An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 3 Managing ProjectProcesses

  2. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop an information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital Example 3.1

  3. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time J has 3 prior Figure 3.1 Example 3.1

  4. Path Expected Time (wks) A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time Figure 3.1 Example 3.1

  5. I 15 12 27 Earliest start time Earliest finish time 48 63 Latest start time Latest finish time F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 Figure 3.2 St. Adolf’s Hospital Latest Start and Latest Finish Times

  6. St. Adolf’s Hospital Gantt Charts Figure 3.3

  7. Activity Slack I 15 12 27 48 63 SlackK = 0 or SlackK = 0 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Finish Start 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 Example 3.3 St. Adolf’s Hospital Activity Slack Analysis

  8. Node Duration ESLS Slack A 12 0 2 2 B 9 0 0 0 C 10 12 14 2 D 10 9 9 0 E 24 9 35 26 F 10 12 53 41 G 35 22 24 2 H 40 19 19 0 I 15 12 48 36 J 4 59 59 0 K 6 63 63 0 I 15 12 27 48 63 F 10 K 6 63 69 12 22 63 69 53 63 C 10 G 35 12 22 22 57 Finish 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 Example 3.3 St. Adolf’s Hospital Critical Path

  9. I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 Example 3.3 St. Adolf’s Hospital Critical Path

  10. St. Adolf’s Hospital Activity Slack Figure 3.4

  11. St. Adolf’s Hospital I A F K C G Start Finish B D H J E

  12. St. Adolf’s Hospital Activity Duration Earliest Start Latest Start Slack C 10 16 14 –2 G 35 26 24 –2 J 4 61 59 –2 K 6 65 63 –2 D 10 10 9 –1 H 40 20 19 –1 E 24 10 35 25 I 15 16 48 32 F 10 16 53 37 Table 3.1

  13. Definition and organization Planning Execution Close out Resource requirements Start Finish Time Project Life Cycle Figure 3.5