1 / 27

ELC 347 project management

ELC 347 project management. Week 12. Agenda. Integrative Project 4 th part due Outline of deliverables (posted in WebCT) Quiz 2 Corrected More effort wouldn’t hurt Today we will discuss Critical Chain Project Scheduling . Schedule for the final few Days. Nov 28 Assignment 5 due

lali
Download Presentation

ELC 347 project management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ELC 347 project management Week 12

  2. Agenda • Integrative Project • 4th part due • Outline of deliverables (posted in WebCT) • Quiz 2 Corrected • More effort wouldn’t hurt • Today we will discuss Critical Chain Project Scheduling

  3. Schedule for the final few Days • Nov 28 • Assignment 5 due • Nov 30 • IP part 5 due • Discussion on resource Leveling (Chap 12) • Dec 7 • IP part 6 Due (will be corrected and returned within 24 hours) • Quiz 3 Assigned (Chap 10, 11, 12, & 13) • Discussion on Project Evaluation and Control (chap 13) • Dec 8 @ Midnight • Resubmission of IP part 1 – 5 deadline • Dec 11 @ 10 AM • IP project (complete) due • Resubmission of Part 6 • IP project Presentation • Dec 15 @ noon • Quiz 3 Due • One less quiz and 2 less assignments then was identified in syllabus

  4. Course Grading Rubric

  5. Critical Chain Project Scheduling Chapter 11 © 2007 Pearson Education

  6. BAE Systems http://www.baesystems.com/

  7. Theory of Constraints & Critical Chain Project Scheduling A constraint limits system output. The Goal – Goldratt TOC Methodology • Identify the constraint • Exploit the constraint • Subordinate the system • Elevate the constraint • Repeat the process

  8. Dr J Edwards Deming

  9. Variation Common Cause Inherent in the system Special Cause Due to a special circumstance Managers should • Understand the difference between the two • Not adjust the process if variation is common cause • Not include special cause variation in risk simulation • Not aggregate discrete project risks

  10. 25% 50% 80% 90% time CCPM and the Causes of Project Delay How safety is added to project activities • Individual activities overestimated • Project manager safety margin • Anticipating expected cuts from management Gaussian Distribution

  11. Wasting Extra Safety Margin • The Student Syndrome • Immediate deadlines • Padded estimates • High demand • Failure to pass along positive variation • Other tasks • Overestimation penalty • Perfectionism • Multitasking • Path Merging

  12. Critical Chain Solutions • Central Limit Theorem • Standard deviation of the sum is less than the sum of the standard deviations! • Aggregating risk leads to reduced risk • Activity durations estimated at 50% level • Buffer reapplied at project level • Goldratt rule of thumb (50%) • Newbold formula (2σ) • Feeder buffers for non-critical paths

  13. CCPM Changes • Due dates & milestones eliminated • Realistic estimates – 50% level not 90% • “No blame” culture • Subcontractor deliveries & work scheduled ES • Non critical activities scheduled LS • Factor the effects of resource contention • Critical chain usually not the critical path • Solve resource conflicts with minimal disruption

  14. Bob Bob Bob Feeder Buffer Feeder Buffer Feeder Buffer ProjectBuffer Critical Chain Solutions Buffers protect constraints and prevent delays

  15. Critical Chain Project Portfolios Drum – system-wide constraint that sets the beat for the firm’s throughput • Drum – person, department, policy, resource • Capacity constraint buffer – safety margin between projects • Drum buffer – extra safety before the constraint

  16. Applying CCPM to Project Portfolios • Identify the drum • Exploit the drum • Prepare a schedule for each project • Determine priority for the drum • Create the drum schedule • Subordinate the project schedules (next slide) • Elevate the capacity of the drum • Go back to step 2

  17. Subordinating Project Schedules • Schedule projects based on drum • Designate critical chain • Insert capacity constraint buffers • Resolve any conflicts • Insert drum buffers so the constraint is not starved

  18. CCPM Critiques • No milestones used • Not significantly different from PERT • Unproven at the portfolio level • Anecdotal support only • Incomplete solution • Overestimation of activity duration padding • Cultural changes unattainable

  19. Problems on 373 • Assignment 5 • Problems 1,2,3 4 & 5 on page 373 & 373 • Pert to CCPM • Figure total Duration • Take 50% activity duration • Figure new total duration • Project buffer = 50%(old –new) • If you have non critical path critical • Change to Late start • Feeder buffer is 50% of slack on non –critical path

More Related