1 / 40

Thailand’s experiences in the power sector

Thailand’s experiences in the power sector. Chuenchom Sangarasri Greacen Chris Greacen, Ph.D. Palang Thai International Seminar on Dams and Sustainable Energy 24 March 2005 Melia Hotel, Hanoi, Vietnam. Overview. Energy consumption and economic development

leach
Download Presentation

Thailand’s experiences in the power sector

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Thailand’s experiences in the power sector Chuenchom Sangarasri Greacen Chris Greacen, Ph.D. Palang Thai International Seminar on Dams and Sustainable Energy 24 March 2005 Melia Hotel, Hanoi, Vietnam

  2. Overview • Energy consumption and economic development • Thai government’s energy strategies • Current practices and consequences of Thai power sector planning • Load growth forecast • Power development plan (PDP) • GMS Grid • An alternative to the supply-driven power sector planning • Thailand’s abundant clean energy opportunities • 8% target • Potential • Examples

  3. Thailand compared with Vietnam Source: CIA World Factbook, 2005

  4. Thailand’s power consumption growth outstrips economic growth

  5. 1.0 (2008) Thai government has set a target for energy elasticity

  6. Ratio of GDP growth to electricity demand growth in Thailand * Source : EGAT’s Power Development Plan 2003 ** Source : Electricity Demand Forecast Report, January 2004

  7. January 2004 Demand Forecast

  8. Past peak demand projections tended to over-estimate

  9. Power Development Plan (Planned installed capacity = peak demand + 15% reserve)

  10. Regional Power Grid • Main agenda of regional cooperation • Claimed benefits: • Increased reliability, shared power reserves • Energy transfer among member countries with different peak periods, resources • Savings of 1,377 – 2,554 MW new capacity avoided (Source: ADB’s GMS Grid Master Plan)

  11. 2020 Peak Demand in GMS Countries Source: Norconsult, Indicative Master Plan on Power Interconnection in GMS Countries, June 2002

  12. ADB’s Interconnection Master Plan for GMS countries Source: Norconsult, Indicative Master Plan on Power Interconnection in GMS Countries, June 2002

  13. Reality of GMS Power Grid:expensive, risky investment • Costs excluded in analysis: • Control center • Water usage • Regulator & reliability coordination • Transitional costs • Increased vulnerability: events in Laos/Cambodia determine reliability of Thai Grid *Cost savings of extended power cooperation scenarios over base case Source: Comments on Indicative Master Plan on Power Interconnection in GMS Countries by Bretton W. Garrett, P.Eng., Ph.D.

  14. US$10 billion overinvestment The public is bearing high electricity costs as a result of THB 400 billion (US$10 billion) over-investment of in power generation. -- Thai Prime Minister Thaksin Shinawatra Source: The Nation (2003). “PM Pressing for Egat IPO this year’. The Nation. March 14.

  15. There is an alternative to the supply-driven, capital-intensive power sector planning

  16. Revised Peak Demand Forecast Reduction of 6,290 MW

  17. EGAT’s PDP 2004 Alternative PDP Thermal Kra Bi #1 340.0 MW Gas Turbine Lan Kra Bue 122.0 MW Lum Ta Kong hyfro dam #1-2 500.0 MW BLCP Power #1-2 1,346.5 MW Gulf Power Generation 700.0 MW Ratchaburi Power #1-2 1,400.0 MW SPP (renewable) 151.1 MW 60.0 MW SPP (old power purchase declaration) Nam Thuen 2 in Laos 920.0 MW total 5539.6 MW Projects under construction/negotiation

  18. New Projects EGAT’s PDP 2004 Alternative PDP

  19. Cleaner, more economic, more efficient sources of supply are not given due consideration despite high potential COGEN Renewable Energy

  20. DSM & Cogeneration: big potential • DSM • 2000 to 3000 MW: “Achievable and cost effective DSM” in 1991 (Utility study) • IIEC (International Institute for Energy Conservation). 1991. Demand Side Management for Thailand’s Electric Power System: Five-Year Master Plan. Submitted to Electricity Generating Authority of Thailand, Metropolitan Electricity Authority and Provincial Electricity Authority, Bangkok, Thailand. Bangkok, Thailand. November. • Cogeneration • 8610 MW cogen installed as of 2001 • http://www.jxj.com/magsandj/cospp/2002_05/cogen_southeast_asia.html • Since 1998, utilities accepting no new cogen. At least 3,000 MW of additional cogen had applied and have not been accepted.

