q4/2001 TDETBSEUpstream TT40/TI8Q4/2001Q1/2002 HCA422 Q4/2001 TDEDownstream SR8Q3/2002 MKI UA87pre. Q3/2001Q1/2002 SR8Q3/2002 TCDI, TDI, TCDD SR8Q3/2002 RequestInstallation

  13. Software DependenciesAssumptions SL/BT will provide software up to the equipment server layer in accordance with SL/CO predefined equipment access contracts (server API) • Q4/2001 : MSE’s in LSS2 & LSS6, TED & TBSE in TT60 & TT20 included into SPS2001 framework • Q3/2002 : all the different types of SL/BT equipment included into and operated from SPS2001 framework (Kicker, Electro-magnetic septa and beam obstacles TED & TBSE) • Q1/2003 : copy of the different device servers for equipment in the LSS4 extraction channel

  14. Software dependencies Software Commissioning Equipment access contracts (server API) Alarm Q1/2002 Software interlock State ۷ Settings & measurements ۷ Device data ۷ Error handling Settings management Operational Q1/2002 Equipment Analogue signals acquisition and visualisation Q4/2002 VME front-end [MKI] HW drivers: timing delay module [1] Q4/2003 [Q2/2003] HW drivers: analogue out [2] HW drivers: analogue in [2] [1] : Highland technology V850[2] : tbs. SL/CO – SL/PO recommendation

  15. Software dependencies Software Commissioning Post-mortem MKE [MKI] Synchronisation mechanism, contract definition, inter-connection with machine protection Q1/2003[Q1/2004] Logging / Archiving Operational level: data definition, time stamping mechanism, contract definition, off-line analysis tools Q1/2003[Q1/2004]

  16. Analogue signals acquisition and visualization • Remote visualization of signals (nAos) • Synchronization • Signals recording • Equipment post-mortem • Continuous signals analysis • Equipment stability, pulsed regulation loop • Remote scope • Signals acquired in the UA (no access during operation), selection, configuration, analysis & visualization in the SR • Cabling cost reduction

  17. Critical items • Cabling specification (All the technical choices have not yet been made at the equipment level but also at the LHC control architecture level) • Analogue signal acquisition, analysis, display… • SPS interlock and machine protection (for LSS4 extraction but also for beam dumping system) • Integration of equipment into the control architecture (Equipment server contract specifications,…) • LHC Beam Energy Measurement System (BEM)