1 / 23

Utility Coordination

Utility Coordination. SW Region – Madison Office April 22, 2013. SW Region Utility Staff. TSS Supervisor Ruth Alfaro Utility Engineer Matthew Dapp Utility Coordinators Gary Plummer (Madison) Chad Renly (Madison) Bobbie Keck (Madison) Gary Jackson (La Crosse) Bob Gonia (La Crosse)

liona
Download Presentation

Utility Coordination

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Coordination SW Region – Madison Office April 22, 2013

  2. SW Region Utility Staff • TSS Supervisor • Ruth Alfaro • Utility Engineer • Matthew Dapp • Utility Coordinators • Gary Plummer (Madison) • Chad Renly (Madison) • Bobbie Keck (Madison) • Gary Jackson (La Crosse) • Bob Gonia (La Crosse) • Utility Permit Coordinator • Mark Goggin (Madison/La Crosse)

  3. Objectives • Reasons for Coordination • What is Trans 220? • Trans 220 Process • Compensability • Non-Compensable Timeline (No Plat) • Compensable Timeline (R/W Plat) • Common Project Issues • Common Design Conflicts • Common Construction Conflicts

  4. Reasons for Coordination • Utility relocations are one of most common reasons for project delays and increased project cost • Avoid, minimize, mitigate • Reduce number of conflicts in design & construction • Save money and time • Reduce delays in construction • Letting may be delayed • Increase safety

  5. What is Trans 220? • Administrative rule that implements State Statute 84.063 Utility Facilities Relocation (state law) • Objective of law and rule is to prevent delays to the highway contractor caused by utility relocation activities • Applies to all state trunk highway improvement projects that have facilities on them and are let to contract • “Improvement” includes construction, reconstruction, rehabilitation, and processes incidental to building, fabricating, or bettering a highway or street, but not maintenance

  6. What is Trans 220? • Local Roads and Connecting Highways are NOT required to follow Trans 220 • Trans 220 imposes specific timeframes for various activities • All days are calendar days

  7. Trans 220 Process • Utilities notified of project (1077’s) • Typically at time of OPM (Operation Planning Meeting) • Utility has 60 days to respond with system maps • Send completed plans to utilities (1078’s) • Typically at 60% plan completion • Utilities notified of potential conflicts • Requires a completed plat (for compensable parcels) • Utility has limited time to review the project plans and develop a work plan • Resurfacing – 60 days • Pavement Replacement – 90 days • Stand-alone Bridge Replacement – 90 days • Reconditioning – 120 days • Reconstruction – 120 days • Expansion – 120 days • Major Project – 120 days

  8. Trans 220 Process • Utilities notified of project (1077’s) • Typically at time of OPM (Operation Planning Meeting) • Utility has 60 days to respond with system maps • Send completed plans to utilities (1078’s) • Typically at 60% plan completion • Utilities notified of potential conflicts • Requires a completed plat (for compensable parcels) • Utility has limited time to review the project plans and develop a work plan • Resurfacing – 60 days • Pavement Replacement – 90 days • Stand-alone Bridge Replacement – 90 days • Reconditioning – 120 days • Reconstruction – 120 days • Expansion – 120 days • Major Project – 120 days

  9. System Map

  10. Trans 220 Process • Utilities notified of project (1077’s) • Typically at time of OPM (Operation Planning Meeting) • Utility has 60 days to respond with system maps • Send completed plans to utilities (1078’s) • Typically at 60% plan completion • Utilities notified of potential conflicts • Requires a completed plat (for compensable parcels) • Utility has limited time to review the project plans and develop a work plan • Resurfacing – 60 days • Pavement Replacement – 90 days • Stand-alone Bridge Replacement – 90 days • Reconditioning – 120 days • Reconstruction – 120 days • Expansion – 120 days • Major Project – 120 days

  11. Trans 220 Process • Additional 30 days will be added if coordination is required with other utility facility owners, or if the work is compensable • Designer reviews work plans – if rejected, utility has 30 days to redo and resubmit • Utility companies have 60 days to redesign their plan if any changes are made to the original plans • If WisDOT requires additional work to a utility facility after the facility has been relocated in accordance with a work plan, the department shall bear the reasonable cost of additional work

