An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac4-PSB 160 MeV connection readiness review Tuesday 30 August 2016

  2. BE-BI Jocelyn Tan • Table of Contents: • Equipment dismantling • Equipment installation • Risks / Mitigation • Summary Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  3. Equipment dismantling Dose rates source: https://espace.cern.ch/rpps/public-portal/Shared%20Documents/Linac2/2016-04-13_Linac2.pdf https://espace.cern.ch/rpps/public-portal/Shared%20Documents/PS_Booster/2016-06-07_Booster.pdf Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  4. Equipment installation: Linac4 TLs Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  5. Equipment installation: BI line (1) Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  6. Equipment installation: BI line (2) Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  7. Equipment installation: PSB Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  8. Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI

  9. Summary • A list of 24 BI activities to be carried out with: • EN-EL, TE-VSC: heavily involved in over 20 activities • EN-HE, TE-ABT, HSE-RP, BE-OP. • Readiness for December 2016: • Linac4 instruments: Ready • BI line and new injection region: Ready • PSB orbit and intensity: Ready • The tune PUs shall be ready for Q1 2017. • Risk assessment • Minimum HW commissioning time requested • Some new systems need validation with beam: H0/H- current meas. with HST, BTMS • Technology used is well known and robust • Risk is low • No showstopper for Linac4-PSB 160MeV connection Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI