Town of Hillsborough Construction & Demolition Debris Salvage & Recycling

CRRA Conference August 3-6, 2008. Town of Hillsborough Construction & Demolition Debris Salvage & Recycling. Ed Cooney Consulting Environmental Programs Manager Town of Hillsborough, CA. About the Town C&D Program Deconstruction Case Study C&D and Green Building

keitha
Download Presentation

Town of Hillsborough Construction & Demolition Debris Salvage & Recycling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CRRA ConferenceAugust 3-6, 2008 Town of Hillsborough Construction & Demolition Debris Salvage & Recycling Ed Cooney Consulting Environmental Programs Manager Town of Hillsborough, CA

  2. About the Town • C&D Program • Deconstruction Case Study • C&D and Green Building • C&D and Green House Gases • Challenges C&D Recycling in Hillsborough Overview

  3. About the Town Hillsborough is a residential community located on the San Francisco peninsula, immediately west of Burlingame:

  4. Square miles: 6.23 • Population: 11,000 • Residential properties: 4,200 • Commercial properties: 3 • Smallest residential lot size: 1/2 acre • Average home price in 2007: $2.6 million • Schools: 5 About the Town Statistics:

  5. Residential community. No commercial sector. • Lots of construction activity. Continues to be strong. • Very large residential structures = high C&D tonnage and multi-year building projects. • C&D debris is approximately 35% of the Town’s total generated waste. About the Town Waste stream characterization:

  6. Building and demo permits require a Waste Reduction Plan (WRP). Separate plans are required for house demolition and new construction. • No specific diversion requirement. Building Official or designee must approve Waste Reduction Plan. • Must use an approved debris box company and mixed debris processing facility. The Town has non-exclusive performance agreements regarding handling of mixed debris. (Source separated materials can go to any recycling facility.) Hillsborough’s C&D Program Hillsborough adopted a C&D Resolution in 1999 and a C&D Ordinance in December 2001. Key features include:

  7. A Diversion Summary Report is required prior to final inspection. Weight tickets and salvage receipts must be submitted. • The Waste Reduction Plan and the Diversion Summary Report must correlate. The “before” and “after” pictures are compared. Hillsborough’s C&D Program Ordinance features (continued):

  8. Hillsborough’s C&D Program • Demolition or construction activities performed without a permit or an approved WRP. • Failure to comply with the approved WRP. • Failure to provide all required diversion documentation prior to final inspection. Penalties: Up to 10 times the permit fee may be assessed for:

  9. Hillsborough’s C&D Program

  10. Fully funded C&D Recycling Specialist position (through MSW collection fees). Hillsborough’s C&D Program • Recycling Specialist engages the permit applicant early in the process. Program features:

  11. Emphasis on promoting highest and best use of materials: 1) deconstruction, 2) source separation, 3) mixed debris. • ADC does not count as diversion. • Largest focus on largest projects (WRP vs. Short Form). • Project and program diversion tracking. Hillsborough’s C&D Program Program features (cont.): Over 1,400 new home, demolition or major remodel construction projects have submitted WRPs and documented diversion from landfills.

  12. Hillsborough’s C&D Program remodels) educated but not quantified (Short Form). The impacts: 86% average diversion of C&D materials (excluding ADC). At least 58,000 tons (250,000 cubic yards) of documented C&D material diverted (Long Form). Thousands of other smaller projects (e.g., bathroom 250,000 cubic yards of debris piled onto an NFL football field, including both end zones, would stand 120 feet tall or over 10 stories high.

  13. The Town has integrated the C&D program into the CRW permit system at critical review and inspection touch points. An ordinance-covered project cannot receive: • Building/demolition permit prior to having an approved WRP(s). • Final inspection prior to submittal and review of the Diversion Summary Report and weight tickets. • Best to integrate C&D project tracking and reporting features during building permit system design phase. Hillsborough’s C&D Program Project tracking and permitting:

  14. Project tracking in CRW is supplemented by a diversion tracking system developed specifically for the C&D program: • Facilitates detailed (manual) CIWMB reporting. • Identified as best practice by CIWMB auditors. Hillsborough’s C&D Program Project tracking and reporting:

  15. Hillsborough’s C&D Program Individual Project Diversion Calculations

  16. Hillsborough’s C&D Program Project Diversion Calculations

  17. Hillsborough’s C&D Program Cumulative Diversion Tracking and Reporting

  18. Hillsborough’s C&D Program Diversion Tracking and Reporting

  19. Full house demolition of a 1950’s, 3400 sq. ft., ranch style home and cabana built in 1950’s. Deconstruction service subcontracted by general contractor. • Top-to-bottom deconstruction. • Deconstruction occurred approximately 4 weeks prior to scheduled demolition. • Tax write-off for owner. Hillsborough’s C&D Program Deconstruction case study: 815 Hillsborough Boulevard

  20. Wood / Lumber = 13,510 linear ft. • Examples: ceiling joists, floor joists, siding, fence panels Hillsborough’s C&D Program Deconstruction case study: 815 Hillsborough Boulevard

  21. Miscellaneous interior and exterior elements Hillsborough’s C&D Program • Examples: 2000 red clay bricks,1600 sq ft of blue slate, 1500 linear ft radiant floor tubing, garage door, opener and track. Deconstruction case study: 815 Hillsborough Boulevard

  22. Bathroom and kitchen items • Examples: Jacuzzi tub, skylight, icemaker, bread warmer, sinks. Hillsborough’s C&D Program Deconstruction case study: 815 Hillsborough Boulevard

  23. Doors, windows, and lighting Hillsborough’s C&D Program • Examples: double front door set, French doors, all windows, 113 various lighting fixtures. Deconstruction case study: 815 Hillsborough Boulevard

  24. Debris materials separated onsite • Wood waste • Metal • Green waste • Concrete Hillsborough’s C&D Program Deconstruction case study: 815 Hillsborough Boulevard

  25. Project diversion rate = 89% (not including ADC) Hillsborough’s C&D Program Deconstruction case study: 815 Hillsborough Boulevard

  26. Green Building in Hillsborough • Green Building program initiated in January 2008. • All permits that require WRP must submit Build It Green checklist. • No minimum point requirement—voluntary program. • Gathering data: expect program to move to mandatory for private sector (ordinance). Mandatory civic ordinance and resolution for private sector voluntary measures:

  27. Green Building in Hillsborough • Complementary goals in waste and GHG reduction. • Same workflow and permit system touch points. • Combined outreach/education effort ensures efficiency. • Similar staff skill set required. • Hillsborough green building program piggy-backed on the existing C&D program. • Contact Hillsborough Building Department for more info. The combination of C&D and Green Building programs is a natural fit for Hillsborough:

  28. Emissions Reductions from a Model GreenPoint Rated New Home Green House Gases and C&D Source: StopWaste.org

  29. GHG emission inventory protocols underestimate and undervalue solid waste impacts (lifecycle). Green House Gases and C&D

  30. Hillsborough’s C&D Program • Challenges • Extra time for deconstruction. • Dependency of deconstruction on tax benefits. • Mixed debris facility diversion rates. Conclusion A highly successful and well-established recycling program.

  31. Questions Ed Cooney ecooney@hillsborough.net