An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proton Improvement Plan (FY13 PMG Q3)

  2. PIP • FY13 Q3 Summary • Task Highlights • Budget and Labor Review Summary • Outstanding Issues • Plans - Schedule • FY13 Budget Updates • FY13 Goals/Issues - Next Quarter • Additional PIP Items William Pellico, Fermilab PMG, Aug 21 2013

  3. PIP – Path to Higher Proton Throughput and Reliability Linac Modulators Shielding Improvements LCW systems Transformers BPM systems Linac HP RF Linac Notch Booster Anode Supplies Bias Supplies New Tuners New Cavities Collimation System Booster Solid State RFQ Injector Dampers Booster Cavity Refurbishment Over 30 Tasks ~87 M $$ ~ 7 years of work Beam Physics/Optics Booster Notcher/Absorber Cogging William Pellico, Fermilab PMG, Aug 21 2013

  4. FY13 Q3 Task Summary – Highlights William Pellico, Fermilab PMG, Aug 21 2013

  5. PIP FY13 Milestone Summary FY13 Q1 FY13 Q2 The current RLS is out of date and is being updated. Effort to adjust RLS when changes to budget and labor occur is challenging. FY13 Q3 Completed Not Completed William Pellico, Fermilab PMG, Aug 21 2013

  6. WBS 1.1 LINAC FY13 Q3Summary Tasks at a Glance William Pellico, Fermilab PMG, Aug 21 2013

  7. Linac Notch Creation WBS 1.1 LINAC (Highlights)WBS 1.1.1.2 Modulators WBS 1.1.2.3 Linac Notch CreationWBS 1.1.5.1 Power Distribution 3D Print of laser cavity Hatch Install Lattice in TraceWin Modulator 3 Cell Testing Detailed study DTLregion William Pellico, Fermilab PMG, Aug 21 2013

  8. WBS 1.2 Booster FY13 Q3Summary Tasks at a Glance William Pellico, Fermilab PMG, Aug 21 2013

  9. WBS 1.2 Booster (Highlights)1.2.2.3Notcher System • 1.2.1.5Cavity Refurbishment Cavity preparing to repair flanges Buildup of High Voltage Rack for Short Kickers Cones and new cooling loops Labor intensive work William Pellico, Fermilab PMG, Aug 21 2013

  10. Saga of new ferrites for cavity tuners Issues: Old Vendors Gone New vendors having difficulty making similar ferrites…. Looking for high Q, low loss and two values of mu ~(12, 20) TD ready to build tuners once we have ferrites William Pellico, Fermilab PMG, Aug 21 2013

  11. William Pellico, Fermilab PMG, Aug 21 2013

  12. WBS 1.2.2 Accelerator Physics (Booster) • WBS 1.2.2.2 Alignment & Aperture • Magnet moves • Scans Location Long 16 Vertical Move This was the fourth area where we moved magnets…. More to come mm Tunnel Location William Pellico, Fermilab PMG, Aug 21 2013

  13. Budget and Labor Review Summary William Pellico, Fermilab PMG, Aug 21 2013

  14. FY13 To-date FTEs by OHAP – Fcstvs Act William Pellico, Fermilab PMG, Aug 21 2013

  15. FY13 To-date FTEs by Div – Fcst vs Act William Pellico, Fermilab PMG, Aug 21 2013

  16. PIP Labor Usage (FTE) Planned Actual William Pellico, Fermilab PMG, Aug 21 2013

  17. PIP M&S 82% of FY13 Allocated April - Correction for Solid State Task Closure Labor & M&S K$ William Pellico, Fermilab PMG, Aug 21 2013

  18. Supplemental Spending Additional funds were provided in July – Although part of Q4 – This is a significant $$ and will have a positive effect on the schedule. Part of funds will be used to remedy the recent PS budgets which impacted PIP goals (7835 tubes). Part of funds will be used to put back track PIP items impacted from previous reductions (e.g. laser notcher). Part of funds will be used to move tasks forward (Refurb) William Pellico, Fermilab PMG, Aug 21 2013

  19. Plans - Schedule

  20. Proton Source/PIP – FY13 Calendar While waiting for users PIP continues to take advantage of Proton Source only operations: Goals (PIP & PS) On Schedule OLD Booster Beam Dump/High Intensity Tuning MI Startup Q2 William Pellico, Fermilab PMG, Aug 21 2013

  21. Proton Improvement Plan Projection NOvA Shutdown 120 GeV LBNE g-2 8 GeV Mu2e MiniBooNE Maybe William Pellico, Fermilab PMG, Aug 21 2013

  22. Additional PIP Items

  23. Cooperation on Linac Power Amplifiers Brookhaven Linac is very similar design to Fermilab Low-Energy Linac • Not interested at this point in any financial arrangement SLAC SOW to provide expertise and local oversight for the klystron prototyping LANL has sent information on their pursuit of a 200 MHz klystron (CPI). Interested but still pursuing Thales tube. William Pellico, Fermilab PMG, Aug 21 2013

  24. Nigel 6 Nigel Tour of MI-60 / Cavity Refurbishment Work Nigel visit to MI-60 to try and understand why it is taking so long to refurbish cavities. Reassures us that once he is in charge – things will change. William Pellico, Fermilab PMG, Aug 21 2013

  25. PIP FY13 Q3 Summary & Concerns WBS 1.1 Linac • Linac WBS efforts are in good shape • Klystron effort continues – Business Services/CPI/PIP • Modulator efforts continue with both SLAC and AD/EE support • Simulation and Studies-> continue development code for DTL lattice, WBS 1.2 Booster • Cavity Refurbishment – Labor & Time constraints • Contract Employees • Dosage (ALARA) – will need to rotate personnel • Need to deal with operations vs. repair (MI startup) • Booster shielding – progressing • Booster Rep rate limit – still unresolved and require testing • Booster has not found a ferrite that meets our High μ need • Delaying new tuners • Booster High Intensity/rep rate: MI starts up soon and will be first real test Supplemental Funding – Big Boost and will help PIP/FY14 William Pellico, Fermilab PMG, Aug 21 2013