1 / 16

Paper No. SPE 166315

Paper No. SPE 166315 Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing. Darrell Dowd. Slide 2. Slide 2. Introduction. Projects of all types represent an increasingly significant challenge.

kcorson
Download Presentation

Paper No. SPE 166315

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Paper No. SPE 166315 Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing Darrell Dowd

  2. Slide 2 Slide 2 Introduction • Projects of all types represent an increasingly significant challenge. • They also offer an increasingly significant opportunity. • EH&S issues faced in previous projects should be part of the recipe for the success of future projects. • What we do today, should improve tomorrow.

  3. Slide 3 Remember when? Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  4. Slide 4 Slide 4 But what if? Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  5. Slide 5 Slide 5 What if you could? • Increase productivity/ decrease schedule by eliminating delays. • Effectively utilize knowledge to improve future projects. • Increase safety “buy in” by making it easier to get the “job” done. • Transform safety from a cost center to a profit center. Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  6. Slide 6 Slide 6 Pre-Planning: Needs Assessment A process to review the work with key plant management stakeholders to get a clear understanding of the role each one plays. • Prepare readiness plans. • Identify causes of unplanned work. • Integrate custom fit plan into T/A Plan. • Identify peak load requirements. • Build confidence and trust among contractors.

  7. Slide 7 Pre-Planning: Needs Assessment Data gathered during execution is not only useful during project close out. Data will help: • drive efficiencies • provide actionable info • predict potential problems Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  8. Slide 8 Pre-Planning: Needs Assessment Unplanned activities can result in delays, equipment or manpower shortages and increased cost. Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  9. Slide 9 Execution Phase • Key areas for tracking: • Equipment utilization and deployment • Equipment reliability • Resource utilization and deployment • Finance – cost tracking/reporting • I/A and Near Miss reports

  10. Slide 10 Execution and Completion: Stewardship Report • Allows information flow and technology innovation driven by customer feedback. • Ensures that lessons are learnt • Proposes actions and solutions prior to the next project. Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  11. Slide 11 Sample Turnaround Utilization Chart • Daily data on usage rates, rental items and equipment utilization. • Monitor usage during project. • Plan future work with similar scope. Courtesy of United Safety LTD., 2013

  12. Slide 12 Execution and Completion: Stewardship Report • Examines and evaluates how the contractors and company personnel performed during the project. • Provides unbiased, objective recap of project. ×What didn’t work • What worked

  13. Slide 13 The Learning Loop • True Transfer Where most stop learning

  14. Slide 14 What makes a Learning Organization

  15. Slide 15 Summary • Create a learning loop, not a learning line. • Engage the SMEs to gain current project knowledge. • Its not really knowledge until it’s used. Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd

  16. Slide 16 Slide 16 • Works Cited • Garvin, D. A. 1993. Building a Learning Organization. Harvard Business Review 71 (July-August) 78-91. Retreived from http://www.slideshare.net/ProfessorAdalbertoAzevedo/garvin-1993 • Lee, S., Courtney J.F. and O’Keefe R.M. 1992. A System for Organizational Learning Using Cognitive Maps. OMEGA International Journal of Management Science 20 (Spring): 23-26. Retrieved from http://www.sciencedirect.com/science/article/pii/030504839290053A • Raybould, B. 1995. Peformance Support Engineering: An Emerging Development Methodology for Enabling Organizational Learning. Performance Improvement Quarterly, 8 (1) pp. 7-22. Retrieved from http://onlinelibrary.wiley.com/doi/10.1111/j.1937-8327.1995.tb00658.x/abstract • Senge, P.M. 1990. The Fifth Discipline: The Art and Practice of the Learning Organization. New York: Doubleday/Currency. Retrieved from http://www.giee.ntnu.edu.tw/files/archive/380_9e53918d.pdf • Sinkula J.M., Baker, W. E. and Noordewier T. 1997. A Framework for Market-Based Organizational Learning: Linking Values, Knowledge and Behavior. Journal of the Academy of Marketing Science. Vol. 25, No. 4 pp 305-318. Retrieved from http://cmapspublic.ihmc.us/rid%3D1255442990968_1707056073_21936/A%2520Framework%2520for%2520Market-Based%2520Organizational%2520Learning.pdf • Darrell Dowd • VP, Industrial, Middle East • United Safety LTD • Quality & Innovative Safety Solutions • Airdrie, AB, Canada T4A 2J8 • United Safety International • Quality & Innovative Safety Solutions • P.O. Box 500582 Office Park Building, • 3rd Floor Block A, Dubai Media City, UAE • T: +971 4 369 5075 • C: +971552367987 • dowd@unitedsafety.net Paper 166315 • Improving EH&S Practices during Turnarounds in Facilities and Plants: A Process of Knowledge Capture and Transfer worth Implementing • Darrell Dowd