An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CTS Decommission ProjectLegacy Campus Fiber Network September 2012 Bruce Shurtz TSD

  2. Overview Consolidated Technology Services (CTS) has operated the CFN service on the Capitol Campus in Olympia since the late 1990’s. This service has provided 10/100Mb Ethernet connectivity to various state operated buildings on the Olympia campus. Though this legacy network has served agencies well for over a decade, the equipment, technology and design comprising it are no longer a supportable service for CTS to provide. The network design does not meet newer standards required for an optimally resilient and redundant network service, and creates an undue potential risk to customers served by it.

  3. General Service Status • Sun-setting of service • Provided 10/100Mb network service on Capitol Campus • Replaced by State Metropolitan Optical Network (SMON) • No existing contractual commitments • On-going customer demand met by SMON service • Legacy equipment out of support (OOS)

  4. Financial Summary

  5. Sourcing and Contracts • No existing contracts. • All equipment EOL & OOS. • All Fiber Infrastructure is amortized.

  6. Service Roadmap • Migrate existing CFN customers to SMON • Grandfather existing circuits at same cost until FY13 • Decommission Legacy CFN equipment.

  7. Actions • Brief CAC on decommission plan Oct 3, 2012 • Start Decommission Project 10/15/2012 • Complete Decommission Project 9/30/2013