An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COV Asset Baselining Plan September 23, 2008

  2. Background (old approach) • Kickoff meeting held with agency to discuss reconciliation plan • Plan consisted of a phased approach • Approach supported reconciling wall-to-wall to asset inventory and other data points • Committed to completing the reconciliation within 2 - 4 months • Reconciliation was to be completed by service delivery staff • Approach is taking too long and schedule to meet completion date is at risk

  3. New Approach Needed to Meet Objectives and Schedule • Our new approach: • Leverages success and lessons learned from Dept. of Health • 120 sites completed in four weeks, with approx 19,500 assets • Clearly details the need for agency participation • Clarifies the need for the agency to provide a sign-off upon completion of a site along with final sign-off on mock bill • Documents assets and data points in-scope to the project • Provides an escalation process

  4. Lessons Learned from Dept. of Health • Agency participation - agency recognized this is a valuable and necessary process; agency was very open and communication was excellent • Good upper-management support from agency • This process identified the importance of using a single resource for data collection, particularly one with experience in data collection related to assets • Agency to determine up front the consistent statewide use of the optional Agency Use fields • Agency Site POCs available and working onsite with TEK Systems to scan assets and provide information

  5. Revised Approach • Phase 1-Physical Inventory • Northrop Grumman/TEK will complete physical inventory • Agency will provide Points of Contact (POC) for each site • POC responsible for assisting with data population of agency optional data fields and signing off on site completion • Service delivery staff will identify and tag all workstations requiring Altiris agent • Phase 2 – Data Validation (performed by Northrop Grumman/TEK) • Populate additional fields required for Altiris not captured during physical • Perform quality control • Compare new file with Asset Inventory and provide differential report to Northrop Grumman • Prepare file for mock bill creation • Phase 3 – Mock bill presentation • VITA presents mock bill for AITR sign-off • Sign-off from AITR desired within 3 business days of receipt of mock bill

  6. Roles and Responsibilities • Northrop Grumman/TEK is responsible for the following: • Developing process, and a schedule including every site • Managing inventory activities at all sites • Providing teams of inventory specialists to complete physical inventory at all sites • Assisting in populating additional data points for assets provided by Agency POC • Performing quality assurance/quality control on data • Providing baseline data for mock bill • Agencyis responsible for the following: • Providing two resources, a lead and a backup POC, for each site with the authority to signoff on accuracy of counts and completion of inventory for that site within 24 hours of completion • Granting access to all areas with inventory • Providing the remaining agency optional data necessary to complete the record for each asset • Reviewing and signing off on a physical inventory • Providing final agency sign-off on all sites within 3 business days of receipt of final data and mock bill • Adhering to and supporting VITA’s escalation process

  7. Why Will This Process Work? • The use of dedicated personnel from the partnership to interface between Service Delivery site staff and Asset Management to ensure accurate reconciliation • Active involvement, participation, and signoff by knowledgeable Agency personnel • Utilization of the Install, Move, Add, and Change (IMAC) process to ensure accurate updates once the asset baseline is complete • Planned use of quality control process for periodic sampling to assess effectiveness of IMAC process

  8. Next Steps • Schedule agency kickoff meetings with affected agencies • Identify Agency POCs for each site • Northrop Grumman Project Coordinator to review schedule and documents with each site POC • Agency identify optional data fields to populate • Confirm scheduled site visits • Begin inventorying sites