  12. Trans 220 Process • WisDOT reviews and approves utility work plan • Used to write USR and “Utility” Special Provisions • Utility company obtains a permit from WisDOT to work on right-of-way • Utilities should be allowed one year to relocate facilities prior to letting • If utility company does not follow Trans 220, utility company will be liable to the contractor for all delay costs and liquidated damages incurred by the contractor • If WisDOT does not follow Trans 220, WisDOT will be liable to the contractor for all delay costs and liquidated damages incurred by the contractor

  13. Compensable Facility • WisDOT will pay for the cost to relocate or adjust utility facilities that occupy an area being acquired for highway right-of-way where the utility has acquired a land interest either through an easement or under prescriptive rights • Typically, utility facilities that lie in existing highway right-of-way are not eligible for compensation • Utility company will obtain a permit which grants them the right to occupy highway right-of-way • Allow 8 weeks for processing in Central Office

  14. Non-Compensable Timeline (No Plat) • 60 days to respond • Time depends on project complexity Send 1077’s to Utilities Send 1078’s to Utilities • Utilities Identified • Compare field survey to system maps At OPM At 60% Plan Complete Trans 220 • Time depends on project scope – 60, 90, 120 days • 7 months Utility Work Plans Due • Potential conflicts are identified • Utilities develop work plan • Work plans reviewed/approved • USR and special provisions written • Permitting process • Utility Relocates • 3 to 6 months PSE Date LET Date • Send final plans to utilities • Addendum if necessary • Add 60 days if plan change • Add 30 days if coordination required with other utilities

  15. Compensable Timeline (R/W Plat) • Time depends on project duration • 60 days to respond Send 1077’s to Utilities Send 1078’s to Utilities • Utilities Identified • Compare field survey to system maps At OPM At 60% Plan Complete Trans 220 • Time depends on project scope – 90, 120, 150 days • 2 months Utility Work Plans Due • 2 months UTL PSE • Work plans reviewed/approved • Potential conflicts are identified • Utilities develop work plan • Requires finished plat • Add 30 days if compensable • Compensable issues to CO for review • 7 months • 3 to 6 months LET Date UTL Date PSE Date • Utilities cleared by CO • USR and special provisions • Permitting process • Utility Relocates • Send final plans to utilities • Addendum if necessary • Add 60 days if plan change • Add 30 days if coordination required with other utilities

  16. Common Project Issues • August/November PS&E dates • Utility will need to relocate in winter months • Higher costs when dealing with frost issues • Advanced/compressed schedules • Utilities are allowed timeframes specified by law in Trans 220 • Utilities need time to budget, bid work, order material • Right-of-Way not clear • Utility needs time to move facilities

  17. Common Design Conflicts • Cuts or fills for side roads/driveways • Cuts for driveways may not be shown on cross sections • Excavation below subgrade (EBS) • Avoid placing proposed utilities in potential EBS areas • Environmental areas • Utility company many not be aware of arch. sites, historical sites, contaminated sites • Traffic control staging and temporary widening • Poles and pedestals may not be in conflict with final roadway, but might be in conflict with temporary work • Overhead lines vs. construction equipment • Crane should be able to swing 180 degrees without violating OSHA clearances • Lighting and signal bases and poles • May be larger than you expect and often overlooked • Structures • 1:1 slope usually needed from bottom of structure to existing ground for structural backfill • No room to relocate facility • Possibly purchase additional 10 ft of right-of-way for utilities to occupy

  18. Common Construction Conflicts • Field changes • Must notify utility of any changes and give adequate time to design and construct a relocation of their facility • Unknown facilities • Not picked up, survey crew missed it, utility company not aware of facility • Undetected conflicts • Contact utility person listed in the plan • Incorrectly marked facilities • Can cause an extremely dangerous situation • May lead to injury and/or costly delays • Facilities shown on plan incorrectly • Contractor must always call Diggers Hotline

  19. Any Questions?

More Related