1 / 14

Prado Basin Feasibility Study Cost-Benefit Analysis

Prado Basin Feasibility Study Cost-Benefit Analysis. Water Issues Committee March 14, 2018. Prado Basin Feasibility Study. Agreement with Army Corps established District as non-federal (local) sponsor Feasibility Study includes Ecosystem restoration

karolynw
Download Presentation

Prado Basin Feasibility Study Cost-Benefit Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Prado Basin Feasibility Study Cost-Benefit Analysis Water Issues Committee March 14, 2018

  2. Prado Basin Feasibility Study • Agreement with Army Corps established District as non-federal (local) sponsor • Feasibility Study includes • Ecosystem restoration • Water conservation (temporary stormwater capture) • Sediment management

  3. Ecosystem Restoration Measures in Feasibility Study These are a range of features to enhance the environment, including: • Non-native plant removal • Non-native animal removal (aquatic species & feral pigs) • Sediment removal • Modifications to Chino Creek to restore riparian habitat

  4. Sedimentation in Prado Basin • From 1941 to 2008, lost 25,000 acre-feet of storage below 505 ft elevation • 20,000 acre-feet remaining as of 2008 survey • Sedimentation in Prado Basin will essentially eliminate water conservation storage in 50 years if not addressed • Loss of 30,000 acre-feet per year of water

  5. Sediment Management Measures • Capture sediment in general area of River Road bridge • Captured sediment is either: • Moved to storage sites away from the river channel, generally around perimeter of Prado Basin – accessible for future aggregate use or other beneficial re-use; or • Re-entrained into SAR below Prado Dam

  6. Summary of Alternatives

  7. Cost-Benefit Analysis Assumptions • Cost of firm untreated water purchased from Metropolitan and O&M for project inflates 3% per year • Annual capital cost is estimated based on a 5% interest loan over 50 years. • Increased storage space created by sediment management is utilized one time per year.

  8. Cost Share between Corps & OCWD • Water Conservation: 100% OCWD cost • Ecosystem restoration: construction 65% Corps, 35% OCWD • O&M: 100% OCWD is standard • Can request federal cost share of O&M due to unique nature of sediment management costs (higher percentage of O&M relative to construction cost) • Exploring phased implementation of some project measures, such as sediment management measures

  9. Summary of Plan 9

  10. Summary of Plan 11

  11. Summary of Plans 9 & 11

  12. Next Steps • Reviewing cost increase to complete Study from Corps • Evaluate sensitivity to assumptions in cost benefit analysis • Release draft Feasibility Study report for public comments (includes draft EIR) • OCWD identify preferred alternative

More Related