  21. Hourly electricity load duration curve (year 2002) > 1,000 MW in 66 hours

  22. Renewables account for very little of Thailands’ installed generating capacity Imported coal 0.6% grid-connected renewables Big hydro lignite Fuel oil Natural gas TOTAL: 26,000 MW Source: EGAT (2003). Power Development Plan

  23. Thai government target: 8% renewable energy by year 2011 Conventional energy 81% TE 16.5% TE = Traditional Energy NRE = New & Renewable Energy NRE 0.5% (265 ktoe) 2002 TE 11% 52,939 KTOE Conventional energy 81% NRE 8% (6,668 KTOE) 2011 83,354 KTOE

  24. Electricity 1,170 KTOE Thai government target & strategy for renewable energy • RPS 437 MW • - Solar 200 MW • Wind 100 MW • MSW 100 MW • - Biomass • - Hydro INCENTIVE 37 MW Electricity Solar 6 MW Wind 0.2 MW Biomass 560 MW RPS Incentive 1,093 MW -Biomass -Hydro RE 8% Heat ~ 0.00 KTOE RE 0.5% Heat (Incentive) 3,900 KTOE Bio fuel ~ 0.00 KTOE Bio Fuel(Incentive) 1,600 KTOE Ethanol 3.0 M liter/day Bio diesel 2.4 M liter/day R & D Facilitator 2002 2011 Replacement of imported oil 48 mill. barrels values 96,537 Mill. Baht

  25. Estimate of installed grid-connected renewables in Thailand (2004) Source: 2003 Thai government figures + updates for biogas & PV based on recent installations

  26. Estimated renewable energy potential in Thailand * Commercial potential based on actual prices paid to renewable energy generators currently on-line Source: Technical potential and Targets from Thai Ministry of Energy. (2003).“Energy Strategy for Competitiveness” http://www.eppo.go.th/admin/moe-workshop1/index.html. Commercial potential from from Black & Veatch 2000 and NEPO/DANCED 1998 as well as interviews with power plant managers.

  27. Breakdown of economically viable biomass resource Source: Black and Veatch (2000). Final Report: Thailand Biomass-Based Power Generation and Cogeneration Within Small Rural Industries. Bangkok, NEPO; NEPO/DANCED (1998). Investigation of Pricing Incentive in a Renewable Energy Strategy -- Main report. Bangkok. Bagasse figure from interview with interview with Sirisak Tatong, power plant manager at Mitr Phol sugar factory. Biogas from interviews with biogas developers

  28. Technology is available… • Steam turbines for direct combustion of biomass • Rice husk, wood chip, palm husk, bagasse, coconut husk, etc. • Size >1 MW • Capital cost $1200/kW • Commercially available in Thailand • Bio-digestors & engines for biogas • Pig manure, cassava, palm oil, municipal wastes, distillery slop • Size > 30 kW • Problems with SO2 resolvable • Gasifiers • Rice husk, wood chip • Size > 50 kW. • Problems with tar in some fuels • Commercially available for wood chip

  29. Reduces air and water pollution Produces fertilizer Produces electricity Biogas from Pig Farms

  30. Biogas from Pig Farms

  31. Community micro-hydro • Mae Kam Pong village, Chiang Mai • 40 kW • Community cooperative • Expected gross revenues: 30,000 baht/month

  32. 40 kW micro-hydro generator at Mae Kam Pong

  33. Korat Waste to Energy - biogas • Uses waste water from cassava to make methane • Produces gas for all factory heat (30 MW thermal) + 3 MW of electricity • Earns high market returns • Developer estimates 300 MW from waste water + 800 MW from wet cake

  34. Korat Waste to Energy - biogas • 3 x 1 MW Jenbacher gas generators

  35. Thank you For more information, please contact chom@palangthai.orgchris@palangthai.org

  36. EGAT (Thermal Generation) ~ 15,000 MW Power Purchase IPP/Egco/Ratch/SPP ~ 10,000 MW New generation (distributed generation/ community-owned/ renewables) New Generation (Private sector) Independent Regulatory Body Transmission Utility (EGAT Transmission) Transmission System Operation Hydropower Existing demand ~ 19,000 MW New demand (residential/small businesses/ others) New demand (large users) Distribution Utilities (MEA/PEA) Distribution Supply/Retail * Proposed reform for Thailand’s power sector กัน * Communities and local bodies have the right to manage and procure their own power supply if they wish. MEA/PEA provide distribution services but do not monopolize the system use.

  37. EGAT PDP Excessive electricity demand prediction Little consideration of clean/cost-effective alternatives Alternative PDP Correct errors; revise demand based on historic growth Incorporate DSM, cogeneration, and renewable energy The “alternative PDP”: a response to the problems of supply-driven planning process

More Related