Offshore Ice-Resistant Stationary Platform “ Prirazlomnaya ” Constructed at PO “ Sevmash ” in the town Severodvinsk. Alexandrova readings – 2012 Scientific and Research Centre « Kurchatov Institute », Moscow , 13.02.2012. Main route. Murmansk. Oil field.

lilli
Download Presentation

Alexandrova readings – 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Offshore Ice-Resistant Stationary Platform“Prirazlomnaya”Constructed at PO “Sevmash”in the town Severodvinsk Alexandrova readings – 2012 Scientific and Research Centre «Kurchatov Institute», Moscow, 13.02.2012

  2. Main route Murmansk Oil field On 25.08.2011 the first offshore ice-resistantstationary platform in Russia was delivered to “Prirazlomnoe” oil filed in Barents Sea

  3. MLSP “Prirazlomnaya” is at the oil field

  4. Technical Characteristics of the Platform Length (with a helipad), m 139 Width (with a helipad), m 144 Overall height (with a torch mast), m 141 Caisson length, m126 Caisson width, m 126 Caisson height above bottom level, m 24 Weight without a ballast, t 117000 Firm ballast weight, t 122000 Number of wells 40 Oil production, m3per day/mil. of tons per year 21000/up-to 6,5 Oil storages capacity, m3 131000 Oil dispatch devices “Kupon” 2 Oil dispatch speed, m3/hour10000 Main turbo generators power, mWt (e) 3 х 28 Personnel, persons 200 Autonomy, days60 Service life, years25 Sea depth at the installation place, m 19 Distance from the shore, km60

  5. Severodvinsk, 1992 In 1992 with support of the President of Russia Yeltsin B.N. GAZPROM, SEVMASH and Kurchatov Institute headed progress of enormous oil and gas recourses development of the Russian Arctic shelf on the basis of nuclear underwater shipbuilding technologies and productions. From left to right: President of the Stategas group ofcompanies“Gazprom” Chernomyrdin Victor Stepanovich President of the Research and Scientific Centre “Kurchatov Institute” Velikhov Evgeny Pavlovich General Director of PO “Sevmash” Pashaev David Guseynovich

  6. Meeting of the Founders of “Rosshelf” On 07.05.1992 in “Kurchatov Institute” the Meeting of the Founders of the Russian company for shelf development took place. The shareholders of “Rosshelf” became GAZPROM, SEVMASH, MK of Cherepovets, ARKHANGELSKGEOLOGIYA, “Kurchatov Institute”, the leading enterprises in the sphere of nuclear underwater shipbuilding, oil and gas fields development.

  7. Chairman of the Board of Directors-President of “Rosshelf” company was elected Velikhov Evgeny Pavlovich; he hold this position till April, 2001. The First Chairman of the Board of Directors of “Rosshelf” became Grechkov Yury Nikolaevich, the Chief Designer of nuclear submarines of PO “Sevmash”. Velikhov E.P. Grechkov Y.N.

  8. The Board of Directors of “Rosshelf” made the decision on construction beginning of “Prirazlomnaya” offshore ice-resistance stationary platform at PO “Sevmash” in winter, 1995. 05.12.1995. Solemn laying of PO “Sevmash” platform.

  9. Director of “Brown and Root Energy Services” in Russia Walter Jackson Chief Designer of Central Design Bureau MT “Rubin” Kovalev Sergey N. MT “Rubin” and “Brown and Root” were the originators of concept forming of offshore ice-resistant stationary platform for “Prirazlomnoye” oil field.

  10. Caisson Components Protection (deflector) Blocks Superblocks Caisson dimentions 126x126x40,5 m, weight 72 thousand tons

  11. Caisson superblock bottom sections assembly and joining in Shop

  12. A caisson block is transferred between Shops

  13. Superblock 3 in Shop

  14. The last caisson superblock transportation from Shop

  15. Transportation of each superblock became a solemn event for a plant personnel and participants of the project

  16. At the plant quay superblocks joined together by special devices and welded above and below of water line. More than 15 km of hull structures welding joints were performed.

  17. Divers of “InterAqua” company provided welding of three joint sealing devices. More than 500 m of joints were performed by special mechanisms for underwater welding. In the course of UGS dismantling the underwater cutting was used.

  18. Deputy General Director of PO “Sevmash” Borodin V.V. Chief Designer of the Central Design BureauMT “Rubin” Gintovt A.R. The platform design and construction was carried out at the close cooperation of PO “Sevmash” and MT “Rubin”

  19. Intermediate deck forming at the quay

  20. Rolling-on of the top structure on a caisson in Severodvinsk

  21. Installation of accommodation module by RAMBIZ floating crane

  22. On the platform drilling system module, power engineering devices, oil dispatch devices, helipad, etc. were installed.

  23. 11.2010. MLSP “Prirazlomnaya” tugging to Murmansk for construction completionand taking of firm ballast - concrete

  24. Platform at 35 SRZ mooragein Murmansk

  25. Two mobile concrete plants were installed ashore close to the platform and 122 thousand tons of concrete was injected into the platform base in spring, 2011.

  26. Velikhov E.P. with a group of the platform builders in Murmansk. May, 2011.

  27. We’ve done it! In August, 2011 the project builders and participants saw off the platform from Murmansk to the installation site in Barents Sea

  28. At the solemn meeting SEVMASH, GAZPROM and Kurchatov Institute called on.

  29. The platform was installed at “Prorazlomnoye” oil field in Barents Sea on 28.08.2011 at 02:00 AM

  30. МЛСП For soil erosion prevention laying of protective berm was performed along the perimeter Stone and crushed stone berm “Prirazlomnaya” Platform “Seahorse” Dutch vessel made six cruises from Murmansk and discharged 102 thousand tons of stone and crushed stone into the berm

  31. On 23.09.2011 Prime Minister Putin V.V. at “Arctic is the Dialogue Territory” International Conference identified “Prirazlomanya” platform construction and installation at the site as the beginning of the Russian Arctic shelf practical development

  32. High-quality cold-resistant steel was produced in Russia. • In large industrial scales cold-resistant steel welding technology was developed. • The Project allowed to carry out plant radical modernization and provided support and staff preservation during the most severe 1990’s. • Cooperation with foreign Designers allowed to assimilate the advanced design methods. • Unique experience with large number of contractors including the foreign contractors is received. • Technology of afloat structures assembly nearly any dimensions using underwater welding is developed and assimilated. • The extensive offshore experience in the Arctic conditions is received. • Uniformity of design supervision approaches is necessary. • Design institute for the shelf development of the Russian Federation is necessary to create.